Work schedule

Date Types of work Amount of work


January 12 up to 19 Excavation phase one Digging the ground for
basement up to 5 meter
January 20 Leveling surface Excavate and level the
surface for footing pads
January 21&22 Lean concrete Lean concert for footing
pad
CF3,CF4 CF1,SF1,SF2,SF3
AND SF4
January 23 up to 25 FORM WORK Form work for footing pad
CF3,CF4 CF1,SF1,SF2,SF3
AND SF4
January 26 up to April 2 Re-bar Re-bar for CF3,CF4
CF1,SF1,SF2,SF3 , SF4 ,
column and shear wall
April 3 up to 4 Concrete work for footing Concrete work for CF3,CF4
pad CF1,SF1,SF2,SF3 AND SF4
April 5 Leveling and lean concrete
for grade beam
April 6 Form work for grade
beam
April 7 Concrete for grade beam
April8 up to 14 Form work Form work for retaining
wall and for columns
April 15 up to 17 Concrete work Concrete work for
retaining wall and columns
April 18 up to 28 Back fill Excavate phase 2 and
back fill
April 29 up to may 3 Excavation Excavate phase two for
shear wall one and for
footing pad two(2)
may 4 &5 Leveling and lean concrete For CF2 AND SW1
May 6 up to may9 Re-bar CF2&SW1
May 10& Concrete work Concrete work for
CF2&SW1