January 12 up to 19 Excavation phase one Digging the ground for basement up to 5 meter January 20 Leveling surface Excavate and level the surface for footing pads January 21&22 Lean concrete Lean concert for footing pad CF3,CF4 CF1,SF1,SF2,SF3 AND SF4 January 23 up to 25 FORM WORK Form work for footing pad CF3,CF4 CF1,SF1,SF2,SF3 AND SF4 January 26 up to April 2 Re-bar Re-bar for CF3,CF4 CF1,SF1,SF2,SF3 , SF4 , column and shear wall April 3 up to 4 Concrete work for footing Concrete work for CF3,CF4 pad CF1,SF1,SF2,SF3 AND SF4 April 5 Leveling and lean concrete for grade beam April 6 Form work for grade beam April 7 Concrete for grade beam April8 up to 14 Form work Form work for retaining wall and for columns April 15 up to 17 Concrete work Concrete work for retaining wall and columns April 18 up to 28 Back fill Excavate phase 2 and back fill April 29 up to may 3 Excavation Excavate phase two for shear wall one and for footing pad two(2) may 4 &5 Leveling and lean concrete For CF2 AND SW1 May 6 up to may9 Re-bar CF2&SW1 May 10& Concrete work Concrete work for CF2&SW1