Number:584186777088).
5. Substandard support.
6. PSV failure.
1. Hydro test test Area shall be barricaded and provide warning boards
to prevent personnel entry.
10. There shall be at least two pressure gauges, one at lowest point and
another at the highest point in the system
11. Hydro testing crew should not stay in the direction of the blind
flanges to prevent injury in case of flange rapture.
14. Personnel shall not approach the system under high Pressure.
15. Only essential and trained persons shall be allowed at the Hydro
test work location
18. Risk assessment shall be done for any hydro test job.