ITP - FOR SBS Modified Bituminous Sheet Waterproofing Works
ITP - FOR SBS Modified Bituminous Sheet Waterproofing Works
PROJECT NAME/NO.: CORDOBA (PHASE 1) AT BLOOM LIVING, ZAYED CITY, ABU DHABI - MAIN WORKS PACKAGE
Description: Substructure SBS Modified Bituminous Sheet Waterproofing Works Works. Date: 20/03/2023
INSPECTION POINT
QUALITY INSPECTIONS REFERENCES
PROCESS CONTROL FORMS
SN FREQUENCY OF TEST (Mode of ACCEPTANCE CRITERIA (SPECIFICATION, METHOD
DESCRIPTION DATA SUB
measurement) STATEMENTS, OTHERS) COMPANY CONSULTANT CONTRACTOR TPI
CONTRACTOR
AD20164-0200S-FM-17 REV 00 1
INSPECTION AND TEST PLAN
PROJECT NAME/NO.: CORDOBA (PHASE 1) AT BLOOM LIVING, ZAYED CITY, ABU DHABI - MAIN WORKS PACKAGE
Description: Substructure SBS Modified Bituminous Sheet Waterproofing Works Works. Date: 20/03/2023
INSPECTION POINT
QUALITY INSPECTIONS REFERENCES
PROCESS CONTROL FORMS
SN FREQUENCY OF TEST (Mode of ACCEPTANCE CRITERIA (SPECIFICATION, METHOD
DESCRIPTION DATA SUB
measurement) STATEMENTS, OTHERS) COMPANY CONSULTANT CONTRACTOR TPI
CONTRACTOR
Specification Section #
6.5 Protection Board For each element WIR As per approved material
07135.16
WIR S H/A R S
LEGENDS: W – Witness H – Hold R – Review A – Approval S – Surveillance TPI – Third Party Inspection Agency
AD20164-0200S-FM-17 REV 00 2