Elisa Del Giacomo Martin Sirtori (COIMS)
(COQC) (COPX)
June Issued for
03
2020 Implementation Michele
Carlo Celenza Francesco Bagorda Caramuta
(CIMS/KO) (MECO) (OE&C)
Roberto Poggi
(COQC)
Reason for
REV. DATE Prepared Verified Approved
issue
Rev 0:
ISSUE
Pages 24
This document supersedes and replaces the specifications:
• 06570.COO.AVV.FUN – Mechanical Completion & Pre-commissioning
• 06571.COO.AVV.FUN – Offshore Installations – Commissioning & Functional Test
Rev 1:
DATE: July 2015
ISSUE FOR IMPLEMENTATION
Pages 49
List of sections changed from Revision 0:
• ACRONYMS AND ABBREVIATIONS
• HSE PRINCIPLES
• QUALITY CONTROL SYSTEM: ESSENTIAL VARIABLES
• SPECIAL PROCESS
• PERSONNEL QUALIFICATION
• QUALITY CONTROL, INSPECTION AND TESTING PROCEDURES
• QCP & ITP
• WITNESSING GENERAL PRINCIPLES
• ITR’s AND OTHER RECORDS
• ATTACHMENTS
Rev. 03: Actual revision is of 49 pages and of 05 attachments
Date: June 2020
List of sections changed from Revision 1:
• ACRONYMS AND ABBREVIATIONS
• DOCUMENT MANAGMENT
• HSE PRINCIPLES
• QUALITY CONTROL SYSTEM: ESSENTIAL VARIABLES
• SPECIAL PROCESS
• PERSONNEL QUALIFICATION
• QUALITY CONTROL, INSPECTION AND TESTING PROCEDURES
• QCP & ITP
• WITNESSING GENERAL PRINCIPLES
• ITR’s AND OTHER RECORDS
• MECHANICAL COMPLETION
• ATTACHMENTS
INFORMATION REQUEST
For information about the content of this standard, please refer to persons mentioned on first
page or to Company Standard Team (mbxc&st@eni.com).
INDEX
CONTRACTOR shall use this standard in conjunction with specific Project documents, the relevant
Contract’s requirements, and the applicable Quality Management Specifications referenced in Para. 3 below.
All Construction and Commissioning Quality Control activities shall be described in the
CONTRACTOR Quality Control Plan and clearly defined in the Construction discipline Inspection
and Test Plans (Construction ITPs) and in the Commissioning Inspection and test plan
(Commissioning ITPs).
The ITPs for construction and commissioning activities includes all the inspections and
verifications to be carried out by CONTRACTOR to demonstrate that the plant and equipment
have been fabricated, constructed, installed and commissioned correctly, as per design.
This will mainly include:
• Review of all Manufactory Inspection Release Records, Certificates relevant to
CONTRACTOR and/or COMPANY supplied bulk materials and tagged items delivered to
site, to make sure they satisfy all statutory, Eni standards, Project Inspection Plans and
specifications;
• Review of all FAT’s, EFAT’s certificates and relevant punch lists for all CONTRACTOR
and/or COMPANY supplied equipment and packages. Such tests are carried out and
certified at Vendor premises, and witnessed by relevant CONTRACTOR and/or
COMPANY Inspector; All the mentioned documentation shall be included in the
Manufacturer Record Book to be provided to COMPANY by the terms established in the
Contract;
• Performance of incoming material inspections to establish conformity to PO
requirements and conditions at site arrival;
• Conformity checks and quality verifications carried out during construction, including:
Non Destructive Testing, welding inspections, visual and dimensional checks, sample
collection and testing (field and laboratory) etc…;
• Visual inspection of all installed equipment or component, such as instruments,
packages, motors, cables, vessels, etc., to verify visually the condition of the
equipment, the quality of the installation, the compliance with project documentation,
as-built drawings, approved technical/site queries, specifications and vendor
instructions;
• Static / de-energised tests & cold testing, including: calibration of instruments,
machinery cold alignments, setting of safety valves, flushing / pressure testing of
piping, continuity/isolation/Hi Pot tests for electrical equipment’s and cables, and all
relevant reinstatement activities;
• Functional / energized tests & loop check including: leak tests, energization steps, I/O,
functional tests and OTP and all relevant commissioning activities;
• Surveillance of Preservation activities after reinstatement;
• Preparation of Final Documentations inclusive of Manufacturing Record Books,
Fabrication Dossiers and Mechanical Completion Dossier.
Commissioning ITP additional requirements are reported in 27952.COS.AVV.STD and
27970.COS.AVV.STD.
[19] 28046 ICO.AVV.SDS Stud Bolt Tightening and Joint Integrity Management
Code Description
ISO 9000 Quality management systems - Fundamentals and vocabulary
Term Definition
Term Definition
Term Definition
Factory Acceptance Test The complete set of Inspections, Checks and Tests
(FAT): carried out at the Manufacturer/Supplier’s premises
to ensure that the Supply is adequately completed
and Operationally Tested, per Purchase Order
requirements, to be delivered to the Facility’s
Construction Yard for relevant installation.
Inspection Test Plan (ITP) ITPs are the Plans identifying, with regard to the
respective phase, for each type of equipment and
discipline the required Inspections, Checks and Tests to
be executed, including applicable procedures, acceptance
criteria, and witnessing scheme to be applied;
Term Definition
Term Definition
Ready For Hydrocarbon-In The Milestone progress status achieved when a Pre
(RFHC-In): Start-up Review (PSUR) have been successfully
completed for all Facility’s Systems intended to be set
into operations through the relevant introduction of
Well’s Hydrocarbon feedstock or First Charge.
Ready For Performance The Facility’s Completion Status achieved when all
Test
conditions are met to approach the verification of
RFPT
Facility’s Performance vs. Contractual and Design
requirements.
Term Definition
Ready For Start-up The Milestone progress status achieved when all
(RFSU): Commissioning Functional and Operational Tests on
a Facility’s System have been completed and
documented to the extent necessary to safely and
effectively start the intended System’s operations.
Site Acceptance Test A set of Acceptance Tests carried out after a supplied
(SAT): Equipment have been assembled and installed on
the Facility, aimed to ascertain that all relevant
Purchase Order requirements have been
satisfactorily accomplished.
System Completion: The process through which the Design and Technical
integrity of Facility’s Sub-systems/Systems is
verified and tested, and Systems are gradually
Turned-Over between the Project Development and
the Operations Organizations, or from
CONTRACTOR(s) to COMPANY.
Term Definition
Third Party Inspection inspection carried out by entities that are indepented
from Company and Contractor Organization
Should any conflict arise or be noted between the requirements of this document, or the
specific Project Documents, and these given in the various applicable International Codes,
Standards, Best Industrial Practices, etc., then a written notice shall be forwarded to the
owner of this Standard, with details of contrasting or ambiguous requirements, for evaluation
and identification of adequate corrective actions and way forward.
References to International Codes, Standards and Best Industrial Practices shall always be
intended to the latest editions, inclusive of amendments/supplements/revisions thereto, in
force at the date of Contract Award.
i. Local Laws and Regulations in force in the Country(ies) where the various part of the
Project are executed;
International Codes and Standards are at the lower level of hierarchy as their contents, assumed
as reference, are developed and detailed within the Company’s Project Specifications and
Standards specifically applicable to the area of business in which Eni Spa and its subsidiaries are
the Operators.
The requirements included into applicable Local Laws and Regulations shall always prevail on
this document.
2 HSE PRINCIPLES
All Construction, Installation and testing activities shall be carried-out in accordance with Eni’s
HSE Standards and Golden Rules, Quality and Engineering requirements, and with all applicable
Legislation and Regulations in force in the Country(ies) where the various parts of the Projects
are executed.
• Hazard identification (HAZID) activities, including Risk Assessments, Job Safety Analysis
(JSA) and Tool Box Talks, shall be conducted in accordance with applicable Company’s
Governing Documents, Best Practices and Procedures;
• Construction, Installation, and testing activities shall be planned and executed with zero
harm on the environment. Releases of substances that may harm human health or the
environment shall be avoided. Any discharges/emissions shall be duly logged and
reported;
• All Construction and installation activities, including Inspections, Checks and Tests shall
be carried-out in conformity with the applicable PTWS;
• All activities shall be executed in line with the requirements set forth into the respective
approved work permit.
• Personnel qualification;
• Control of Nonconformances;
CONTRACTOR shall ensure that strategies, procedures and instructions for the management of
the above variables are included inside the Project Quality Plan or alternatively, in dedicated
project documents.
Documented Criticality Assessment shall be carried out by Contractor to support the surveillance
strategies of its suppliers, sub-contractors and sub-vendors. The level of involvement of
Company in this activities (inspection and/or documentation follow up) will be also based on the
results of such assessment.
The above requirements are expected to be fulfilled also by Supplier, Sub-Contractor, Vendors
and Sub-Vendors selected by CONTRACTOR to perform the assigned scope of work.
• review the list of special processes involved for construction activities as defined in
chapter 5 of this specification;
• review the Project Quality Plan and the list of other expected quality-related deliverables
in order to anticipate the need for any additional procedures/work instruction/report;
• review the list of key specifications and testing procedures with regard to quality
requirements, especially where special processes are involved (NDT including any
preliminary validations, welding);
• review and agree the ITPs and the baseline level of intervention of EC, Company and any
Third Party according to the local regulations or the applicable technical specifications.
Company’s expected level of attendance shall not constitute a prejudice for Company to
exert in full the right to inspect, as defined in the contract’s general terms and conditions;
• identify the type and frequency of progress and quality reporting;
• discuss modalities and cut-off dates for Contractor’s KPI (see section 12) issue to
Company (if/where applicable);
• review requirements for final certifications and dossiers and agree accordingly on the IT
system to be used for QC and MC documentation management in electronic format during
and after the execution of the works, as well as on the key categories of records to be
provided in hardcopy (e.g. NDT records).
Contractor appointed attendant shall prepare Minutes of the Kick-Off Meeting and distribute it to
both Company’s and Contractor’s affected contract holder(s), Project/Package manager(s) and
QC Manager.
5 SPECIAL PROCESSES
Special processes are defined as processes where the resulting output cannot be verified by
subsequent monitoring or measurement and, as a consequence, deficiencies become apparent
only after the product is in use or the service has been delivered. (ISO 9001).
Special Process is defined within the project as any activity, work, testing and inspection that
needs to be performed and controlled in accordance with a specific program which defines the
parameters, the equipment, personnel qualifications required and how to complete and to
document the activity itself. Programs require validation on an as-needed base.
CONTRACTOR shall prepare and issue a list defining all the special processes considered in the
project, such list shall be agreed and endorsed by COMPANY. Such list shall be presented and
agreed with COMPANY during the kick-off meeting.
During Construction activities, at least the activities related to the following processes shall be
included into the list:
• NDT activities (VT, RT, UT, AUT, MT, PT, ET, etc…);
• Coating activities, applied in factory on components, and field applied (on site) (Painting,
Liquid coatings, Shrink sleeves, insulation, PFP, FBE, all of the required acceptance testing
etc…);
• in accordance with approved and qualified procedure (see paragraph Errore. L'origine r
iferimento non è stata trovata.);
• with competent and skilled personnel who need to have the required professional
qualification and/or certification (see paragraph Errore. L'origine riferimento non è s
tata trovata.);
CONTRACTOR shall obtain all state licences, permits, certifications, authorizations by COMPANY,
Local Regulatory Authority and /or recognised body required for performing all above activities,
at its own cost in due time without affecting project schedule.
6 PERSONNEL QUALIFICATION
CONTRACTOR shall implement special processes and inspection activities with qualified and
certified personnel, as required by COMPANY and Local Regulatory Authority.
The above mentioned standard shall be considered only for personell qualifications purpose.
Cases where the specific project requirements exceed the applicable standards shall be identified
by CONTRACTOR and for each of them the additional requirements shall be specified in the
applicable documents (e.g. UT operators’ qualification for “zero root defect” in sour service,
welders qualification for socket joints).
CONTRACTOR shall issue a qualification scheme (or procedure) for COMPANY approval (e.g.
welders for high pressure sour service lines, pipeline joint coating, special paint application, bolt
tensioning, hardness test operators, steam tracing joints, fitter/pipe fitter) that shall comply with
the indication provided by the project specification and the specified minimum level of
qualification expected by COMPANY shown in Attachment 16.1, whichever provides the most
stringent requirements.
In the lack of applicable reference standards, the personnel qualification shall be specified to be
in accordance with “good industrial recognised practice” and agreed with COMPANY.
The matrix with the minimum level of personnel qualification, provided in attachment 16.1 of
the present document, is indicative only and may be tailored and completed by project team
considering project specific requirements (design and codes) as well as local Regulatory
Authority requirements.
COMPANY shall have the prerogative to witness and validate the personnel qualification process.
Any CONTRACTOR operator covered by this section has to be specifically accepted by COMPANY
and its performance, work log and validity for qualification controlled by dedicated logs to be
produced by CONTRACTOR.
No activity will start failing the acceptance of COMPANY of all the above requirements.
CONTRACTOR shall include in the proposed CONTRACTOR Document List Index all the
procedures necessary to cover the project quality control, inspection, testing and Mechanical
Completion scope. The relevant procedures shall be sent to COMPANY for review before the
commencement of relevant activities.
COMPANY reserves the right to approve the procedures of testing and execution activities.
“COMPANY approval level” of testing and execution procedures shall be defined at the early
project stage and shall comply with the applicable and relevant COMPANY standards and project
specifications.
• Purpose – Brief description of the working or testing activity including the definition of
the proposed method and techniques;
WPQR or PQR /WPS Documents shall have as a minimum all the requirements as laid out in:
A project Welding Summary shall be prepared by Contractor and daily made available to
COMPANY to allow proper follow up on welding activities.
The project Welding summary shall include at lest the following information for each weld:
• Line Indication;
• NDT Class;
• Material Type;
• Fluid;
• Weld Map;
• Location (Prefab or Erection);
• Diameter;
• Thikness;
• Test Pack;
• Material Grade;
• WPS;
• Welders;
• Heat Numbers;
• Weld Process;
• Welding Date;
• Vistual Report;
• PWHT as applicable;
• Other NDT as applicable (eg. MPI, DPI, RT, PAUT, UT, EC, PMI, HT, etc);
• Accpetance;
• Piles testing;
• Concrete pouring control and testing;
• Concrete coating;
• Coating applications:
o Special Insulations;
o Fire proofing;
o FBE.
• Painting application:
o Painting Inspection;
• NDT Inspections:
o Visual;
o Radiographic;
o Ultrasonic;
o Authomatic or semi-authomatic Ultrasonic;
o Magnetic Particle;
o Liquid Penetrant;
o Eddy Current.
• Heat treatments (local & furnace) ;
• Valves reinstatements;
• Hydrostatic testing;
• Pneumatic testing;
• Piping cleaning;
• Pipeline pigging and purging;
• Cladding installation;
• Flange connection and close out;
• Gasket installation;
• Torqueing (including hydraulic bolt torqueing and tensioning) ;
• Instrument calibration;
• Installation and testing of HVAC Equipment’s;
8 QUALITY CONTROL PLAN (QCP) AND INSPECTION AND TEST PLAN (ITP)
Field quality control activities are governed and controlled by applicable Quality Control Plan
(QCP) and relevant discipline Inspection & Test Plans (ITP).
CONTRACTOR shall issue a Quality Control Plan for COMPANY approval in accordance with project
quality plan and contract attachments (i.e.contract coordination requirements), covering:
• All applicable discipline ITP’s covering construction and commissioning scope of work;
• All applicable inspection and testing procedures for construction and commissioning
scope of work;
• Control of Product Non Conformances;
In Attachment 16.3 the typical Company discipline construction ITPs are reported. Typical
Commissioning ITPs are reported in 27970.COS.AVV.STD.
CONTRACTOR shall prepare its own ITPs based on contract scope of work, contractual technical
specifications, relevant data sheets and requirements, ensuring that all the applicable testing
and inspection activities are included and that the CONTRACTOR & COMPANY witnessing scheme
is properly addressed.
Contractor shall prepare dedicated ITP for each discipline involved in construction activities.
The disciplines to be covered by ITP are (at least but not limited) the following:
• Architectural Works;
• Civil Works;
• Electrical works;
• HVAC works;
• Instrument works;
• Mechanical works;
• Offshore works;
• Pipeline works;
• Piping works;
• Structural works;
• Telecom Works;
• Acceptance criteria;
• Type and number of document to be issued (ITRs, Quality Records, Material Test
Certificates, Passports, various laboratory certificates, check lists).
CONTRACTOR besides QCP and ITPs shall also produce the templates of ALL Inspection Test
Report (ITRA and B) that will be utilized to cover all applicable activities. CONTRACTOR shall also
issue for COMPANY review/approval a matrix where discipline by discipline (eg. Civil, Piping,
Electrical, etc…) is reported the list of ITRs applicable for each Equipment to be installed or
activity to be carried out.
Whereas CONTRACTOR intend to use its own ITRs coding system, it is requested anyway to
include in the above mentioned matrix, the information about correlation between CONTRACTOR
and COMPANY ITRs codes.
In Attachment 16.3 are reported Company typical construction ITRs (ITRA). Typical
Commissioning ITRs (ITRB) are reported in 27970.COS.AVV.STD. In Attachment 16.2 it is
reported the typical Company Matrix of Construction ITPs / ITRs for completion purposes, based
on the relevant ITPs (attachment 16.3).
During site execution activities, due to their nature, notification for Hold/Witness points may be
required on a continuous base; CONTRACTOR should prepare and agree with COMPANY
dedicated look ahead plans (for shifts or days) informing the COMPANY about type of activities
requiring Witnessing and area identification where activities will be completed. Anyway, this does
not relieve the CONTRACTOR to issue RFI for all the activities involving COMPANY “W” and “H”
intervention points.
RFI shall contain for each activity as a minimum the following information:
• Type of inspection;
• Reference of item to be inspected (e.g. tag item, piping line number, etc.);
CONTRACTOR shall properly define its set of ITRs and records to support the completion process
providing the confirmation that testing activities have been properly executed during
construction and commissioning (as applicable depending on SOW) activities.
ITRs shall be prepared and signed off by relevant parties - CONTRACTOR, COMPANY, regulatory
authorities (if needed) etc., as applicable - after test completion in order to ensure reliability of
test results and to guarantee proper traceability.
CONTRACTOR shall make available to COMPANY all Test reports (eg. FAT report, Report, NDT
reports, etc..) as soon as available according to the related procedures for testing; Test records
shall be part of final documentation.
Vendors Inspection reports shall include reference to relevant test report as well as description
of inspection activities with details on how test was performed, who was present during testing,
pictures and any other useful information related to the completed inspection. Inspection reports
shall be available for COMPANY review, and provided to upon COMPANY request.
Product Non-conformances are deviation from specified requirements with respect to technical
project documents or procedures, which will likely result in:
NCR follow up and statistics will be part of the weekly Quality reporting.
Company reserves the right to open Non Conformity Reports if/where deemed applicable and in
accordance to the defined Company Project NCR procedure.
Non-Conformance (NC): Is any product, document or process that, at any stage of the work
process, is found not complying with the requirements of the applicable specifications, technical
Project documents (drawings, data sheets etc.) and approved procedures and for which the
remedial action is not covered by an approved and qualified process or procedure.
Major NC: Major NCs are deviations or non-conforming conditions which may become permanent
or whose rectifications will anyway result in final product not meeting the originally designed
characteristics for what concerns the utilization, workability, durability, life,
type/frequency/extent of maintenance.
Minor Non-conformance: Minor NCs are deviations or non-conforming conditions which may be
rectified or corrected to meet the originally designed characteristic of the product.
Major Non-Conformances require COMPANY input and approval prior to corrective or remedial
action being implemented or prior to permanently installing the NC product, while Minor Non-
conformances are required to be issued to COMPANY for information periodically as agreed.
NCs status shall be continuously monitored to ensure the effectiveness of the rectification and
close out process and to identify any need for process correction or improvement. The NCs status
shall be reported to COMPANY through typical reports preferably on a weekly basis.
Contractor shall (if/where applicable depending on the specific contract features) collect the
required KPI data on a quarterly basis or otherwise, as agreed during the Kick off meeting, and
provide them to Company for its evaluation.
The applicability of the above requirement and the application modalities shall be clarified at the
Kick off meeting.
13 MECHANICAL COMPLETION
ENGINEERING COMPANY STANDARD
Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
Rev. 03 - June 2020
27951.COS.QUA.STD
Pag. 35 of 49
The completion phase of a new plant is a critical process. Not all parts of the process facilities
reach the same degree of completion at the same time, therefore some areas or units may be
mechanically completed while others are not.
Therefore, while construction work progresses, essentially organised by areas, sub-areas and
disciplines, the completion phase is controlled by functional systems and sub-systems as
described in Company Standard 27950.COS.QUA.STD “Facilities Completion Specification”.
Each sub-system is characterized by tag-items, which represent the minimum discrete portions
of the plant univocally identified by a code, and which are associated to particular quality control
activities and functional tests. For non-tag items (e.g. piping) a level of material and processes
traceability shall be defined and relevant traceability plan prepared and implemented (e.g.
welding book).
Sub-systems are “Mechanically Complete” when all construction, quality control, integrity testing
and reinstatement activities are completed. All records pertaining to construction quality
inspection, integrity testing and reinstatement activities are compiled in a specific package,
arranged by sub-system.
The COMPANY software tool CCMS (Completion and Commissioning Management system) shall
be utilized as Integrated Completion database for reporting and for MC/Commissioning progress
control purposes.
Before the commencement of the works, upon COMPANY request, CONTRACTOR shall populate
CCMS with all ITRs template (for each inspection item/activities), agreeded with COMPANY, in
order to create the ITRs (with barcode system included) forms to be used to record inspection
activities.
CONTRACTOR shall regularly upload into CCMS all ITR’s completed and accepted by COMPANY,
the updated master punch list and Mechanical Completion certificates.
COMPANY can authorize CONTRACTOR to utilize its own software as Integrated Completion
Database. COMPANY approval will be subject to the verification of functionalities and
compatibilities with the other COMPANY tools ensuring that Maximum integration between
CONTRACTOR Integrated Completion Database and COMPANY document management system
shall be maintained.
The Completion database shall be organized per sub-systems, in a way to guarantee that each
critical document and certificate can be easily collected, retrieved and relevant system
completion progress checked accordingly.
While construction is carried out, CONTRACTOR shall record all missing items, discrepancies per
sub-system in the Master Punch List (MPL).
One item is considered as a stop point for concerned sub-system if:
• it challenges the safety or operational aspect of the following activity to be carried out on
the system;
• it does not satisfy requirements due to particular local rules and regulations.
CONTRACTOR shall manage punch lists according to the following three punch list priority levels:
PL B: items that are not considered as a stop-point for safe commissioning, and which are
however to be cleared prior to set the system in operation;
PL C: minor items not considered as a stop-point for safe start up, but related to a contractual
acceptance of the equipment and milestone.
• List of applicable Inspection & Testing (ITP’s, ITR’s and Quality records library);
• Subsystems “Mechanical Completion Certificate” and Hand-over to Commissioning;
Typical index and content of Fabrication Dossier, Mechanical Completion Dossier and Certificate
are provided respectively in Attachments 16.4 and 16.5. Index and content are indicative and
some could be not applicable to specific projects. If applicable, the documents listed therein shall
be considered as the “minimum required”.
The EX inspections as per COMPANY philosophy are not considered one separate activity, shall
be integrated instead in the regular Contractor QC inspection activity in terms of personnel
involved and QC records, without duplication of figure and certificate: one inspection, one ITR.
The CONTRACTOR shall upload all information regarding Ex equipment in a suitable Ex register
that shall be uploaded in the project completion system database (CCMS or other), completed
with inspection results. The as-built Ex register shall be included in Final Documentation for
Handover to Company.
• Tag Number;
• Reference Drawing;
• Serial Number;
• Manufacturer;
• Location;
• Equipment type;
• Zone;
• Gas Group;
• Protection Concept;
• Temperature Class;
• IP grade;
• Ex Certificate;
• Record of Inspection;
• Inspection Date;
• Inspector Name;
• Inspection Level;
• Remarks;
• Ex Compliance.
To achieve subsystem’ Mechanical Completion Status, the following steps shall be completed:
• Preparation, updating and upload of EX Register inside the Completion System database
(CCMS)
• Confirmation that Ex Item were properly installed (ITR A for installation) with the
signature of an Ex qualified inspector
• Confirmation of proper subsystem Area Completion with a dedicated ITR and inspection
verification completed by Qualified Ex inspector
Commissioning activities may affect the integrity of Ex equipment after Mechanical Completion
phase, therefore CONTRACTOR and COMPANY shall agree a clear operative procedure/instruction
to verify, at the end of Commissioning activities, that all Ex items affected by Commissioning
activities are still in compliance with EX regulation.
16 ATTACHMENTS
• PERSONNEL QUALIFICATION REQUIREMENTS;
• MATRICES FOR DISCIPLINE INSPECTION & TEST PLANS AND ITRs;
• DISCIPLINE ITPs AND ITRs;
• TYPICAL MECHANICAL COMPLETION AND FABRICATION DOSSIER CONTENTS.
16.2 MATRICES FOR DISCIPLINE INSPECTION & TEST PLANS AND ITRS