Completion of contract for ‘Modification of ram car track Batt 3”

P.O. No.: 4515002306/269 Dt 08.12.2011

Contractor: M/s ABS CONSTRUCTION

1.The above-referred job was for “Modification of ram car track Battery 3”
and scheduled to be completed by 17.08.2012. But due to non availability of
shutdown of ram car track because of hot repair of 3B, provisional time
extension was given up to 30/09/2012

1. The job has been completed on 30/09/2012 satisfactorily and final order is
required to be issued.

2. As job has been completed, it is proposed to give final order for time
extension without LD up to 30/09/2012.

3. Approval may be given for final time extension of the above referred job.

No.: COR/Final TE/4502002306


Dt : 5.02.2013
(D.Saha)
DGM(Mech) COR
- GM (CO&CC)
-----------------
- DGM I/C(CD)
STEEL AUTHORITY OF INDIA LTD.
DURGAPUR STEEL PLANT

Sub: Completion of contract work

M/s ABS CONSTRUCTION had completed the following work. Necessary information in
this connection are furnished.

Sl Description Remarks
1 Name of Work Modification of ram car track Battery 3
2 Name of the Contractor M/s ABS CONSTRUCTION
3 P.O. No.: 4515002306/269
Work Order No. & Date Dt 08.12.2011

4 Tender value of work Rs. 1,090,419.64


5 Dt 08.12.2011
Date of Work Order
6 Date of handing over the site 18.04.2012
7 Time of completion as per letter of intent 17.08.2012
8 Revised date of completion 30/09/2012
9 Up-to-date progress of work Job completed
10 Shutdown not available due to ongoing hot
Reasons for delay
repair of 3B
11 Whether any extension of time previously
No.
granted (If yes, the extension period which
date may please be mentioned)
12 Remarks

(D.Saha)
DGM(Mech) COR