You are on page 1of 2

INSPECTION AND TEST PLAN

PROJECT NAME/NO.: CORDOBA (PHASE 1) AT BLOOM LIVING, ZAYED CITY, ABU DHABI - MAIN WORKS PACKAGE

EMPLOYER: BLOOM DISTRICT PROPERTIES CONTRACTOR: Emirates Link Maltauro LLC

ENGINEER: DAR AL-HANDASAH CONSULTANT SUB-CONTRACTOR:

Doc. Submittal Reference: Rev. No.: B

Description: Substructure SBS Modified Bituminous Sheet Waterproofing Works Works. Date: 20/03/2023
INSPECTION POINT
QUALITY INSPECTIONS REFERENCES
PROCESS CONTROL FORMS
SN FREQUENCY OF TEST (Mode of ACCEPTANCE CRITERIA (SPECIFICATION, METHOD
DESCRIPTION DATA SUB
measurement) STATEMENTS, OTHERS) COMPANY CONSULTANT CONTRACTOR TPI
CONTRACTOR

A Preliminary work / Document Review


1 Relevant Authority Requirements
1.1 NOC’s and permits Once at start of the project Relevant Authority As per Project As per requirements Authority Approval S R S

2 Shop Drawing & Method Statement Submittal


Specification Section #
2.1 Shop Drawings Once at start of the project Review Shop Drawings As per IFC / ADM DWG
07135.16
Check & Review R H/A R S
As per Project Specification Section #
2.2 Method Statement Once at start of the project Review Method Statement
Specifications 07135.16
Review R W/H S S

3 Material Submittal & Approval


Witness & Checked by
Compliance as per Specification Section # Engineer's for
3.1 ELASTOCOL WB Once at start of the project Material Approval Request
Specification 07135.16 preparation,mixing &
S W/A R S
application
Witness & Checked by
Compliance as per Specification Section # Engineer's for
3.2 SOPRALENE FLAM 180 4P20 Once at start of the project Material Approval Request
Specification 07135.16 preparation,mixing &
S W/A R S
application
Witness & Checked by
Compliance as per Specification Section # Engineer's for
3.3 SOPRABOARD SF Once at start of the project Material Approval Request
Specification 07135.16 preparation,mixing &
S W/A R S
application
4 Third Party Qualification Submittal & Approval (as required)
Sub-Contractor/Supplier Review and Submit Min 5 Years Experience in Specification Section # Review Prequalification
4.1 Prequalification
Once at start of the project
Prequalification Documents UAE or as per Vendor List 07135.16 Documents
R A R S

B Material Receiving Inspection and Testing


5 Material Inspection and Testing
ELASTOCOL WB Delivery Note &
Once required material at Compliance as per Specification Section #
5.1 SOPRALENE FLAM 180 4P20
site
Material Approval Request
Specification 07135.16
preparation,mixing & S W/A R S
SOPRABOARD SF application
C Construction Phase
6 Activity 1 (according to the subject)
Drawings / Layout as per Specification Section #
6.1 Surface Preparation for Substructure For each element Visual Check
Dwgs 07135.16
Checked S A R S
Specification Section #
6.2 1st Layer For each element WIR As per approved material
07135.16
Checked S A R S
Specification Section #
6.3 2nd Layer For each element WIR As per approved material
07135.16
Checked S A R S
Specification Section #
6.4 Termination For each element WIR As per approved material
07135.16
Checked S A R S

AD20164-0200S-FM-17 REV 00 1
INSPECTION AND TEST PLAN

PROJECT NAME/NO.: CORDOBA (PHASE 1) AT BLOOM LIVING, ZAYED CITY, ABU DHABI - MAIN WORKS PACKAGE

EMPLOYER: BLOOM DISTRICT PROPERTIES CONTRACTOR: Emirates Link Maltauro LLC

ENGINEER: DAR AL-HANDASAH CONSULTANT SUB-CONTRACTOR:

Doc. Submittal Reference: Rev. No.: B

Description: Substructure SBS Modified Bituminous Sheet Waterproofing Works Works. Date: 20/03/2023
INSPECTION POINT
QUALITY INSPECTIONS REFERENCES
PROCESS CONTROL FORMS
SN FREQUENCY OF TEST (Mode of ACCEPTANCE CRITERIA (SPECIFICATION, METHOD
DESCRIPTION DATA SUB
measurement) STATEMENTS, OTHERS) COMPANY CONSULTANT CONTRACTOR TPI
CONTRACTOR

Specification Section #
6.5 Protection Board For each element WIR As per approved material
07135.16
WIR S H/A R S

D Post Construction Activities


7 Closeout Document Submittals
Review As Built Drawings & Specification Section #
7.1 As built records Once handover the project
Approval
As per site / As Built DWG
07135.16
Check & Review S H/A R S

LEGENDS: W – Witness H – Hold R – Review A – Approval S – Surveillance TPI – Third Party Inspection Agency

AD20164-0200S-FM-17 REV 00 2

You might also like