Professional Documents
Culture Documents
BIPI-PDD-QF-007-00
BREAKDOWN COST
Effectivity Date:
April 01, 2015
SUMMARY OF COST
4M COMPUTATION
Effectivity Date:
April 01, 2015
Dimension of WWTP
Length = 25.54 m
Width = 18.2 m
Area = 464.828 sq.m
Site Preparation
Area = 687.192 sq.m
Excavation STP
Length = 25.54 m
Width = 18.2 m
Offset on Foundation = 0.8 m
Allowance for excavation = 1.5 m
Depth of Walls underground= 1.325 m
Depth of Excavation = 2.275 m
Length = 30.14 m
Width = 22.8 m
Area = 687.192 sq. m
Volume = 1,563.36 cu.m
Foundation
Length = 27.14 m
Width = 19.8 m
Area = 537.372 sq. m
Thickness = 0.8 m
Gravel Bed = 0.15 m
Volume = 429.8976 cu.m
Walls Concrete
Outside Length (m) Height (m) Thickness (m) Volume (cu.m)
Horizontal 51.08 8 0.4 163.456
0
0
Vertical 36.4 8 0.4 116.48
0
0
Inside
Horizontal 22.34 8 0.4 71.488
0
0
Vertical 36.4 8 0.4 116.48
0
0
Total: 467.904
ASD & EQT Cover Length (m) Width (m) Thickness (m) Volume (cu.m)
0 0 0 0
Columns Height (m) Width (m) Thickness (m) No. of Columns Volume (cu.m)
0 0 0 0 0
Walls Plastering
Outside Length (m) Height (m) Area (sq.m)
Horizontal 51.08 6.675 340.959
0 -1.325 0
Influent 10 m Length
1 m Width
1 m Depth
1 m Length of RCP
Effluent 10 m Length
1 m Width
1 m Depth
1 m Length of RCP
Document Code: BIPI-
PDD-QF-006-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
4M COMPUTATION
Effectivity Date:
April 01, 2015
EDUC 106,400.00
SUBTOTAL 113,498.56
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
Concrete Length(m) Width (m) Depth (m) Vol. (cu.m) 524.35 cum total backfill (20% compacted)
STP Walls 25.54 18.20 1.33 615.90 100.00 cum / day per compactor
Foundation w/ Gravel bed 27.14 19.80 0.95 510.50 2.00 pc/s plate compactor
Total: 1,126.40 200.00 cum / day capacity
3.00 day/s to finish backfilling
24.00 hour/s to finish backfilling
4M COMPUTATION
Effectivity Date:
April 01, 2015
Length (m) Width (m) Thickness (m) volume (cum) 96.73 cum gravel bedding (20% compacted)
Foundation 27.14 19.80 0.15 80.61 100.00 cum / day per compactor
- 1.00 pc/s plate compactor
- 100.00 cum / day capacity
- 1.00 day/s to finish gravel bedding
Total: 80.61 8.00 hour/s to finish gravel bedding
ITEM
DESCRIPTION UNIT QTY. DIRECT COST (Php) AMOUNT (Php)
NO.
A. MATERIAL -
Gravel 3/4" cum 97.00 1,200.00 116,400.00
-
-
-
-
-
-
-
MDUC 116,400.00
B. LABOR / MANPOWER
1 Laborer hr 8.00 63.38 507.04
1 Plate Compactor Operator hr 8.00 67.13 537.04
-
-
-
-
-
-
-
-
-
LDUC 1,044.08
C. EQUIPMENT / MACHINE
1 Plate compactor hr 8.00 213.50 1,708.00
-
-
-
-
-
-
-
-
-
-
-
EDUC 1,708.00
SUBTOTAL 119,152.08
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
78 total trips
DIRECT COST
ITEM NO. DESCRIPTION UNIT QTY. AMOUNT (Php)
(Php)
A. MATERIAL -
-
-
-
-
-
-
-
-
MDUC -
B. LABOR / MANPOWER
2 Helper hr 32 63.38 4,056.32
-
-
-
-
-
-
-
-
-
-
LDUC 4,056.32
C. EQUIPMENT / MACHINE
Mini Dumptruck w/ Driver (10 cu.m) trip(s) 78 1,750.00 136,500.00
Backhoe Loader w/ Driver cu.m 780 90.00 70,200.00
-
-
-
-
-
-
-
-
-
-
EDUC 206,700.00
SUBTOTAL 210,756.32
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
2 day/s concreting
16 hrs
-
-
-
-
MDUC 2,745,352.64
B. LABOR / MANPOWER
1 Laborer hr 112 63.38 7,098.56
1 Mason hr 16 67.13 1,074.08
20 Steelman hr 96 67.13 128,889.60
LDUC 137,062.24
C. EQUIPMENT / MACHINE
1 Pumpcrete cu.m 430 200.00 86,000.00
2 Concrete Vibrator hr 16 350.00 11,200.00
2 Bar Cutter hr 96 26.25 5,040.00
EDUC 102,240.00
SUBTOTAL 2,984,654.88
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
LDUC 238,199.84
C. EQUIPMENT / MACHINE
1 Pumpcrete cu.m 468 200.00 93,600.00
2 Concrete Vibrator hr 16 350.00 11,200.00
3 Bar Cutter hr 160 26.25 12,600.00
-
-
-
EDUC 117,400.00
SUBTOTAL 3,911,630.01
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
EDUC 7,480.00
SUBTOTAL 166,070.90
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
4M COMPUTATION
Effectivity Date:
April 01, 2015
4M COMPUTATION
Effectivity Date:
April 01, 2015
4M COMPUTATION
Effectivity Date:
April 01, 2015
DIRECT
ITEM NO. DESCRIPTION UNIT QTY. AMOUNT (Php)
COST (Php)
A. MATERIAL -
Paint Primer gal 47 550.00 25,850.00
Paint gal 47 650.00 30,550.00
Thinner gal 24 250.00 6,000.00
Paint Brush/Roller lot 1 5,000.00 5,000.00
-
-
-
-
MDUC 67,400.00
B. LABOR / MANPOWER
5 Painter hr 32 67.13 10,740.80
2 Helper hr 32 63.38 4,056.32
-
-
-
-
-
-
-
-
-
LDUC 14,797.12
C. EQUIPMENT / MACHINE
Air Compressor hr 358.00 -
Backhoe Loader hr 1,430.00 -
Concrete Cutter hr 116.00 -
Concrete Mixer hr 172.00 -
Jackhammer hr 50.72 -
Mini Dumptruck hr 529.00 -
Plate compactor hr 213.50 -
Roller Compactor hr 378.00 -
Small truck with boom hr 934.00 -
Small truck without boom hr 712.00 -
Vibrator hammer hr 94.21 -
Pump hr 350.00 -
EDUC -
SUBTOTAL 82,197.12
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
-
-
MDUC 575,905.00
B. LABOR / MANPOWER
8 Carpenter hr 224.00 67.13 120,296.96
2 Laborer hr 224.00 63.38 28,394.24
Scaffolders lot 1 100,000.00 100,000.00
LDUC 248,691.20
C. EQUIPMENT / MACHINE
Air Compressor hr 358.00 -
Backhoe Loader hr 1,430.00 -
Concrete Cutter hr 116.00 -
Concrete Mixer hr 172.00 -
Jackhammer hr 50.72 -
Mini Dumptruck hr 529.00 -
Plate compactor hr 213.50 -
Roller Compactor hr 378.00 -
Small truck with boom hr 934.00 -
Small truck without boom hr 712.00 -
Vibrator hammer hr 94.21 -
Pump hr 350.00 -
EDUC -
SUBTOTAL 824,596.20
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
MCC Room
Length 3m
Width 4.9 m
ITEM DIRECT
DESCRIPTION UNIT QTY. AMOUNT (Php)
NO. COST (Php)
A. MATERIAL -
Blower Room sq.m 31 12,000.00 370,146.00
MCC Room sq.m 15 11,000.00 161,700.00
Screw Press Area sq.m 17 18,500.00 316,072.50
-
-
-
-
-
-
-
MDUC 847,918.50
B. LABOR / MANPOWER
-
-
-
-
-
-
-
-
LDUC -
C. EQUIPMENT / MACHINE
Air Compressor hr 358.00 -
Backhoe Loader hr 1,430.00 -
Concrete Cutter hr 116.00 -
Concrete Mixer hr 172.00 -
Jackhammer hr 50.72 -
Mini Dumptruck hr 529.00 -
Plate compactor hr 213.50 -
Roller Compactor hr 378.00 -
Small truck with boom hr 934.00 -
Small truck without boom hr 712.00 -
Vibrator hammer hr 94.21 -
Pump hr 350.00 -
EDUC -
SUBTOTAL 847,918.50
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
DIRECT
ITEM NO. DESCRIPTION UNIT QTY. AMOUNT (Php)
COST (Php)
A. MATERIAL -
Paint Primer gal 67 550.00 36,850.00
Paint gal 67 650.00 43,550.00
Thinner gal 34 250.00 8,500.00
Paint Brush/Roller lot 1 5,000.00 5,000.00
-
-
-
-
MDUC 93,900.00
B. LABOR / MANPOWER
5 Painter hr 48 67.13 16,111.20
3 Laborer hr 80 63.38 15,211.20
-
-
-
-
-
-
-
-
-
LDUC 31,322.40
C. EQUIPMENT / MACHINE
Air Compressor hr 358.00 -
Backhoe Loader hr 1,430.00 -
Concrete Cutter hr 116.00 -
Concrete Mixer hr 172.00 -
Jackhammer hr 50.72 -
Mini Dumptruck hr 529.00 -
Plate compactor hr 213.50 -
Roller Compactor hr 378.00 -
Small truck with boom hr 934.00 -
Small truck without boom hr 712.00 -
Vibrator hammer hr 94.21 -
Pump hr 350.00 -
EDUC -
SUBTOTAL 125,222.40
Document Code:
BIPI-PDD-QF-007-00
4M COMPUTATION
Effectivity Date:
April 01, 2015
Computation: