Time Window
Project Title Area Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 from Syn Scope
from Required
Trip(hr)
Furnace (hr)
Fire(hr)

Furnace Fire
12 24 36 48 60 68 72 84 96 108 114 120 126 132 144 146 156 168 180 192 196
NRV Installation on Hydrogen Line Amm-3 74 Hours 72 20 36 Dummy Spool Piece to be Removed and NRV to be Installed.

Ammonia Production
E-510 CWR Valve Replacement Amm-3 28 Hours 68 -30 24 Gate Valve to be replaced with Globe Valve
Syn Trip

LNG Line Tie-In Amm-3 36 Hours 60 -30 36 Tie-Ins for LNG Line (By Pass Scope Senior Orifice)
CO2 Integration Urea-3 102 Hours 12 -12 96 Permanent Scope Tie-Ins
TR Scope : Strainer Installation at FT-1011 Urea-3 66 Hours 48 -12 12 Dummy Spool Piece to be Removed and Strainer to be Installed.
Encop-3 Trim Cooler Tie-Ins UTY-1 72 Tie-Ins for Trim Cooler on K-901-C
Fuel Gas NRV 48