Professional Documents
Culture Documents
2.
a) Plot the mass diagram for the earthwork quantities contained in the accompanying table. The
initial ordinate has been arbitrarily set at 5000 m3.
b) Calculate the total earthwork costs for this project using the following data.
• Free haul distance= 300 m
• Excavation costs (including 300 m free haul) = $5.00 /m3.
• Borrow (including cost of hauling)= $10.50/m3.
• Cost of overhaul= 7.00/sta-m.
• Cost of waste is included in cost of excavation
5. For an urban road with a rectangular side drain the maximum quantity of water expected
is 1.8m3/sec. the side drain is a smooth concrete with a manning roughness coefficient of
0.012 and an assumed base width of 1.0m. the allowable velocity of flow in the drain is
0.6m/sec. design the cross section and longitudinal slope.
6. A rural highway which we want to construct the roadway with asphalt bituminous surface and the
drainage structures with concrete and one cross section as shown in the figure. The properties
around the road are
• The catchment area which contribute for the one side ditch is 3.0 km2 covered with grass and
0.5 km2 covered with cultivated fields in addition to 1km stretch of the asphalt surface and
there is 30mm/hr rainfall intensity around the area
• The hydraulic channel will have 0.5% longitudinal flat slope and the carriageway will have
2% crown slope.
Determine
a. The peak discharge around the ditch
b. The best hydraulic section to accommodate the peak discharge
7. The surface water from road side is drained to the longitudinal side drain
from across one half a bituminous pavement surface of total width 7.0 m,
shoulder and adjoining land of width 8.0 m one side of the drain. On the
other side of the longitudinal drain, water flows across from reserved land
with grass and 2% cross slope towards the side drain, the width of this strip
of land being 25 m. The run off coefficients of the pavement, shoulder and
reserve land with grass surface are 0.8, 0.25, and 0.35 respectively. The
length of the stretch of land parallel to the road from where water is
expected to flow to the side drain is about 400 m. Estimate the quantity of
run-off flowing in the drain assuming 25 years period of frequency. Assume
the project is on A1 region.