Professional Documents
Culture Documents
Hydro One Limited, through its wholly owned subsidiaries, is Ontario’s largest
electricity transmission and distribution provider with approximately 1.5 million
valued customers, approximately $30.4 billion in assets as of December 31,
2021, and annual revenues in 2021 of approximately $7.2 billion. Our team of
approximately 9,300 skilled and dedicated employees proudly build and
maintain a safe and reliable electricity system which is essential to supporting
strong and successful communities. In 2021, Hydro One invested approximately
$2.1 billion in its transmission and distribution networks and supported the
economy through buying approximately $1.7 billion of goods and services.
At the dawn of the 20th century, private companies were developing power
generation facilities along the Niagara River, exploiting the bounty of
hydroelectric potential in the southern region of Canada’s province of Ontario.
In the interest of providing its constituents with a public utility, the government
of Ontario passed the Power Commission Act in 1906, thereby forming the
Hydro-Electric Power Commission of Ontario, which was renamed as Ontario
Hydro in 1970. In the late 1980’s a move toward deregulated energy markets
swept across North America; through the Energy Competition Act, 1998, Ontario
Hydro was restructured into five entities to provide competitive electricity rates
for consumers. One of these five entities, dealing with transmission and
distribution, became Ontario Hydro Services Company (Ontario Hydro), the
predecessor to the modern Hydro One. With close to a hundred years of
history, Hydro One has had an extensive history of protecting transmission lines
and improving its settings philosophy. (Figure 2).
Before 1965
In the early 1900’s, the Hydro-Electric Power Commission of Ontario became one
of the world’s first integrated public electric utilities. It completed the first 110-kV
bulk electric power transmission lines to supply several municipalities in
southwestern Ontario and by 1920, hydro accounted for more than 97% of total
electricity production in Canada.
The first protective relays developed were electromechanical type. These were
Magazine
applied on the Events Areas
utility’s growing
of Interest
transmission News
network.
Advertising
It was in 1928 that the firstPAC World Store
230-kV lines of the province were put into service at 25-Hz. The scheme for
these lines employed balanced-beam impedance relays which were designed
and manufactured in house. In this scheme, two sets of impedance relays were
employed (one for phase and one for ground), supervised by directional
overcurrent elements. To account for metering error in the instrument
transformers, two tripping zones were used: an instantaneous underreaching
Zone 1, and a time-delayed overreaching Zone 2 (acting also as a protection
backup). Phase relays were yet unable to discriminate between phase-phase
and three-phase faults and had to be set accordingly. Ground relays, prior to the
development of zero-sequence compensation, were set based online
impedance with a much-added reach for Zone 2.
Emerging from the Great Depression, in 1938, more 230-kV lines were put into
service in southern Ontario. Communication media, in the form of power line
carrier, were installed to support a permissive overreaching transfer trip scheme
on these lines, increasing dependability. A decade later the grid began to
standardize to a 60-Hz frequency, and a sweeping effort to replace the 25-Hz
protection system began.
As the
Hydro-
Electric
Power
Commis
sion of
Ontario
began
Magazine Events Areas of Interest News Advertising
interco PAC World Store
nnectin
g its 230-kV network with the United States for the purposes of creating the
northeastern grid to improve reliability, constraints in Zone 2 as a conventional
backup were revealed. To address this, Zone 3 relays (timed at 3 seconds) were
introduced with a very high reach all the way over to the line ends of circuits
adjacent to the remote terminal breaker. Consequently, the risk of load
conditions encroaching into the phase Mho characteristic increased. (Figure 4).
This risk was unfortunately realized on a cold November day in 1965, when a
line in the Niagara region was overloaded and a Zone 3 remote backup tripped.
After the loss of the line, other loaded lines at the substation also tripped on
Zone 3, leading to a cascading blackout that spilled into the northeastern United
States, including New York City where restoration efforts took up to two days.
To address the security risk, blinders were added to the Zone 3 characteristic to
block load encroachment. This solution was not without its limitations in an
increasingly complex network. The 1965 blackout and its political repercussions
served as an important juncture in the story of the utility’s protection
philosophy, triggering new protection standards and an era where modern
communications began to be used for remote end breaker failure. Protection
would be duplicated in 2 packages, designated ‘A’ group and ‘B’ group – each
identical in function, fully self-contained and independent of the other.
Direct underreaching transfer trip (DUTT) via microwave or power line carrier
(PLC) was embraced as a standard scheme for 230-kV lines. A local Zone 1 trip
initiates breaker failure and automatic reclosure, and transfer trip is transmitted
to the remote line end. Receival of a transfer trip signal from the remote end
would initiate a local trip, breaker failure and automatic reclosure.
In a simple 2-terminal DUTT application, for a fault occurrence at 50% of the line
where Zone 1’s overlap, the fault is cleared instantaneously. Near the line ends
where only one Zone 1 sees the fault and transfer trips to the other end, the
fault clearing time would take slightly more time for the channel delay.
The POTT scheme via microwave was adopted as the standard for most 230-kV
lines in southern Ontario. In the POTT scheme, if local Zone 2 (set to ~125% of
line impedance) picks up, it will transmit a permissive signal to the remote line
end. If it receives a permissive signal from the remote end, and it detects a fault,
it will trip immediately. In addition, it will initiate breaker failure and automatic
reclosure and send a transfer trip to the remote line end. Should the remote line
end be open when the local end keys permission, the permissive signal would
be echoed back to local. (Figures 5, 6).
In the DCB scheme via either microwave or PLC, Zone 2 elements wait 50-ms for
a blocking signal to be received from the remote end. If no block is received by
the elapsed time, it will trip locally, initiating breaker failure and automatic
reclosure, and send a transfer trip. If a block is received, the relay will not trip. If
local Zone 3 reverse-facing elements pick up, it will transmit a blocking signal to
the remote end. Zone 3 reach is set to the overreach of the remote Zone 2 of
the neighboring system plus a margin (typically 10%) to ensure blocking of
remote Zone 2 for out of zone faults (Figure 7).
In the early
Magazine 1970s, the problem
Events of high-impedance
Areas of Interest faults
Newscaught
the attention of PAC World
Advertising Store
the public as well as that of protection engineers at the newly minted Ontario
Hydro. The utility had a unique interest in the consequences of open phase due
to the architecture of its system. While elsewhere, generation is typically spread
out over a large geographic area and connected to the grid at multiple nodes,
Ontario Hydro interfaces with large concentrations of generation found close to
each other. This exposes a high amount of generation to the risk of being
shaken off for a single open phase.
One of Ontario Hydro’s most innovative developments of this era was high
resistance open phase (HIROP) protection (ANSI device code 97N), which served
two functions: the detection of an open phase, and the detection of a high
resistance fault.
The Ontario system is solidly grounded, such that zero-sequence current will
flow in all cases (excluding radial lines). Furthermore, there was no line where an
open phase would not result in at least twice as much zero-sequence current on
the line with the open phase than on any other line in the system.
This would enable selective operation and isolation of the open phased element
at the affected terminal since the relay at this terminal would operate first.
Coordination was achieved by having all relays use the exact same pickup, time
dial and curve. The minimum pickup of the overcurrent was based on a balance
between the maximum natural unbalance current on the transmission lines, and
the zero-sequence current as it is directly related to the pre-open phase load
current. As
Magazine
some 500-kV
Events
lines had aofnatural
Areas unbalance
Interest
as high
News
asAdvertising
175-A, it was PAC World Store
decided to use a pickup of 360-A (twice the unbalance with some margin) for all
relays. A time dial of 0.5 and the IEC Curve ‘A’ ensured the open phase
protection would never operate before line protection.
Yet for high magnitude high resistance ground faults that could not be detected
by the ground distance relays, coordination could not be ensured (Figure 8).
In adopting IEDs, Hydro One made a conscious decision to disable native relay
logic in favor of programming its own unique logic which matched the existing
setting philosophy. In addition, consistent input and output signals were used,
meaning that regardless of the relay model, the wiring and operation remained
standard.
IEDs brought innumerable benefits for the design and installation of protection
systems. A single
Magazine IED could
Events
replace theInterest
Areas of functions
of several
News electromechanical
Advertising PAC World Store
relays that formerly took up more space on the rack mount.
With IEDs in 1999, directional ground instantaneous overcurrent elements could
be included in the POTT/DCB schemes at no additional cost. This addressed the
limitation with HIROP and meant that all high resistance ground faults down to
only 2-kA could be detected. As a result, the high set instantaneous elements
that were in place on longer lines were phased out.
In 2009, Hydro One began to connect distributed generation onto existing high
voltage lines, adding a layer of complexity from a protection perspective. Prior to
this moment, generation would supply energy to a major bus at a terminal
station. Now, generators directly supplied energy onto long transmission lines
across multiple locations.
The logic of POTT and DCB would also require adjustment to accommodate the
terminals involved in the scheme. For POTT, a permissive signal would need to
be received from all remote ends before initiating local tripping to ensure that
the fault is seen by all ends and was therefore in zone (AND-gate). For DCB, if a
blocked signal was received from any line end, it should then inhibit local
tripping as the Zone 2 could be overreaching any one of the remote terminals
(OR-gate).
Future
Most local distribution companies in Ontario have adopted its principles. These
requirements play an important role in protecting DERs, where protections
cannot determine if undervoltages are due to an in-zone fault or transients
elsewhere in the system. The implementation of transfer trip with DERs allows
faults to be cleared in these scenarios in a timely manner without adverse
effects on a larger base of customers.
Disclaimer: Any opinions expressed in this article are those of the authors and
do not necessarily reflect the views and opinions of Hydro One. Hydro One will
not be liable or be held responsible for any consequences of the use of, or
reliance on the information contained in this article.
Biographies:
Magazine Daniyal
EventsQureshi
Areas of Interest
is a Protection News
& Control
at Advertising
Officer Hydro One PAC World Store
Networks Inc. He specializes in protection system modelling in
industry-standard software, studies for the purposes of compliance,
and the development of automated solutions for analysis and reporting.
Through Daniyal’s prior experience as a consultant, he has contributed to relay
coordination and sensitivity evaluation tools for numerous utilities across North
America. Daniyal regularly authors conference papers and holds a Bachelor of
Applied Science degree in Electrical Engineering from the University of Toronto.
Daniyal loves reading and has a passion for Classical languages, world history
and paleontology. In his spare time, he enjoys horse-riding, travelling, and
writing.