Safety, Health & Environment Risk Assessment
Project Name SICAST Main Contractor GULF BUILDER Reference BLOCK WORK
Project no. GB-20-23 Subs N/A Date 19-Aug-23
Client SICAST Assessor's Name ASIF ALI Signature
✘ Initial Review
Location SUDHAIR RIYADH Task BLOCK WORK Risk assessment type
Risk assessment Risk assessment
(after controls)
(before controls)
Hazards Who affected How affected Controls to be implemented
Risk factor
Risk factor
Likelihood
Likelihood
Risk Level
(check all that apply)
Severity
Severity
Risk level
All the access and egress should be clear from all kind of
Slips trips or Falls hazards,the workers maybe affected obstruction. Store the materials on proper way. Un wanteed
Workers involve in
Access /Egress due to the improper storage materials, skatered tools, 3 4 12 12 materials should be removed immediately. No entry for the 3 1 3 3
activity
poor housekeeping. Not clear the access and egress vehicles to the working area.Wear proper PPE before entering
to the working area.
All workers to be instructed not to carry materials up by hand.
Workers involve in Operators risk injury, particularly to the back, from lifting
Handling & Laying of Blocks 2 3 6 6 2 1 2 2
activity and handling heavy objects.
Good manual handling practices be adopted.
Risk from dry cement / grout powder which may irritate
Workers involve in Goggles, safety gum boots, dust mask, cover all and gloves
Mixing & Filling of Mortar/Grout eyes or sensitive skin, or cause short-term irritation of 2 3 6 6 2 1 2 2
activity must be worn.
respiratory system
All protruding rebar's must be protected by rebar's box or cap.
Workers involve in Dust mask, face shield and gloves must be worn.
Installation of Steel Components Serious hand or body injury 3 2 6 6 3 1 3 3
activity
Proper housekeeping must be obatined.
Workers involve in
Cutting or Grinding of Blocks Serious eye, head or hand injury 4 3 12 12 Euipment inspection and color coding. 4 1 4 4
activity
Safety harness must be worn at all the time when work at
hieght. Scaffolding should be constructed by there basic
Serious or even fatal injury could occur if a operator requirements mid rail, top rail, ladder & ets . Before starting any
Working at Height (Scaffolding) Worker, scaffolders 4 4 16 16 4 1 4 4
falls from height. Others working below also at risk work on scaffolding checked the tagging system , use safety
harness double laneyard , take permit before starting the
work , barricade the area of scaffolding
Page 1 of 2
Document Reference Number: ORG1-06-002-MOD-TS0-0-PRM-TEM-2960-00
Revision Number: 00
Date: 05 January 2020
Risk assessment Risk assessment
(after controls)
(before controls)
Hazards Who affected How affected Controls to be implemented
Risk factor
Risk factor
Likelihood
Likelihood
Risk Level
(check all that apply)
Severity
Severity
Risk level
Goggles, safety gum boots, dust mask, cover all and gloves
must be worn.
Workers involve in Serious Hand, eye and skin Irritation could occur if a
Plastering 3 3 9 9 3 1 3 3
activity operator contineusly contact with concrete mix
Availabilty of eye wash in case of eye
contamination.
The area need to be cleaned properly all time Always keep
slips, trips and falls can happened due to the poor clear access and egress from obstruction Store all the
Workers involve in
Housekeeping house keeping and bad storage management system, 3 2 6 6 materials when not in use ,Remove the scrap materials from 3 1 3 3
activity
Serious bodily injury can happen. the site before start the work and after completing the work do
area housekeeping . Materials should be properly stored.
Workmen are EHS inducted & trained, Material to be shifted
through Pick up & carry crane or telehandler by using proper
Workers involve in lack of supervison and lack of campatency , lack of lifting plan ,Availability of competent riggers &
loading & unloading pallets of block 3 3 9 9 2 2 4 4
activity barrication , lack of signages lack of flagman signalmen ,Availability of tagline must be ensured ,Materials
are kept near the reach of the workmen, Periodical rest is
provided to workmen
provide training to workers how to manage the
work in adhesive weather , after constructing any
falling of new constructed wall due to heavy Workers involve in wall provide the strong support to wall for 24 hours
Injury to person , property damage 3 3 9 9 2 2 4 4
wind activity don’t allow any antother work under the new
constructed wall , don’t take any support from new
constructed wall
stop all Heightwork if the wind reached
32km/h , stop all Scaffolding work if there is
poor visibility of sand storm or fog untill HSE
Worker, Sub Due to sand storms, dust or fog workers/ visitors
department give the green signal to resume
Adverse Weather Conditions Contractor, Visitors. might suffer from lungs issues which leads to 3 3 9 9 2 2 4 4
Etc. the work Provide a shelter for personnel to
serious injury or death.
stay in case of adverse weather conditions.
Provide and use dust mask in case of
sand/dust storm.
Risk factor method Severity Likelihood Notes
Severity
1 2 3 4 5 Risk level 1 - No potential for injury, illness, or incident 1 - Very Unlikely
Likelihood
2 4 6 8 10 Low 2 - Potential for minor injury, illness, or incident 2 - Unlikely
3 6 9 12 15 Medium 3 - Potential for a recordable injury, illness, or incident 3 - Likely
4 8 12 16 20 High 4 - Potential for major incident, or major injury or illness causing short term disability 4 - Very Likely
5 10 15 20 25 5 - Potential for major incident, or major injury or illness causing a fatality or long term disability 5 - Certain
Page 2 of 2