You are on page 1of 8

KIRSKAT VENTURE

Manila Office: Unit 712B Tower-B The Regalia Park Towers 150 P. Tuazon Ave, Cubao, Quezon City
Landline: 0287765788
Email: kirskatventure.manila@gmail.com

May May June June June


Project Schedule Based on Actual
SCOPE Weight Week -01 Week -02 Week -03 Week -04 Week -05
Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Item No Description Duration
27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

27-May-23 28-May-23 29-May-23 30-May-23 31-May-23 1-Jun-23 2-Jun-23 3-Jun-23 4-Jun-23 5-Jun-23 6-Jun-23 7-Jun-23 8-Jun-23 9-Jun-23 10-Jun-23 11-Jun-23 12-Jun-23 13-Jun-23 14-Jun-23 15-Jun-23 16-Jun-23 17-Jun-23 18-Jun-23 19-Jun-23 20-Jun-23 21-Jun-23 22-Jun-23 23-Jun-23 24-Jun-23 25-Jun-23 26-Jun-23 27-Jun-23 28-Jun-23

0 General Requirement 178.00 G 3.68% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%
1 Wall Framing Work 67.00 AR 5.55% 0.148453% 0.258213% 0.133707% 0.43760% 0.67788% 0.5741%
2 CHB laying 60.00 AR 4.97% 0.571013% 0.999427% 0.878800% 0.99995% 1.35041% 0.96095%
3 Approval for approved plan for construction (floor plan) 1.00 AR 0.08%
4 Mock up of soil pipe slope (2nd Floor) 3.00 AR 0.25%
5 Rebar Scanning 7.00 AR 0.58%
6 Approval of Mechanical Plan (Shop Drawing) 7.00 AR 0.58%
7 Plastering works 15.00 AR 1.24%
8 Approval of Reflected Ceiling plan (with final elevations) 15.00 AR 1.24%
9 Approval of Shop Drawing of Coring works location 15.00 AR 1.24%
10 Approval of Electrical Plan and Auxillary Plan (Shop Drawing) 15.00 EE 2.15%
11 Approval of Shop Drawing for treatment of boundary walls 15.00 EE 2.15%
12 Installation Wall board Installation (One side) 22.00 AR 1.82%
13 Concrete neutralizer application 7.00 AR 0.58%
14 Coring Works 7.00 P 0.39%
15 Electrical rough-in/Conduit and Wiring Installation (Splicing) 14.00 EE 2.01%
16 Auxiliary rough-in 14.00 AU 2.15%
17 FDAS rough-in 14.00 AU 2.15%
18 Application of skimcoat 24.00 AR 1.99%
19 Ducting Installation 18.00 M 2.48%
20 Ceiling Framing 18.00 AR 1.49%
21 Application of primer 16.00 AR 1.33%
22 Sanitary layout 18.00 P 1.01%
23 Treatment of boundary walls 11.00 AR 0.91%
24 HVAC Stub Out 21.00 M 2.90%
25 Fire protection layout/piping 21.00 F 0.91%
26 Floor topping/Screeding 14.00 AR 1.16%
Electrical rough-in/above ceiling works and Wiring Installation
27 21.00 EE 3.02%
(Splicing)
28 Water line layout 21.00 P 1.18%
29 General floor topping or screeding 21.00 AR 1.74%
30 Electrical rough-in wall toilets and Wiring Installation (Splicing) 17.00 EE 2.44%
31 HVAC line/Condenser line 17.00 M 2.35%
32 HVAC rough-in 17.00 M 2.35%
33 Installation of wall boards (Enclosed) 21.00 AR 1.74%
34 Waterproofing 14.00 AR 1.16%
35 Layout of tiles works 15.00 AR 1.24%
36 Water leak test 14.00 AR 1.16%
37 Demolition Work 10.00 AR 0.83%
38 Ceiling board installation 21.00 AR 1.74%
39 Tiles Installation 21.00 AR 1.74%
40 Sprinkler Head Installation 22.00 AR 1.82%
41 Outdoor unit of ACU 22.00 M 3.04%
42 Installation of plumbing fixtures 22.00 P 1.23%
43 Installation of door jamb 22.00 AR 1.82%
44 Installation of window 16.00 AR 1.33%
45 Application of Second coat 19.00 AR 1.57%
46 Installation of electrical fixtures and accessories 16.00 EE 2.30%
47 Installation of auxiliary 14.00 AU 2.15%
48 Installation of FDAS 14.00 AU 2.15%
49 Testing and commissioning of Fire protection 8.00 F 0.35%
50 Painting works top coat 14.00 AR 1.16%
51 Installation of doors 14.00 AR 1.16%
52 Installation of ACU indoor unit 14.00 M 1.93%
53 Fixed furniture Installation 14.00 AR 1.16% 8.72% 8.72% 8
54 Installation of door System 14.00 AU 2.15% 7.06%
55 Intercom System 14.00 AU 2.15%
4.91%
56 Installation of Loose furniture 14.00 AR 1.16%
57 Site clearing works 18.00 G 0.37% 3.35%
2.22%
58 Repainting work or Retouching 11.00 G 0.23%
0.84%
59 Cleaning 15.00 G 0.31% 0.00% 0.00%
0.00% 0.00% 0.00%
60 Turnover request 14.00 G 0.29% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00%
0.00% 0.00% 0.00%
61 COC filling 14.00 G 0.29% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00%
62 Pullout/Demobilization 8.00 G 0.17% 0.00% 0.00% 0.00% 0.00%
63 Ribbon cutting 3.00 G 0.06%
TOTAL 100.00%
PROJECTED ACCOMPLISHMENT 0.02% 0.02% 0.02% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%
PROJECTED CUMMULATIVE 0.02% 0.04% 0.06% 0.25% 0.44% 0.63% 0.82% 1.01% 1.20% 1.39% 1.58% 1.77% 1.96% 2.15% 2.34% 2.53% 2.72% 2.91% 3.10% 3.29% 3.48% 3.67% 3.86% 4.05% 4.24% 4.43% 4.62% 4.81% 5.00% 5.19% 5.38% 5.57% 5.76%
ACTUAL ACCOMPLISHMENT 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.84% 1.38% 1.13% 1.56% 2.15% 1.66% 0.00%
ACTUAL CUMMULATIVE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.84% 2.22% 3.35% 4.91% 7.06% 8.72% 8.72%
DEVIATION -0.02% -0.04% -0.06% -0.25% -0.44% -0.63% -0.82% -1.01% -1.20% -1.39% -1.58% -1.77% -1.96% -2.15% -2.34% -2.53% -2.72% -2.91% -3.10% -3.29% -3.48% -3.67% -3.86% -4.05% -4.24% -4.43% -3.78% -2.59% -1.65% -0.28% 1.68% 3.15% 2.96%
KIRSKAT VENTURE
Manila Office: Unit 712B Tower-B The Regalia Park Towers 150 P. Tuazon Ave, Cubao, Quezon City
Landline: 0287765788
Email: kirskatventure.manila@gmail.com

June July July July July July - August


Project Schedule Based on Actual
Week -05 Week -06 Week -07 Week -08 Week -09 Week -10
Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Item No Description Duration
29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02

29-Jun-23 30-Jun-23 1-Jul-23 2-Jul-23 3-Jul-23 4-Jul-23 5-Jul-23 6-Jul-23 7-Jul-23 8-Jul-23 9-Jul-23 10-Jul-23 11-Jul-23 12-Jul-23 13-Jul-23 14-Jul-23 15-Jul-23 16-Jul-23 17-Jul-23 18-Jul-23 19-Jul-23 20-Jul-23 21-Jul-23 22-Jul-23 23-Jul-23 24-Jul-23 25-Jul-23 26-Jul-23 27-Jul-23 28-Jul-23 29-Jul-23 30-Jul-23 31-Jul-23 1-Aug-23 2-Aug-23

0 General Requirement 178.00 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%
1 Wall Framing Work 67.00 0.59966% 0.59966% 0.22% 0.2544% 0.23967% 0.38729% 0.63% 0.21710% 0.20143% 0.04% 0.34243% 0.22682% 0.54546% 0.53490% 0.42415% 0.03591% 0.32913% 0.44296% 0.40271% 0.15925%
2 CHB laying 60.00 0.5487% 0.3432% 0.4376% 0.0267% 0.28660% 0.59329% 0.43630% 0.23193% 0.9988% 0.05% 0.84940% 1.41709% 0.1540% 0.0835%
3 Approval for approved plan for construction (floor plan) 1.00
4 Mock up of soil pipe slope (2nd Floor) 3.00
5 Rebar Scanning 7.00
6 Approval of Mechanical Plan (Shop Drawing) 7.00
7 Plastering works 15.00 2.78574% 0.70612% 0.58674%
8 Approval of Reflected Ceiling plan (with final elevations) 15.00
9 Approval of Shop Drawing of Coring works location 15.00
10 Approval of Electrical Plan and Auxillary Plan (Shop Drawing) 15.00
11 Approval of Shop Drawing for treatment of boundary walls 15.00
12 Installation Wall board Installation (One side) 22.00
13 Concrete neutralizer application 7.00
14 Coring Works 7.00
15 Electrical rough-in/Conduit and Wiring Installation (Splicing) 14.00
16 Auxiliary rough-in 14.00
17 FDAS rough-in 14.00
18 Application of skimcoat 24.00
19 Ducting Installation 18.00
20 Ceiling Framing 18.00
21 Application of primer 16.00
22 Sanitary layout 18.00
23 Treatment of boundary walls 11.00
24 HVAC Stub Out 21.00
25 Fire protection layout/piping 21.00
26 Floor topping/Screeding 14.00
Electrical rough-in/above ceiling works and Wiring Installation
27 21.00
(Splicing)
28 Water line layout 21.00
29 General floor topping or screeding 21.00
30 Electrical rough-in wall toilets and Wiring Installation (Splicing) 17.00
31 HVAC line/Condenser line 17.00
32 HVAC rough-in 17.00
33 Installation of wall boards (Enclosed) 21.00
34 Waterproofing 14.00 29.13%
28.51%
35 Layout of tiles works 15.00
27.64%
36 Water leak test 14.00
37 Demolition Work 10.00 26.41%
25.85%
38 Ceiling board installation 21.00 25.24% 25.40%
39 Tiles Installation 21.00 24.69%
40 Sprinkler Head Installation 22.00
41 Outdoor unit of ACU 22.00
21.17%
42 Installation of plumbing fixtures 22.00 20.35%
43 Installation of door jamb 22.00
18.58%
44 Installation of window 16.00
17.05% 17.27%
45 Application of Second coat 19.00
15.73%
46 Installation of electrical fixtures and accessories 16.00 15.16%
47 Installation of auxiliary 14.00 13.98%
48 Installation of FDAS 14.00 12.88%
12.23%
49 Testing and commissioning of Fire protection 8.00 11.83%
11.05%
50 Painting works top coat 14.00 9.99%
51 Installation of doors 14.00 8.72% 8.72% 8.72%
8.72% 8.72% 8.72%
52 Installation of ACU indoor unit 14.00 8.72% 8.72% 8.72%
8.72% 8.72% 8.72%
8.72% 8.72% 8.72%
53 Fixed furniture Installation 8.72% 8.72%
14.00
54 Installation of door System 7.06% 14.00
55 Intercom System 14.00
56 Installation of Loose furniture 4.91% 14.00
57 Site clearing3.35%
works 18.00
2.22%
58 Repainting work or Retouching 11.00
0.84%
59 Cleaning 15.00
60 Turnover request 14.00
61 COC filling 14.00
62 Pullout/Demobilization 8.00
63 Ribbon cutting 3.00
TOTAL
0.19%
PROJECTED ACCOMPLISHMENT 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.27% 0.19% 0.35% 0.43% 0.52% 0.35% 0.35% 0.66% 0.66% 0.58%
PROJECTED5.95%
CUMMULATIVE 6.14% 6.33% 6.52% 6.71% 6.90% 7.09% 7.28% 7.47% 7.66% 7.85% 8.04% 8.23% 8.42% 8.61% 8.80% 8.99% 9.18% 9.37% 9.56% 9.75% 9.94% 10.13% 10.32% 10.51% 10.78% 10.97% 11.32% 11.75% 12.27% 12.62% 12.97% 13.63% 14.29% 14.87%
0.00%
ACTUAL ACCOMPLISHMENT 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.27% 1.06% 0.78% 0.40% 0.65% 1.10% 1.18% 0.57% 1.32% 0.22% 1.31% 1.77% 0.82% 3.53% 0.55% 0.16% 0.45% 0.56% 1.23% 0.87%
8.72%
ACTUAL CUMMULATIVE 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 8.72% 9.99% 11.05% 11.83% 12.23% 12.88% 13.98% 15.16% 15.73% 17.05% 17.27% 18.58% 20.35% 21.17% 24.69% 25.24% 25.40% 25.85% 26.41% 27.64% 28.51%
DEVIATION
2.77% 2.58% 2.39% 2.20% 2.01% 1.82% 1.63% 1.44% 1.25% 1.06% 0.87% 0.68% 0.49% 0.30% 0.11% 1.18% 2.06% 2.65% 2.86% 3.32% 4.23% 5.22% 5.60% 6.73% 6.76% 7.80% 9.38% 9.85% 12.94% 12.97% 12.77% 12.87% 12.78% 13.35% 13.63%
KIRSKAT VENTURE
Manila Office: Unit 712B Tower-B The Regalia Park Towers 150 P. Tuazon Ave, Cubao, Quezon City
Landline: 0287765788
Email: kirskatventure.manila@gmail.com

July - August August August August August - September September


Project Schedule Based on Actual
Week -10 Week -11 Week -12 Week -13 Week -14 Week -15
Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Item No Description Duration
03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06

3-Aug-23 4-Aug-23 5-Aug-23 6-Aug-23 7-Aug-23 8-Aug-23 9-Aug-23 10-Aug-23 11-Aug-23 12-Aug-23 13-Aug-23 14-Aug-23 15-Aug-23 16-Aug-23 17-Aug-23 18-Aug-23 19-Aug-23 20-Aug-23 21-Aug-23 22-Aug-23 23-Aug-23 24-Aug-23 25-Aug-23 26-Aug-23 27-Aug-23 28-Aug-23 29-Aug-23 30-Aug-23 31-Aug-23 1-Sep-23 2-Sep-23 3-Sep-23 4-Sep-23 5-Sep-23 6-Sep-23

0 General Requirement 178.00 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%
1 Wall Framing Work 67.00 0.16289% 0.02% 0.16237% 0.42392% 0.27%
2 CHB laying 60.00 0.0129% 0.15885% 0.42640% 0.37704% 0.37712% 0.38786%
3 Approval for approved plan for construction (floor plan) 1.00
4 Mock up of soil pipe slope (2nd Floor) 3.00
5 Rebar Scanning 7.00
6 Approval of Mechanical Plan (Shop Drawing) 7.00
7 Plastering works 15.00 0.31760% 0.16413% 0.11040% 0.2767%
8 Approval of Reflected Ceiling plan (with final elevations) 15.00
9 Approval of Shop Drawing of Coring works location 15.00
10 Approval of Electrical Plan and Auxillary Plan (Shop Drawing) 15.00
11 Approval of Shop Drawing for treatment of boundary walls 15.00
12 Installation Wall board Installation (One side) 22.00 0.00487% 3.78086% 0.0751% 0.1243% 0.2084% 0.27473% 0.30969% 0.19990% 0.37%
13 Concrete neutralizer application 7.00
14 Coring Works 7.00
15 Electrical rough-in/Conduit and Wiring Installation (Splicing) 14.00
16 Auxiliary rough-in 14.00
17 FDAS rough-in 14.00
18 Application of skimcoat 24.00
19 Ducting Installation 18.00
20 Ceiling Framing 18.00
21 Application of primer 16.00
22 Sanitary layout 18.00
40.05%
23 Treatment of boundary walls 11.00 39.55%
24 HVAC Stub Out 21.00
38.94%
25 Fire protection layout/piping 21.00 38.23%
26 Floor topping/Screeding 14.00
37.16%
Electrical rough-in/above ceiling works and Wiring Installation 0
27 21.00 36.25%
(Splicing) 35.93% 0
28 Water line layout 21.00 35.50% 0
35.10%
29 General floor topping or screeding 21.00 34.61% 0
30 Electrical rough-in wall toilets and Wiring Installation (Splicing) 17.00 33.99% 0
31 HVAC line/Condenser line 17.00 33.20% 0
32 HVAC rough-in 17.00 0
33 Installation of wall boards (Enclosed) 21.00 0.29186% 0.2027% 0.3758% 0.1102% 0
34 Waterproofing 14.00 29.13%
0
28.51%
35 Layout of tiles works 15.00 0
27.64%
36 Water leak test 14.00 0
26.41% 0
37 Demolition Work 10.00
25.85% 0
3825.24%Ceiling board25.40%
installation 21.00
0
24.69% 39 Tiles Installation 21.00
0
40 Sprinkler Head Installation 22.00
0
41 Outdoor unit of ACU 22.00
0
42 Installation of plumbing fixtures 22.00
0
43 Installation of door jamb 22.00
0
44 Installation of window 16.00 0
45 Application of Second coat 19.00 0
0
46 Installation of electrical fixtures and accessories 16.00 0
47 Installation of auxiliary 14.00
48 Installation of FDAS 14.00
49 Testing and commissioning of Fire protection 8.00
50 Painting works top coat 14.00
51 Installation of doors 14.00
52 Installation of ACU indoor unit 14.00
53 Fixed furniture Installation 14.00
54 Installation of door System 14.00
55 Intercom System 14.00
56 Installation of Loose furniture 14.00
57 Site clearing works 18.00
58 Repainting work or Retouching 11.00
59 Cleaning 15.00
60 Turnover request 14.00
61 COC filling 14.00
62 Pullout/Demobilization 8.00
63 Ribbon cutting 3.00
TOTAL
0.64%
PROJECTED ACCOMPLISHMENT0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.70% 0.70% 1.15% 0.84% 0.92% 0.92% 0.78% 1.20% 1.20% 1.54% 1.63% 1.63% 1.63% 1.63% 1.63% 1.54% 1.09% 1.09% 1.60% 1.60% 1.68% 1.68% 1.68% 1.68% 1.68% 1.37%
PROJECTED15.51%
CUMMULATIVE16.15% 16.79% 17.43% 18.07% 18.71% 19.35% 19.99% 20.63% 21.33% 22.03% 23.18% 24.02% 24.94% 25.86% 26.64% 27.84% 29.04% 30.58% 32.21% 33.84% 35.47% 37.10% 38.73% 40.27% 41.36% 42.45% 44.05% 45.65% 47.33% 49.01% 50.69% 52.37% 54.05% 55.42%
0.62%
ACTUAL ACCOMPLISHMENT 4.08% 0.78% 0.62% 0.49% 0.40% 0.43% 0.32% 0.91% 1.06% 0.71% 0.61% 0.51% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
ACTUAL 29.13%
CUMMULATIVE 33.20% 33.99% 34.61% 35.10% 35.50% 35.93% 36.25% 37.16% 38.23% 38.94% 39.55% 40.05%
DEVIATION
13.61% 17.05% 17.20% 17.18% 17.03% 16.79% 16.58% 16.26% 16.53% 16.90% 16.91% 16.36% 16.03%
KIRSKAT VENTURE
Manila Office: Unit 712B Tower-B The Regalia Park Towers 150 P. Tuazon Ave, Cubao, Quezon City
Landline: 0287765788
Email: kirskatventure.manila@gmail.com

September September September September September - October October


Project Schedule Based on Actual
Week -15 Week -16 Week -17 Week -18 Week -19 Week -20
Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Item No Description Duration
07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11

7-Sep-23 8-Sep-23 9-Sep-23 10-Sep-23 11-Sep-23 12-Sep-23 13-Sep-23 14-Sep-23 15-Sep-23 16-Sep-23 17-Sep-23 18-Sep-23 19-Sep-23 20-Sep-23 21-Sep-23 22-Sep-23 23-Sep-23 24-Sep-23 25-Sep-23 26-Sep-23 27-Sep-23 28-Sep-23 29-Sep-23 30-Sep-23 1-Oct-23 2-Oct-23 3-Oct-23 4-Oct-23 5-Oct-23 6-Oct-23 7-Oct-23 8-Oct-23 9-Oct-23 10-Oct-23 11-Oct-23

0 General Requirement 178.00


1 Wall Framing Work 67.00
2 CHB laying 60.00
3 Approval for approved plan for construction (floor plan) 1.00
4 Mock up of soil pipe slope (2nd Floor) 3.00
5 Rebar Scanning 7.00
6 Approval of Mechanical Plan (Shop Drawing) 7.00
7 Plastering works 15.00
8 Approval of Reflected Ceiling plan (with final elevations) 15.00
9 Approval of Shop Drawing of Coring works location 15.00
10 Approval of Electrical Plan and Auxillary Plan (Shop Drawing) 15.00
0
11 Approval of Shop Drawing for treatment of boundary walls 15.00 0
0
12 Installation Wall board Installation (One side) 22.00 0
0
0
13 Concrete neutralizer application 7.00 0
0
14 Coring Works 7.00 0
0
15 Electrical rough-in/Conduit and Wiring Installation (Splicing) 14.00 0
0
0
16 Auxiliary rough-in 14.00 0
0
17 FDAS rough-in 14.00 0
0
18 Application of skimcoat 24.00 0
0
0
19 Ducting Installation 18.00 0
0
0
20 Ceiling Framing 18.00 0
0
0
21 Application of primer 16.00 0
0
22 Sanitary layout 18.00 0
23 Treatment of boundary walls 11.00 0
0
24 HVAC Stub Out 21.00 0
0
25 Fire protection layout/piping 21.00
0
26 Floor topping/Screeding 14.00 0
Electrical rough-in/above ceiling works and Wiring Installation 0
27 21.00
(Splicing) 0
28 Water line layout 0 21.00
29 General floor topping or screeding 0 21.00
30 Electrical rough-in wall toilets and0 Wiring Installation (Splicing) 17.00
31 HVAC line/Condenser
0 line 17.00
32 0 HVAC rough-in 17.00
0 33 Installation of wall boards (Enclosed) 21.00
34 Waterproofing 14.00
35 Layout of tiles works 15.00
36 Water leak test 14.00
37 Demolition Work 10.00
38 Ceiling board installation 21.00
39 Tiles Installation 21.00
40 Sprinkler Head Installation 22.00
41 Outdoor unit of ACU 22.00
42 Installation of plumbing fixtures 22.00
43 Installation of door jamb 22.00
44 Installation of window 16.00
45 Application of Second coat 19.00
46 Installation of electrical fixtures and accessories 16.00
47 Installation of auxiliary 14.00
48 Installation of FDAS 14.00
49 Testing and commissioning of Fire protection 8.00
50 Painting works top coat 14.00
51 Installation of doors 14.00
52 Installation of ACU indoor unit 14.00
53 Fixed furniture Installation 14.00
54 Installation of door System 14.00
55 Intercom System 14.00
56 Installation of Loose furniture 14.00
57 Site clearing works 18.00
58 Repainting work or Retouching 11.00
59 Cleaning 15.00
60 Turnover request 14.00
61 COC filling 14.00
62 Pullout/Demobilization 8.00
63 Ribbon cutting 3.00
TOTAL
1.37%
PROJECTED ACCOMPLISHMENT1.32% 1.30% 1.30% 1.10% 1.02% 0.94% 0.94% 0.94% 0.71% 0.71% 0.71% 0.63% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.86% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69% 0.64% 0.64% 0.64% 0.68%
56.79%
PROJECTED CUMMULATIVE58.11% 59.41% 60.71% 61.81% 62.83% 63.77% 64.71% 65.65% 66.36% 67.07% 67.78% 68.41% 68.96% 69.51% 70.06% 70.61% 71.16% 71.71% 72.26% 72.81% 73.36% 74.22% 74.91% 75.60% 76.29% 76.98% 77.67% 78.36% 79.05% 79.74% 80.38% 81.02% 81.66% 82.34%
0.00%
ACTUAL ACCOMPLISHMENT 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
ACTUAL CUMMULATIVE
DEVIATION
KIRSKAT VENTURE
Manila Office: Unit 712B Tower-B The Regalia Park Towers 150 P. Tuazon Ave, Cubao, Quezon City
Landline: 0287765788
Email: kirskatventure.manila@gmail.com

October October October October - November November November


Project Schedule Based on Actual
Week -20 Week -21 Week -22 Week -23 Week -24 Week -25
Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Item No Description Duration
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15

12-Oct-23 13-Oct-23 14-Oct-23 15-Oct-23 16-Oct-23 17-Oct-23 18-Oct-23 19-Oct-23 20-Oct-23 21-Oct-23 22-Oct-23 23-Oct-23 24-Oct-23 25-Oct-23 26-Oct-23 27-Oct-23 28-Oct-23 29-Oct-23 30-Oct-23 31-Oct-23 1-Nov-23 2-Nov-23 3-Nov-23 4-Nov-23 5-Nov-23 6-Nov-23 7-Nov-23 8-Nov-23 9-Nov-23 10-Nov-23 11-Nov-23 12-Nov-23 13-Nov-23 14-Nov-23 15-Nov-23

0 General Requirement 178.00 0 0 0 0 0


0 0 0
0 0
1 Wall Framing Work 67.00 0 0 0
0 0
2 CHB laying 60.00 0
0
3 Approval for approved plan for construction (floor plan) 1.00 0
0
4 Mock up of soil pipe slope (2nd Floor) 3.00 0
0
0
5 Rebar Scanning 7.00 0
0
6 Approval of Mechanical Plan (Shop Drawing) 7.00 0
0
7 Plastering works 15.00 0
0
0
8 Approval of Reflected Ceiling plan (with final elevations) 15.00 0
0
9 Approval of Shop Drawing of Coring works location 15.00 0
0
0
10 Approval of Electrical Plan and Auxillary Plan (Shop Drawing) 15.00 0
0
11 Approval of Shop Drawing for treatment of boundary walls 0
15.00 0
12 Installation Wall board Installation0(One side) 0 22.00
0
13 0 Concrete neutralizer application 7.00
0
14 Coring Works 7.00
15 Electrical rough-in/Conduit and Wiring Installation (Splicing) 14.00
16 Auxiliary rough-in 14.00
17 FDAS rough-in 14.00
18 Application of skimcoat 24.00
19 Ducting Installation 18.00
20 Ceiling Framing 18.00
21 Application of primer 16.00
22 Sanitary layout 18.00
23 Treatment of boundary walls 11.00
24 HVAC Stub Out 21.00
25 Fire protection layout/piping 21.00
26 Floor topping/Screeding 14.00
Electrical rough-in/above ceiling works and Wiring Installation
27 21.00
(Splicing)
28 Water line layout 21.00
29 General floor topping or screeding 21.00
30 Electrical rough-in wall toilets and Wiring Installation (Splicing) 17.00
31 HVAC line/Condenser line 17.00
32 HVAC rough-in 17.00
33 Installation of wall boards (Enclosed) 21.00
34 Waterproofing 14.00
35 Layout of tiles works 15.00
36 Water leak test 14.00
37 Demolition Work 10.00
38 Ceiling board installation 21.00
39 Tiles Installation 21.00
40 Sprinkler Head Installation 22.00
41 Outdoor unit of ACU 22.00
42 Installation of plumbing fixtures 22.00
43 Installation of door jamb 22.00
44 Installation of window 16.00
45 Application of Second coat 19.00
46 Installation of electrical fixtures and accessories 16.00
47 Installation of auxiliary 14.00
48 Installation of FDAS 14.00
49 Testing and commissioning of Fire protection 8.00
50 Painting works top coat 14.00
51 Installation of doors 14.00
52 Installation of ACU indoor unit 14.00
53 Fixed furniture Installation 14.00
54 Installation of door System 14.00
55 Intercom System 14.00
56 Installation of Loose furniture 14.00
57 Site clearing works 18.00
58 Repainting work or Retouching 11.00
59 Cleaning 15.00
60 Turnover request 14.00
61 COC filling 14.00
62 Pullout/Demobilization 8.00
63 Ribbon cutting 3.00
TOTAL
0.68%
PROJECTED ACCOMPLISHMENT0.68% 0.68% 0.62% 0.62% 0.62% 0.67% 0.63% 0.63% 0.63% 0.71% 0.71% 0.71% 0.71% 0.71% 0.71% 0.71% 0.65% 0.65% 0.65% 0.51% 0.51% 0.51% 0.51% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.14% 0.14% 0.14% 0.14%
83.02%
PROJECTED CUMMULATIVE83.70% 84.38% 85.00% 85.62% 86.24% 86.91% 87.54% 88.17% 88.80% 89.51% 90.22% 90.93% 91.64% 92.35% 93.06% 93.77% 94.42% 95.07% 95.72% 96.23% 96.74% 97.25% 97.76% 97.97% 98.18% 98.39% 98.60% 98.81% 99.02% 99.23% 99.37% 99.51% 99.65% 99.79%
0.00%
ACTUAL ACCOMPLISHMENT 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
ACTUAL CUMMULATIVE
DEVIATION
KIRSKAT VENTURE
Manila Office: Unit 712B Tower-B The Regalia Park Towers 150 P. Tuazon Ave, Cubao, Quezon City
Landline: 0287765788
Email: kirskatventure.manila@gmail.com

November
Project Schedule Based on Actual
Week -25 Week -26
Thu Fri Sat Sun Mon
Item No Description Duration
16 17 18 19 20

16-Nov-23 17-Nov-23 18-Nov-23 19-Nov-23 20-Nov-23

0 0 0 0 0
0
0
General Requirement
0 0 0 0 178.00 0
0
1 Wall Framing Work 67.00
2 CHB laying 60.00
3 Approval for approved plan for construction (floor plan) 1.00
4 Mock up of soil pipe slope (2nd Floor) 3.00
5 Rebar Scanning 7.00
6 Approval of Mechanical Plan (Shop Drawing) 7.00
7 Plastering works 15.00
8 Approval of Reflected Ceiling plan (with final elevations) 15.00
9 Approval of Shop Drawing of Coring works location 15.00
10 Approval of Electrical Plan and Auxillary Plan (Shop Drawing) 15.00
11 Approval of Shop Drawing for treatment of boundary walls 15.00
12 Installation Wall board Installation (One side) 22.00
13 Concrete neutralizer application 7.00
14 Coring Works 7.00
15 Electrical rough-in/Conduit and Wiring Installation (Splicing) 14.00
16 Auxiliary rough-in 14.00
17 FDAS rough-in 14.00
18 Application of skimcoat 24.00
19 Ducting Installation 18.00
20 Ceiling Framing 18.00
21 Application of primer 16.00
22 Sanitary layout 18.00
23 Treatment of boundary walls 11.00
24 HVAC Stub Out 21.00
25 Fire protection layout/piping 21.00
26 Floor topping/Screeding 14.00
Electrical rough-in/above ceiling works and Wiring Installation
27 21.00
(Splicing)
28 Water line layout 21.00
29 General floor topping or screeding 21.00
30 Electrical rough-in wall toilets and Wiring Installation (Splicing) 17.00
31 HVAC line/Condenser line 17.00
32 HVAC rough-in 17.00
33 Installation of wall boards (Enclosed) 21.00
34 Waterproofing 14.00
35 Layout of tiles works 15.00
36 Water leak test 14.00
37 Demolition Work 10.00
38 Ceiling board installation 21.00
39 Tiles Installation 21.00
40 Sprinkler Head Installation 22.00
41 Outdoor unit of ACU 22.00
42 Installation of plumbing fixtures 22.00
43 Installation of door jamb 22.00
44 Installation of window 16.00
45 Application of Second coat 19.00
46 Installation of electrical fixtures and accessories 16.00
47 Installation of auxiliary 14.00
48 Installation of FDAS 14.00
49 Testing and commissioning of Fire protection 8.00
50 Painting works top coat 14.00
51 Installation of doors 14.00
52 Installation of ACU indoor unit 14.00
53 Fixed furniture Installation 14.00
54 Installation of door System 14.00
55 Intercom System 14.00
56 Installation of Loose furniture 14.00
57 Site clearing works 18.00
58 Repainting work or Retouching 11.00
59 Cleaning 15.00
60 Turnover request 14.00
61 COC filling 14.00
62 Pullout/Demobilization 8.00
63 Ribbon cutting 3.00
TOTAL
0.10%
PROJECTED ACCOMPLISHMENT0.10% 0.12% 0.08% 0.04%
99.89%
PROJECTED CUMMULATIVE99.99% 100.11% 100.19% 100.23%
0.00%
ACTUAL ACCOMPLISHMENT 0.00% 0.00% 0.00% 0.00%
ACTUAL CUMMULATIVE
DEVIATION
G 261 Err:509 Err:509
AR 574 Err:509 Err:509
EE 98 Err:509 Err:509
P 68 Err:509 Err:509
M 109 Err:509 Err:509
F 29 Err:509 Err:509
AU 84 Err:509 Err:509
1223 Err:509
Progress Accomplishment
Item No. Description Weight % Previous Present To Date
% % %
1 General Requirements 5.39%
Barracks and office 0% 4.72% 4.72%
2 Architectural Works 47.54%
Wall framing work 0% 10.10% 10.10%
CHB Laying 0% 13.96% 13.96%
Plastering work 0% 4.95% 4.95%
Installation Wall board Installation (One side) 0% 5.34% 5.34%
Installation of wall boards (Enclosed) 0% 0.98% 0.98%
3 Plumbing and Sanitary 3.82% 0% 0% 0%
4 Mechanical 15.05% 0% 0% 0%
5 Electrical 14.07% 0% 0% 0%
6 Fire Protection 1.25% 0% 0% 0%
7 Auxiliary 12.88% 0% 0% 0%

TOTAL 100.00% 0% 40.05% 40.05%

You might also like