Professional Documents
Culture Documents
Comments Sheet
Comments Sheet
SUBJECT/TITLE : MS for SBS Modified Bituminous Sheet Waterproofing Works ORIGINATOR : ELM / Waterseal
DOCUMENT REF.
: M-DT-MS-071352.16-ST-008 REVISION NO. : B
NO
Sl.
Comments Contractor Response / Consultant & Engineers Comments
No.
Contractor to provide / incorporate the following and re- submit for approval.
Employer PMC Lead Design/Engineer Contractor
Sl.
Comments Contractor Response / Consultant & Engineers Comments
No.
The submitted MS should be submitted through specialized subcontractor not from Main
01 Prepared and stamped by subcontractor
contractor only.
Employer PMC Lead Design/Engineer Contractor
Sl.
Comments Contractor Response / Consultant & Engineers Comments
No.
With reference to (6.1 Site Planning & Preparation): Please clarify point (C) regarding the Noted and removed as not required. Page No. 9
02
protective mortar layer.
03 With reference to 6.2 Work Methodology: Contractor needs to differentiate the application Noted and updated at page No. 9 & 10
in 2 Parts:
a. The horizontal membrane installed at site: application of the 1 st layer with proper
overlapping, then application of the 2nd layer with proper overlapping, lapping
needs to be minimum 10cm.
Employer PMC Lead Design/Engineer Contractor
Sl.
Comments Contractor Response / Consultant & Engineers Comments
No.
b. The vertical membrane installed at precast factory: application of the 1 st layer with
proper overlapping, then application of the 2nd layer with proper overlapping,
lapping needs to be minimum 10cm.
04 Please clarify the termination details of the horizontal and vertical layers. Noted and updated at page No. 9 & 10
Employer PMC Lead Design/Engineer Contractor
Sl.
Comments Contractor Response / Consultant & Engineers Comments
No.
06 Please see the comments on the Method statement in ITP section. Noted and updated
Employer PMC Lead Design/Engineer Contractor
Sl.
Comments Contractor Response / Consultant & Engineers Comments
No.
07 Please specify the location of its usage. Updated, Point 6.2 at page No. 9
08 5. HSE Requirements – this section should be specific to the activity Updated, Point 5 at page no. 7 & 8
Sl.
Comments Contractor Response / Consultant & Engineers Comments
No.