Task NameResource % Work CoWork Units

Identify Pr Project Dir0 8h 100%


Conduct StProject Dir0 8h 100%
Generate SProject Dir0 8h 100%
Identify GoProject Dir0 8h 100%
Develop StProject Dir0 8h 100%
Research PProject Ma0 8h 100%
Develop PrProject Ma0 8h 100%
Develop PrAcceptor 0 8h 100%
Conduct PlProject Dir0 8h 100%
Collect Pr Application0 2h 100%
Collect Pr Technical A0 2h 100%
Collect Pr Project Ma0 8h 100%
Develop R Project Dir0 8h 100%
Develop ReApplication0 8h 100%
Develop ReTechnical A0 8h 100%
Develop ReProject Ma0 8h 100%
Produce R Project Ma0 8h 100%
Produce R Acceptor 0 8h 100%
Document Project Ma0 8h 100%
Define ProProject Ma0 8h 100%
Specify DelProject Ma0 8h 100%
Identify Pr Project Ma0 8h 100%
Document Project
A Ma0 8h 100%
Update ReqProject Ma0 8h 100%
Document Project
P Ma0 8h 100%
Build Proj Project Ma0 8h 100%
Develop WB Project Ma0 8h 100%
Document Project Ma0 8h 100%
Define ProjProject Ma0 8h 100%
Sequence Pr Project Ma0 8h 100%
Estimate AcProject Ma0 8h 100%
Estimate AcProject Ma0 8h 100%
Develop PrProject Ma0 8h 100%
Document Project Dir0 8h 100%
Estimate PrProject Ma0 8h 100%
Determine Project Dir0 8h 100%
Plan ProjecQuality As 0 8h 100%
Plan ProjecAcceptor 0 8h 100%
Develop HuProject Dir0 8h 100%
Plan Proje Project Ma0 8h 100%
Plan Proje Acceptor 0 8h 100%
Plan Risk Project Ma0 8h 100%
Plan Risk Acceptor 0 8h 100%
Identify Pr Project Ma0 8h 100%
Perform QuaProject Ma0 8h 100%
Perform QuaProject Ma0 8h 100%
Plan Risk Project Ma0 8h 100%
Plan Proje Contracts 0 8h 100%
Plan Stak Project Ma0 8h 100%
Document Project Ma0 8h 100%
Document Acceptor 0 8h 100%
Document Project Ma0 8h 100%
Document Acceptor 0 8h 100%
Document Project Ma0 8h 100%
Document Acceptor 0 8h 100%
Prepare ProProject Ma0 8h 100%
Set Up ProQuality As 0 8h 100%
Set Up ProProject Ma0 8h 100%
Set Up ProProject Ma0 8h 100%
Authorize Team Lead0 8h 100%
Manage Pro Project Ma0 8h 100%
Provide GeProject Ma0 8h 100%
AdministerProject Ma0 8h 100%
Participat Quality As 0 8h 100%
Conduct InQuality As 0 8h 100%
Conduct PrQuality As 0 8h 100%
Facilitate Quality As 0 8h 100%
Obtain ReqProject Dir0 8h 100%
Conduct TeProject Dir0 8h 100%
Assign IndiTeam Lead0 8h 100%
Provide TeProject Ma0 8h 100%
Recognize Project Dir0 8h 100%
Conduct PeProject Ma0 8h 100%
Manage StaProject Dir0 8h 100%
Manage TeProject Ma0 8h 100%
Meet WithTeam Lead0 8h 100%
Monitor T Project Ma0 8h 100%
Distribute Project Dir0 8h 100%
Issue RequContracts 0 8h 100%
Evaluate R Contracts 0 8h 100%
Negotiate Contracts 0 8h 100%
Manage StProject Dir0 8h 100%
Resolve S Project Dir0 8h 100%
Manage Act Project Ma0 8h 100%
Manage DaProject Ma0 8h 100%
Manage Con Project Ma0 8h 100%
Manage ReProject Ma0 8h 100%
Manage Pro Project Ma0 8h 100%
Control Pr Project Ma0 8h 100%
Control Sc Project Ma0 8h 100%
Manage Pro Project Ma0 8h 100%
Manage Pro Acceptor 0 8h 100%
Measure WTeam Lead0 8h 100%
Measure WProject Ma0 8h 100%
Maintain PProject Ma0 8h 100%
Maintain WProject Ma0 8h 100%
Monitor CoProject Ma0 8h 100%
Control ProProject Dir0 8h 100%
Maintain FiProject Dir0 8h 100%
Control ProQuality As 0 8h 100%
ParticipateQuality As 0 8h 100%
Measure Qu Quality As 0 8h 100%
Report Wee Team Lead0 8h 100%
Report Wee Acceptor 0 8h 100%
Report Mon Project Ma0 8h 100%
Report Mon Acceptor 0 8h 100%
Control ProProject Ma0 8h 100%
Manage Sub Contracts 0 8h 100%
Control ProProject Ma0 8h 100%
Monitor StaProject Dir0 8h 100%
Obtain Fin Project Dir0 8h 100%
Transition Project Dir0 8h 100%
Assess StakProject Ma0 8h 100%
SummarizeProject Ma0 8h 100%
Review andProject Ma0 8h 100%
Close Out tProject Ma0 8h 100%
Review andProject Ma0 8h 100%
Close SubcContracts 0 8h 100%