You are on page 1of 20

Lab Activity 3 - Division 31 Earthwork

STUDENT NAME
STUDENT ID

ASSIGNMENT INSTRUCTIONS
This assignment is completed individually. You must upload your completed assignment as an Excel file before the submission deadline b
Assignment link. The assignment will be graded based on the specified rubric.
Assignment Mark: 3.00% of Course Grade
Submission Deadline: Sunday, September 24, 2023, 11:59pm
Submission Dropoff: Submit your work on Braightspace by clicking the Lab folder.
You are strictly prohibited from copying from one another. Any evidence of plagiarized work will attract an automatic 0 for your submissio
responsibility to prove that your work was authentic.

ASSIGNMENT REQUIREMENTS
1. Download and study the plan (Dwg. 302) and thesection provided
2. Prepare the quantity takeoff calculations for Division 31 - Earthwork items identified in RECAP tab.
Detailed quantity takeoffs are prepared in the TAKEOFF worksheet. Insert more rows if required.
3. Transfer the final quantities to RECAP sheet and complete the pricing calculations.
4. Submit your completed lab workbook.

ASSIGNMENT RUBRIC

Outstanding Excellent Above


Evaluation Criteria Max (90-100) (80-89) Average (70-
79)
Completeness of Calculations 33.33%
Accuracy of Calculations 33.33%
Organization of Calculations 33.33%
Total 99.99%
cel file before the submission deadline by clicking on the

attract an automatic 0 for your submission. It will be your

Average Below
(60-69) Average (50- Poor (0-49)
59)
Lab Activity 3 - Division 31 Earthwork

STUDENT NAME MANISH MURUGESH


STUDENT ID 101483112

RECAP SHEET

Project: Project No: Estimate No: Page:


Element/Trade: Measured: Estimate Type: Date:
Element/UCI Reference: Extended: Priced: Checked:

Description No. Dimensions Extensions Quantity Unit Unit Price Cost ($)
Brought Forward from Page:
RECAP

31 00 00 - EARTHWORK

31 23 00 Excavation and Fill

1) Site Clearing and Grubbing 269 m2 $1.20 $322.80

2) Top Soil Removal 53.8 m3 $9.00 $484.20

3) Excavation for Foundation Trenches 199 m3 $12.00 $2,388.00

4) Backfill with Native Soil 179 m3 $15.00 $2,685.00

5) Backfill with Granular B Under SOG 27 m3 $45.00 $1,215.00

6)Disposal of Excavated Material (including site clearing) 34 m3 $15.00 $510.00

Total $7,605.00

Profit & Overhead 20.00% $1,521.00

TOTAL COST $9,126.00

Construction Notes:
1) Elevation of the existing grade is the same as the elevation at the top of the foundation wall
2) Fairly good soil conditions
3) 50mm grubbing and clearing over site prior to any excavation works
4) Remove 200 mm topsoil over site (include area for working space and/or slope) and stockpile it on the site for future use.
5) Backfill to the underside of the concrete slab with granular “B” (150 mm)
6) Backfill around foundations with excavated earth up to underside of the granular B base

Carried Forward to Page: $25,857.00


Lab Activity 3 - Division 31 Earthwork

STUDENT NAME MANISH MURUGESH


STUDENT ID 101483112

RECAP SHEET

Project: Project No: Estimate No: Page:


Element/Trade: Measured: Estimate Type: Date:
Element/UCI Reference: Extended: Priced: Checked:

Description No. Dimensions Extensions Quantity Unit Unit Price Cost ($)
Brought Forward from Page:

TAKEOFF L W H

310000- Earthwork
311000- Site Clearing & Grubbing
Length: 18000
Add w /s 2 1600 3200
21200

Width: 11000
Add W/s 2 1600 3200
14200

For Deduction:
Length 8000
Width 4000 8 4 32 32 m2
50m m thick Clearing and Grubbing 21.2 14.2 301.04 301 m2
50m m thick Clearing and Grubbing after Deduction 269 m2
Volume of Site Clearing 0.05 13.45 14 m3

Remove top soil


Depth 200
For Deduction:
Depth 200 8 4 0.2 6.4 6.4 m3
Remove top soil & stockpile it on the site 21.2 14.2 0.2 60.208 60 m3
Remove top soil & stockpile it on the site After Deduction 53.8 m3

312300- Excavation and Fill


Excavate foundation trenches

PCL of Ext. Fdn Wall


Length: 18000
Width 11000
2* 29000
58000
Less 4* 300 1200
PCL of Ext. Fdn Wall 56800
56.8
Cross sectional area of Trench

Top Width 3500


Bottom Width 1500
Depth 1000

3.5 1 1
Area of Trench 3.5

Volume of Trench Excavation


PCL*Area 56.8*3.5 198.8 199 m3

Volume of Concrete footing 56.8 0.6 0.2 6.82 m3

Height of Foundation wall in trench 1000

Volume of Concrete Footing Wall 56.8 0.3 0.8 13.632 m3

Backfill With Native Soil 199


Ded. Of Conc. Footing -6.82
Ded. Of Conc. Footing wall -13.632
178.55 179 m3
Backfill with Granular B Under SOG

Length 18000
less 2* 300 600
17400
Width 11000
less 2* 300 600
10400
Thickness 150

Backfill with Granular B Under SOG 17.4 10.4 0.15 27.144 27 m3


Deduct setback 8 4 0.15 4.8
22

Disposal of Extra Materials 198.8


(incl site clearing) 178.55
13.45
Volume of Disposals 33.7 34 m3

Carried Forward to Page: $0.00


Lab Activity 3 - Division 31 Earthwork

STUDENT NAME
STUDENT ID

RECAP SHEET

Project: Project No:


Element/Trade: Measured:
Element/UCI Reference: Extended:

Description No. Dimensions

TAKEOFF
Estimate No: Page:
Estimate Type: Date:
Priced: Checked:

Extensions Quantity Unit Unit Price Cost ($)


Brought Forward from Page:
Carried Forward to Page: $0.00