Name of Project : Rehabilitation of Session Hall


Location : SP Building, Brgy. San Vicente, City of Ilagan, Isabela
Description : Repair and Repainting of Wall
Size
PROGRAM OF WORKS
BILL OF MATERIALS AND COST ESTIMATE

I. MATERIALS

1/2" Marine Plywood 2 pcs. 800.00 ₱ 1,600.00


1/4" Marine Plywood 12 pcs. 400.00 4,800.00
Flat Latex White 2 gals. 750.00 1,500.00
Skim Coat 1 bag 650.00 650.00
Tuli White 1 gal. 800.00 800.00
Roller Paint w/ Pan 3 sets 200.00 600.00
Paint brush 2" 3 pcs. 100.00 300.00
Paint brush 3" 3 pcs. 150.00 450.00
Finishing Nail 1" 1 kg. 100.00 100.00
Finishing Nail 2" 2 kgs. 100.00 200.00
MATERIAL COST 11,000.00
LABOR COST 3,850.00

TOTAL PROJECT COST ₱ 14,850.00

Prepared by: Checked by: Approved by:

ENGR. RICHELLE JANE VEE L. MIGUEL ENGR. GARRY D. CABANILLA HON. JOSEMARIE L. DIAZ, DMD, MBA
C.E. Aide City Engineer City Mayor