Professional Documents
Culture Documents
28934.ENG.CIV.STD
Rev. 00 – December 2021
REVISION TRACKING
INFORMATION REQUEST
For information about the content of this standard, please refer to persons mentioned on first
page or to Company Standard Team (mbxc&st@eni.com).
HIERARCHY OF REGULATIONS
INDEX
1 SCOPE OF THE DOCUMENT 6
2 DEFINITIONS AND ABBREVIATIONS 6
2.1 DEFINITIONS 6
2.2 ABBREVIATIONS AND ACRONYMS 7
3 UNITS OF MEASUREMENTS 7
4 REFERENCE CODES 7
4.1 COMPANY DOCUMENTS AND STANDARDS 8
4.2 INTERNATIONAL STANDARD 8
4.3 ITALIAN LAWS & DECREES 8
4.4 ORDER OF PRECEDENCE 8
5 GEOTECHNICAL INVESTIGATIONS 9
6 GENERAL: SOIL IMPROVEMENT METHODOLOGIES AND CHARACTERISTICS 10
7 TECHNOLOGY CLASSIFICATION AND ELEMENTS 11
7.1 PRE COMPRESSION OR PRELOADING 11
7.2 VERTICAL DRAINS 12
Applicability 13
Design Principle 13
Construction Considerations 15
Quality Assurance 16
7.3 VIBRO-COMPACTION 18
Applicability 19
Design Principle 20
Equipment 22
Quality Assurance 22
7.4 DYNAMIC COMPACTION (HEAVY TAMPING) 24
Applicability 24
Construction Considerations 25
Design Principle 25
Quality Assurance 27
7.5 STONE COLUMNS 27
Applicability 28
Construction Considerations 29
Design Principle 31
Quality Assurance 33
7.6 DEEP SOIL MIXING 34
Applicability 35
Construction Considerations 36
Design Principle 37
Quality Assurance 38
7.7 JET GROUTING 38
Materials 45
Design Principle 45
Construction Considerations 47
Equipment 50
Quality Assurance 51
7.8 OTHER INJECTION TECHNIQUES 54
Compaction Grouting 54
Permeation Grouting 55
8 POSITIONING 56
8.1 GEODETIC DATUM 56
8.2 SURFACE POSITIONING 56
8.3 VERTICAL DATUM 56
8.4 BENCHMARKS VERIFICATION 56
9 GENERAL DOCUMENTATION TO BE PRODUCED BEFORE COMMENCEMENT OF THE
WORK 56
10 DOCUMENTATION TO BE PRODUCED DURING THE WORK 56
10.1 SCHEDULES 56
10.2 DAILY PROGRESS REPORTS (DPR) 57
10.3 WEEKLY COORDINATION MEETINGS 57
10.4 MINUTES OF MEETING 57
TABLE
Table 7.1: Main Ground Improvement Techniques 11
Table 7.2: Backfill material rating criteria 22
Table 7.3: Typical Vibrators Specifications 22
Table 7.4: Suggested values of parameter Ec for different soil types. 26
Table 7.5: Threshold values of soil chemical parameters: Favorable Soil-Chemistry Factors 36
Table 7.6: Typical Improved Engineering Properties 37
Table 7.7: Design and Execution Activities 41
Table 7.8: Jet Grouting Parameters 48
FIGURE
Figure 7.1: Preloading 12
Figure 7.2: PVDs Installation 12
Figure 7.3: PVD scheme 14
Figure 7.4: PVD Installation operations 16
This document defines the material characteristics, the requirements, and the construction and
acceptance procedures of different soil improvement works including:
• Pre-compression or preloading
• Prefabricated Vertical Drains (PVDs) and Sand Vertical Drains
• Vibro-compaction
• Dynamic Compaction (Heavy Tamping)
• Stone columns
• Deep soil mixing
• Jet-Grouting
• Compaction Grouting
• Permeation Grouting
This document applies to the execution of soil improvement treatments, to be carried out for
refineries, industrial and power plants, camps, office, residential complexes, and all the other
typical works of the Energy Industry.
2.1 DEFINITIONS
Throughout this specification the following definitions shall apply.
Contractor: the firm responsible for the execution of the works defined in this
specification and in the Contractual Documents.
Reference Point: point toward all the investigations points are referred.
Work Data: the data decoded, corrected, validated, processed, etc. directly
in site, according to the requests described in this specification,
to satisfy the scope of work.
Final Data: the work data edited after the end of the survey in their final form
according to the requests described in this specification.
D.A.S.: the Data Acquisition System; i.e. all the transducers, antennas,
cables, connectors, interfaces, computer with peripheral facilities,
software and any other equipment to be installed in site to collect,
decode, correct, pre-process and store the data gathered by the
instruments described in this specification.
3 UNITS OF MEASUREMENTS
4 REFERENCE CODES
ENV 197-1:2011 Cement - Part 1: Composition, specifications and conformity criteria for
common cements
EN 1008:2002 Mixing water for concrete - Specification for sampling, testing and
assessing the suitability of water, including water recovered from
processes in the concrete industry, as mixing water for concrete
EN 1992-1-1:2004 Eurocode 2: Design of concrete structures General rules and rules for
buildings
EN 1997-1:2004 Eurocode 7: Geotechnical design - Part 1: General rules
EN 12716:2018 Execution of special geotechnical work
FHWA-NHI-16-027 Ground Modification Methods
ASCE Soil Improvement-History, Capabilities, and Outlook. J.K Mitchell, Editor,
ASCE, New York, NY, 182p
USACE Guidelines on Ground Improvement for Structures and Facilities.
Technical Letter No. 1110-1-185, Department of the Army. U.S. Army
Corps of Engineers, Washington, D.C., 42p.
USACE Compaction Tests and Critical Density Investigation of Cohesionless Materials
for Franklin Falls Dam. U.S. Engineer Office, Boston, MA.
Different reference codes may be proposed to Company and adopted only prior approval by the
Technical Authority.
International Standards are at the lower level of hierarchy. Their contents, assumed as
reference, is developed and detailed within the Company Specifications considering the specific
application and the area of business in which Eni SpA is operating. On top of those there are the
Local Regulations, the Project Specifications than the Company Specifications.
Any applicable local mandatory rule prevails on this specification. In case of a perceived conflict
between this standard and other referenced standards, or lack of clear definition as to the
applicability of any specification or standard, the Facilities Technical Units owner of the Standard,
shall seek guidance to the Standard Team.
5 GEOTECHNICAL INVESTIGATIONS
During excavation topsoil shall be removed separately and replacement undertaken in the
reverse order of excavation.
Under no circumstances shall personnel enter into unsupported or non-profiled pits that have
been excavated deeper than 1.2 meters.
If trial pits are to be left open for any reason, then these shall be clearly marked with high
visibility tape and barriered/fenced off until such time that these are backfilled.
Once completed, the trial pit shall be closed, topsoil and turf (if any) replaced, and the site left
tidy.
Soil improvement construction methods are used to improve poor/unsuitable subsurface soils
with respect to the loads to be applied, and/or to improve the performance of embankments or
structures.
These methods are used when replacement of the in-situ soils is impractical because of physical
limitations, environmental concerns, or is too costly. Ground improvement methodologies have
the primary function(s) to:
Table 7.1 shows the main ground improvement techniques classified by function. Considerable
overlap exists between the different techniques, as the same function can often be achieved by
means of different methods.
In general, this technique is used in clayey soil. Since clayey soils have low permeability, the
desired consolidation takes very long time to occur, even with very high surcharge load.
Therefore, depending on the construction schedule milestones, preloading may not be a feasible
solution. Hence, sand or prefabricated vertical drains may be used to accelerate consolidation
process by reducing the drainage paths length (see Section 7.2).
Two main types of vertical drains are typically adopted in industry practice: Prefabricated Vertical
Drains (PVDs) and Sand Vertical Drains.
PVDs, commonly referred to as ‘wick’ drains, shall consist of thin plastic strips about 1/8 inch
(3.175 mm) thick by 4 inches (101.6 mm) wide, with a rigid core sheathed in filter fabric. PVDs
are generally driven in the soil by means of hydraulic vibrators. The vibrating element is situated
at the head of the driving tube. In special cases a vibrating chuck can be employed with the
vibration being applied at various tube depths. Vibration driving allows rapid crossing of any
compacted layers above the layer to be drained. Average production can be between 200 to 500
linear meters (m) per hour. Depending on soil characteristics, driving speeds of up to 1.5 m/sec.
can be obtained. Average lengths are around 25 to 30 m, with the possibility of reaching depths
in the order of 40 m.
Sand drains involve the excavation of a vertical shaft filled with graded sand to act as a filter.
Average sand drain diameters vary from 25 to 40 cm and depths of 40 to 45 m can be reached.
Average production can be from 70 to 100 linear m per hour, depending on soil characteristics.
Due to the numerous advantages of PVDs with respect to sand drains, including lower cost,
higher installation speed, better control of drain continuity and lower displacement, sand drains
have been generally replaced by PVDs in current industry practice.
Applicability
PVDs are typically applicable to soil deposits having the following characteristics:
• Moderate to high compressibility (e.g. Liquid Limit greater than 30)
• Low permeability
• Fully saturated
• Final embankment loads must exceed maximum pre-consolidation stress
• Secondary compression must not be a major concern
• Normally to slightly over-consolidated (OCR < 1.5)
Design Principle
The primary purpose of a vertical drain is to reduce the length of the drainage path, thereby
decreasing the time required for the consolidation of low permeability soil layers. To accelerate
the rate of settlement, drains shall be installed on a regular grid pattern, either triangular or
rectangular, to reduce the flow distance for dissipation of excess pore water pressures associated
with the placement of a surcharge.
Prior to installation of vertical drains, theoretical predictions of the magnitude and rate of
settlement, both during and after construction, are typically needed to ensure the proposed
design meet the performance criteria required by project specifications. Vertical drains design
includes the dimensioning and assessment of the stability of the surcharge embankment.
In-situ testing (SPT, CPT and/or DMT) in the intervention area shall be carried out to determine
the need of pre-drilling for drain installation.
The design of the ground improvement intervention by means of vertical drains consists of the
determination of the type, spacing and length of the drains to meet the required performance
criteria (e.g. target degree of consolidation) within a specified time (see Figure 7.3).
The relationship between consolidation time, drain diameter and drain spacing for a given soil
can be expressed as follows:
(1)
And
(2)
Where:
7.2.2.1 Determination of FS
Soil disturbance is typically ignored (Fs=0) except for highly plastic (PI > 21), sensitive (St >5)
soils. For these soils an Fs=2 shall be used. Sample disturbance is typically more pronounced at
drain spacing lower than 5 feet or when large anchor plates are used.
7.2.2.2 Determination of Ch
The horizontal Consolidation Coefficient (Ch) can be obtained by means of laboratory
consolidation testing of high-quality samples. However significant uncertainty exists on the
determination of Ch, thus a typical approach is to set Ch equal to a given percentage of Cv
(which can be measured with higher reliability by means conventional oedometer tests).
In cases where the soil to be treated shows no or limited evidence of horizontal laminations or
layering, Ch can be taken as 1.2 to 1.5 times Cv.
In presence of substantial silt or sand lenses or laminae within the finer soil matrix, Ch can be
taken as 2 to 4 times Cv.
Where possible a robust estimate of the horizontal Consolidation Coefficient Ch can be derived
by the interpretation of CPT in-situ dissipation tests.
7.2.2.3 Determination of d
In the case of sand drains, the circular drain diameter (d) is taken as the nominal diameter of
the excavated shaft, while the equivalent circular drain diameter of a PVD typically varies
between 1.6 to 5.5 inches (40.64 to 139.7 mm), the most commonly adopted being 2.4 inches
(60.96 mm).
7.2.2.4 Determination of D
When using an equilateral triangular pattern, the diameter of the cylinder of influence (D) can
be determined as 1.05 times the drains spacing. Similarly, when adopting a square pattern, D
can be determined as 1.13 times the drain spacing.
Construction Considerations
Sand drains are typically installed by means of a technique involving the use of a water jet under
pressure for drilling and displacement of the soil. The excavated material is carried to the surface
in suspension by the rising flow of water, which at the same time keeps the shaft open until it is
filled with sand. In alternative, subject to the Company approval, the continuous auger technique
can be adopted, consisting of introducing a continuous auger into the soil to the desired depth
and then introducing the sand through the hollow shaft of the auger at the same time, as the
auger itself is withdrawn with a rotary movement.
PVDs are installed using equipment similar in size and characteristics to pile driving or foundation
drilling equipment. A typical installation rig for PVDs is shown in Figure 7.4. A clean sand layer
with minimum thickness of 0.3 m shall be placed at the top of the PVDs to excess pore pressures
relief. Furthermore, in some cases it may be appropriate to install horizontal strip drains across
the ground surface to remove the draining water from the treated area. Such drainage layer can
be installed as a part of the working platform necessary to make the site accessible to PVD
installation equipment.
Quality Assurance
Quality control during installation consists of recording depths and locations of each drain,
observing splices and verticality of the installation equipment and taking material samples for
inspection and testing.
To ensure proper performance, the drains shall be installed in accordance with the plans and
project specifications. It is important that field inspection personnel know the procedures and
possible implications of any deviation from the installation plan.
The construction monitoring personnel shall have access to the project drawings and
specifications and shall have experience in the general functioning of ground improvement
through PVDs installation, including site preparation, fill placement, and other items that might
influence the performance of PVDs.
In case of any variation to the pre-determined installation plan, the modifications and their
implication shall be discussed and approved by the Company.
The presence of obstructions within the treatment area could require offset of one or more drains
(in case of relatively small obstacles), while larger obstacles may typically require predrilling or
removal.
Other aspects, such as the drainage blanket material quality, embankment placement and
compaction, and surcharge loading rate, shall also be monitored during construction.
During construction of a working platform or drainage blanket, the field inspection personnel
shall monitor for any unusual soil movements, which may be indication of mud waving or a
potential failure.
7.2.4.2 Material
Prior to installation, the PVD material shall be visually inspected to verify compliance with the
samples previously submitted and tested, the core and filter jacket shall be continuous and meet
the specified size. Moreover, potential damages during handling or storage shall also be avoided.
Other tests might be required be carried out on PDV material prior to installation according to
project specifications.
7.2.4.3 Equipment
Inspection personnel shall verify installation equipment to comply with project specification
requirements. In particular, the following aspects shall be checked:
• Penetration method
• Mandrel shape, size, and stiffness
• Details of PVD anchorage
• Method to measure and determine penetration depth
• Method to measure and record installation force
• Means and procedures for pre-drilling, where necessary
• Size, type, weight, maximum pushing force, vibratory hammer rated energy, and
configurations of the installation rig
• Drains splicing methodology
7.2.4.4 Documentation
The following documentation shall be produced for PVD installation:
7.3 VIBRO-COMPACTION
Vibro-compaction (also known as vibro-flotation) is a ground improvement method that uses a
specialized vibrating probe for in-situ soil densification at depths beyond which surface
compaction equipment is ineffective.
The vibro-compaction process uses crane-mounted depth vibrators which are lowered into the
ground under their self-weight and thanks to their vibrating action. The vibrator is hung from a
crane cable or, in some instance, it is mounted to leads in a similar fashion as foundation drilling
equipment. The vibrator penetrates under its self-weight (or crowd of the machine if mounted
in leads). If needed, based on the soil characteristics, the water jets shall be used to aid
penetration. Once the probe has reached its target depth, backfill material is fed into the hole
to re-confine the probe. The backfill material is then forced aside radially by the vibrating action
of the probe, further densifying the surrounding soil. This operation may need to be repeated
multiple time at the same depth.
When operating below the water table, the vibrating action of the probe other than directly
displacing the soil around itself, causes the generation of excess pore pressure which may
ultimately overcome the acting vertical effective stress and hence induce a liquefied state in the
surrounding soil. Following the cease of probe induced vibration (or when the probe is pulled-up
to shallower depth), the induced excess pore pressure dissipates causing re-consolidation of the
soil to a denser state with respect to initial conditions.
Applicability
The applicability of vibro-compaction intervention shall be assessed based on the grain-size
distribution of the soils to be treated, as shown in Figure 7.6.
Soil compaction through the rearrangement of soil particles, as achieved in the vibro-compaction
process, is not possible in fine-grained soils (Zone D in Figure 7.6), since the cohesion between
the particles prevents rearrangement and compaction from occurring. For these soils the vibro-
replacement method (i.e. ‘stone columns’) is recommended.
For soils falling in Zone C, gravel (instead of sand) shall be used as backfill during the compaction
process. This is because gravel improves the contact between the vibrator and the treated soil,
resulting in increased compaction.
Design Principle
The performance of the vibrator shall be controlled by adjusting the rate of advancement and
withdrawal, and hence the application time of the vibrating action. Nevertheless, the maximum
performance of each vibrator in terms of target relative density is typically expressed as function
of the tributary area per compaction point and soil type.
For a given soil type, the larger the tributary area, the lower is the maximum relative density
that is achieved with that vibrator. Figure 7.8 provides an example of a vibrator performance
chart. The target DR is generally limited to 85 percent since this density level typically guarantees
increasing bearing capacity and resistance to liquefaction as required by design calculations.
Other than compaction point spacing, their distribution (compaction point pattern) also affects
the performance. An equilateral triangular pattern is generally recognized to be the most
efficient, in particular for large areas. The use of a square pattern in place of an equilateral
triangular pattern requires from 5 to 8 percent more points to achieve the same target density.
Figure 7.8 shows an example of equilateral triangular compaction point grid, considering a
tributary area per compaction point of 3.14 m2 (equivalent column diameter of 2 m) and a target
relative density of 80%. Vibro-compaction can be used to treat limited areas targeting individual
footings. Figure 7.9 shows typical patterns adopted for this type of application.
shall consist of sand or sand and gravel, with less than 10 percent by weight passing the #200
sieve and containing no clay.
Backfill material shall be rated based on its grain size distribution using the Suitability Number
(SN). This parameter can be calculated as:
(4)
Where:
Equipment
Typical high-powered, probe-type, vibrators range between 0.3 m to 0.4 m inches in diameter
and 3 m to 4.5 m in length. The maximum dynamic force imparted by the vibrator ranges
between 150 kN and 450 kN, with vibrating frequencies ranging from 1800 to 2300 revolutions
per minute (rpm). Lower frequency and larger amplitude of vibration typically result in better
densification, since the natural frequency of loose cohesionless soil is typically lies closer to the
lower end of the operating range.
Quality Assurance
The quality assurance plan and inspection activities shall be developed well in advance of the
vibro-compaction work.
Continuous monitoring of the above parameters is essential since the duration required to
achieve a given target density can vary significantly from depth to depth and from location to
location, depending on local soil conditions. Generally, the finer the soil, the longer the time
required to achieve a target degree of compaction. A data logger shall be used for monitoring
and recording of the above parameters. In addition, the current absorption by the electric motor
can also be correlated to soil density and shall therefore also be monitored.
During the compaction process, the compaction shall periodically be verified for quality control
and acceptance purposes. A number of methods can be used for QC purposes of vibro-
compaction interventions, including in order of increasing accuracy:
• Standard Penetration Testing (SPT)
SPT resistance can be correlated with relative density and with the soil properties needed
to estimate settlement and bearing capacity. Data shall not be obtained before pore
pressures have dissipated, in order to avoid the penetration resistance to be not
representative of the actual degree of soil improvement. SPT data are usually taken at
1.5 m intervals.
• Cone Penetration Testing (CPT)
CPT testing overcomes most of the SPT weaknesses. The CPT is relatively inexpensive
and can be correlated directly to expected settlements in compacted areas. The cone
resistance, however, will underestimate the degree of improvement if excess pore
pressures are present.
• Measurement of surface subsidence
This method allows monitoring of the average increase in relative density when the fill
material is obtained from the compacted area. This method shall be preferred when
compaction is to be checked over large areas and the quantity of imported fill is known.
• Density measurements on undisturbed samples
This method allows a precise estimate of the density and hence compaction, however it
requires the collection of undisturbed sampling which is seldom achievable in
predominantly granular deposits.
• Downhole nuclear densimeters
This method allows a precise estimate of in-situ density, overcoming the challenges of
obtaining undisturbed samples. A small diameter aluminum pipe shall be placed in the
ground prior to compaction, reaching down to the planned treatment depth. A site-
calibrated nuclear probe shall be lowered down the casing before and after compaction,
to obtain a continuous density/moisture-content profile. The main limitations of this
technique are related to the limited radial penetration of the probe (150 mm) and to the
fact that requires specialized equipment and personnel, which are typically difficult to
source.
7.3.4.1 Documentation
During vibrocompaction works, a document shall be produced for each compaction-point, with
the following minimum content:
Applicability
Dynamic Compaction method is applicable for a wide variety of soil conditions including
saturated/unsaturated loose sands, even with the presence of silty pockets, dune sands,
inorganic fill, reclaimed soils with variable characteristics and sizes even with the presence of
large sized boulders, landfill deposits and collapsible soils. Dynamic Compaction has been
extensively used to compact loose soils to depths of up to 10m, in order to increase the bearing
capacity, decrease post construction settlement and mitigate liquefaction risk in case of seismic
events.
Key features:
• Applicable for wide range of soils with fines content up to 35%, down to significant depths
up to 10m.
• Very fast production (more than 50,000 sq.m/crane/shift/month).
• Well adapted to large scale projects ‐ Increases the bearing capacity of soils, reduces the
post-construction settlements and eliminates the risk of soil liquefaction in case of seismic
events.
• With a global treatment, Dynamic Compaction can be undertaken ahead of the foundation
design.
• Very sustainable technique: no disposal, no aggregate, no cement.
• Process somewhat invasive, the surface of the soil may require shallow compaction with
possible addition of granular fill following dynamic compaction.
buildings, tanks, artificial islands, road and railway embankments, land reclamations. Dynamic
Compaction technique was implemented as value engineering alternative to deep foundation or
soil replacement for a large number of structures throughout the world.
Construction Considerations
Dynamic compaction equipment only requires:
• A lifting crane able to lift and to drop the pounder from the design height
• A bulldozer to backfill and level out the created print craters
• A pounder of a pre-established weight and contact area
Execution of dynamic compaction work shall be started with a trial area to calibrate and verify
the design, especially when the job is carried out on soil layers where there is no prior similar
experience. The minimum size of the trial area is 2D x 2D square grid, where D represents the
required improvement depth.
Design Principle
Dynamic compaction design shall start by determining the required depth to be improved. The
purpose of the treatment (e.g. liquefaction mitigation, improving the soil’s bearing capacity) is
the governing factor in determining the required improvement depth. Once D is determined, the
next step is to estimate the pounder weight, height of drop, and cumulated energy necessary to
achieve the target improvement depth. The weight and the drop height of pounder shall be
estimated by using the following empirical formula:
𝐷𝐷 = 𝑛𝑛 ∙ √𝑊𝑊 ∙ 𝐻𝐻
where D is the target improvement depth (m), W is the pounder mass (ton), H is the height of
drop (m), and n is an empirical factor varying from 0.3 to 0.9. Figure 7.11 shows the influence
of coefficient n for different soil types.
It shall be noted that different combinations of W and H can be associated to a given target
depth D for a given soil type. Typically, given a pounder of mass M the height of drop is adjusted
to achieve the required performance.
The average energy (Ea) required to compact a given area down to a given target depth shall be
estimated as follows:
𝐸𝐸𝑎𝑎 = 𝐸𝐸𝑐𝑐 ∙ 𝐷𝐷
Where Ec is the empirical dynamic compaction cumulative energy and represents an estimate of
the energy required for compaction of a cubic meter of soil. Table 7.4 summarizes suggested
values of Ec for different soil types.
The estimated number of blows (Nunit) required to densify per unit area of the ground shall be
determined as:
𝑁𝑁𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 = 𝐸𝐸𝑎𝑎 /(𝑊𝑊 ∙ 𝐻𝐻)
The poundings are normally carried out in a square grid pattern with a pounding point centre to
centre distance, herein denoted as S. Note that the pounding point is usually termed as print.
The distance S typically varies between 1.5 to 4 times the pounder diameter. Hence, the total
number of blows at every print shall be estimated as:
𝑁𝑁𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 = 𝑆𝑆 ∙ 𝑆𝑆 ∙ 𝑁𝑁𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢
In actual dynamic compaction execution, the number of N blows calculated above shall not be
carried out at one go. At every print point, the pounding is stopped when the cumulative blow
energy has reached saturation stage. The pounding saturation stage shall be defined as follows:
a) When the depth of the crater created by the blows has reached the height of the pounder
plus 25cm. This is meant for the ease of pulling up the pounder out of the crater.
b) When the ground around the print started to show heaving phenomenon. This is normally
due to the increase of pore water pressure.
In case a, the blow can be directly restarted after the crater is backfilled or flatten out. In case
b, the blow is restarted when the excess pore water pressure has been dissipated and the crater
is backfilled or level out. This second stage of pounding series is restarted/repeated at the same
print point as the previous stage, the pounding series is named as pass two, while the previous
series of blows is named as pass one. Subsequent stages of blows on the same print points, if
any, are named accordingly.
Note that the above criteria shall serve as general guidance only. A more accurate estimate of
saturation stage can be obtained by measuring directly the crater volume (Vd) and side heave
(Vh) after each blow of the pounder. Pounding shall be stopped when compaction efficiency (Ef)
reduces below 40%, with Ef given by:
Considering that this operation is time consuming, it is typically carried out on trial areas.
Pounding shall not be directly applied in one phase with S by S square grid but spread over two
phases or more. If the poundings are spread over two phases, then the execution pattern shall
be as presented in Figure 7.12.
Quality Assurance
The ground shall be periodically tested during the progress of the compaction works for control
purposes, to assess the effectiveness of the treatment and confirm that the specified level of
compaction will achieve the degree of improvement required. Quality control testing during
treatment shall involve in-situ penetration tests (e.g. CPT or SPT) which shall form part of the
final assurance testing. The frequency of testing will be affected by factors specific to each
project, as for example, the variability of the ground before treatment, the nature of the
structure to be supported and its sensitivity to post-treatment movements.
Stone columns are used to improve the stability of slopes, increase bearing capacity, reduce
total and differential settlements, and decrease the time for these settlements to occur. In
addition, Stone columns can be used to improve the stability of a slope by creating discrete
zones of high strength material that will provide more resisting force along the potential failure
surface.
The stone columns will also provide a conduit for the flow of ground water, thus decreasing the
time for settlement similarly to PVDs. Lastly, stone columns are used to mitigate the potential
for liquefaction through densification of the in-situ materials and by providing pore pressure
relief zones, because the stone column will have a greater hydraulic conductivity than the in-
situ sands.
Other than conventional stone columns, this section also discusses other variations of the
methodology such as:
• vibro-concrete columns (VCCs)
• geotextile-encased columns (GECs)
• Geopier® Rammed Aggregate Pier™ (Geopiers)
Stone columns allow to replace deep foundations with shallow foundations. Stone columns also
provide a less expensive option to cut and replace, particularly on large sites with shallow
groundwater. In developed areas where high-vibration methods such as dynamic compaction,
deep blasting, or pile driving would have an impact on adjacent properties, low-vibration stone
columns may provide a viable alternative of ground improvement. The use of stone columns
could decrease the time required for construction by allowing construction to proceed
immediately instead of waiting for the placement of surcharge. In areas that have a potential
for liquefaction, the installation of stone columns can improve the cyclic resistance ratio. In
addition, stone columns can provide vertical drainage and storage capacity to dissipate excess
pore pressures induced by a seismic event.
However, stone columns have limited applicability in terms of soil conditions. In addition, stone
column construction can be hampered by the presence of dense capping layers, boulders,
cobbles or other obstructions that may require pre-drilling prior to installation of the stone
column.
Applicability
Stone columns are a natural development of vibro-compaction methods, extending vibro-system
applications beyond the limited application to clean granular soils (Figure 7.13). Since the
strength and settlement characteristics of stone columns are controlled by the mechanical
properties of surrounding soil, their application shall be avoided in soil profiles including layers
of very soft clay or peat with thickness larger than the diameter of the column.
Construction Considerations
Stone columns are constructed using either vibro-replacement or vibro-displacement techniques.
Vibro-replacement refers to the wet, top feed, process in which jetting water is used to aid
penetration of the vibrator within the ground. Due to the jetting action, part of the in-situ soil is
washed to surface and then replaced by backfill material. The sequence of operations of a vibro-
replacement intervention shall be as follows:
• A high-pressure water jet is used to open a hole for the vibro-probe to follow into
• Once the tip elevation is obtained the vibro-probe is retracted and stone is then placed
into the hole from the top
• The vibro-probe is then turned on and inserted into the stone to densify the stone
• The last step is repeated at different levels until the stone column is formed
The vibro-replacement method shall be used limited to sites with soft to firm soils having
undrained shear strength ranging between 10 and 50 kPa, and shallow groundwater table.
Vibro-displacement refers to a dry, top or bottom feed process; almost no in-situ soil appears at
the surface, being displaced aside by the backfill material. This method is typically used when
environmental impact (i.e. groundwater contamination) is of particular concern. This is because
the vibrator is inserted into the ground without the use of jetting water, thanks to the vibrating
action of the probe in conjunction with its deadweight, air jetting and/or pre-augering, depending
on the specific application. The top feed method (Figure 7.14) shall be preferred for short stone
columns, while for deeper columns, or where the potential for hole collapse exists, the bottom
feed method (Figure 7.15) shall be preferred.
Concrete shall be pumped through the vibrator assembly during initial withdrawal. The poured
concrete shall then be re-penetrated by the vibrator, displacing it into the surrounding soil to
form a high capacity, enlarged column base. The vibrator shall then be slowly withdrawn as
concrete is pumped and maintained at a pressure to form a continuous shaft of concrete up to
the ground level. At ground level, a slight ‘mushrooming’ of the concrete column shall be allowed
to aid load transfer to the vibro-concrete column.
This method combines the ground improvement advantages of the vibro-systems, with the load
carrying characteristics of a deep foundation. The installation of VCCs is a quiet process and
induces minimal vibrations into the in-situ soils allowing for installation immediately adjacent to
existing structures. Since this is a dry displacement process, there is no spoil to remove and no
water requiring detention. VCCs have the additional advantage of being able to extend through
thick very soft clays and organic materials.
GECs can be installed using either the replacement or the displacement methods. The
replacement method consists of driving an open-ended steel pipe pile to the bearing stratum.
The soil within the pile shall then be removed by means of an auger, then the tube inserted into
the pile and filled with sand or fine gravel.
The displacement method uses a steel pipe with two base flaps which close upon contact with
the ground surface. The close ended steel pipe shall be vibrated to the bearing layer, displacing
the soft soil. The geotextile casing shall then be installed and filled with sand or fine gravel.
In both methods the steel pipe shall ultimately be vibration extracted. During this process the
sand or gravel within the geotextile is densified.
The major advantage of GECs over stone columns is that they can be used in soft soils with
undrained shear strengths as low as 2 kPa. The geotextile provides the lateral constraint that
the surrounding soils must provide for stone columns. GECs provide excellent vertical drainage,
which may result in very rapid construction, due to the dissipation of pore water pressure.
For this technique to be successfully applicable, the hole shall be stable without internal support
(i.e., casing). Gravel shall be placed in relatively thin lifts with the first lift of gravel forming a
bulb at the bottom of the pier.
Once gravel from the bottom lift is in place, the soil underneath and around the base of the pier
shall be pre-stressed and pre-strained by a ramming process. High energy (3500 kN/m to 10000
kN/m) beveled tamper are typically used for ramming, to densify the gravel as well as force it
laterally into the sidewalls of the hole. This action increases the lateral stress in the surrounding
soil, further stiffening the stabilizing the composite soil system.
Geopiers have similar advantages to stone columns. The main disadvantage Geopiers is that this
type of ground improvement relies on proprietary, patented, technologies.
Design Principle
According to current industry best practice the design of stone columns is still largely empirical;
however, general design guidelines have been developed and are discussed in this section.
The soils surrounding the columns shall provide lateral support to prevent bulging under the
applied axial loads. In addition, the columns shall terminate in a dense formation to prevent
bearing failures.
Stone columns are typically stiffer than surrounding soil, thus the applied load mostly distributes
among the columns themselves. Soil arching allows for load transfer in between columns.
Ultimately equilibrium is reached when the acting load has been transferred to the columns to
prevent further settlement of the surrounding soils.
Bearing capacity analyses shall be carried out based on industry standard analytical methods
(i.e. according to the Priebe method), considering equivalent strength parameters for the soil-
column system.
The geometry of the unit cell shall be pre-defined based on the characteristics of the soil to be
improved and of the equipment to be adopted. This can be achieved by estimating the following
parameters:
The definition of these parameters is given in the following sections and their estimate is
generally based on the experience of the designer and/or on results of filed trial tests.
The Area Replacement Ratio (αs) is a parameter depending on the area of the soil replaced by
the stone column. αs is calculated as the ratio of the tributary area of the unit cell to the area of
the stone column. The more soil is replaced by the stone column, the higher its performance.
Typical values of αs range from 0.10 to 0.40.
(5)
(6)
Where:
• αs = Area replacement ratio
• As = Area of the stone column
• A = Total area within the unit cell
• as = Area improvement ratio
This assumption, known as the ‘equal strain assumption’, has been validated by both field
measurements, as well as numerical simulations. The ratio of the stress in the stone column to
the stress in the in-situ soil is known as ‘Stress ratio’:
(7)
Where
σs = Stress in the stone column
σc = Stress in the surrounding soil
Measured values of n typically vary between 2.0 and 5.0. Furthermore, theory indicates that n
increases with time. A high n-value (3 to 4) shall be achieved in very weak soils, to avoid
excessive bulging of the columns. Lower values of n (2 to 2.5) are acceptable when the
surrounding soil is stronger and/or the column spacing is wider. For preliminary design, a
conservative n-value of 2.5 shall be targeted.
Quality Assurance
A comprehensive stone column Quality Assurance (QA) assessment program usually consists of
several QA methods, and concerns both the backfill material as well as installation operations.
For what concerns the fill material, gradation, specific gravity, minimum and maximum density
tests shall be run on the fill material to be adopted, typically with a frequency of one test every
5,000 tons of material.
In-situ testing shall be specified to assess the effect of the stone columns on the native soil.
However, the in-situ test method shall be selected based on its ability to measure changes in
lateral pressure in cohesive soils.
The electric cone penetrometer test (CPT), the flat plate dilatometer test (DMT) and the
pressuremeter test (PMT) represent the best in-situ testing methods to measure the change, if
any, in lateral stress following stone column construction.
Stone column performance is dependent upon the integrity of the column. It is important to
comply with the specified minimum column diameter and stone density, in order to ensure the
desired performance. During construction stone consumption shall be continuously monitored
by logging the subsequent dumps of known volume as a function of the achieved depth, to
estimate the achieved column diameter based on the adopted fill volume and the in-place stone
density.
For any group of 50 consecutively installed stone columns, the average diameter over the total
length shall not be less than the target value reported in the project specifications.
No stone column shall have a diameter less than 90% of the minimum diameter reported in the
project specifications.
Verticality of the rig shall be monitored, and no stone column axis shall be inclined from the
vertical by more than 5 cm in 3 m.
During construction of the column, each lift shall be re-penetrated until the specified current
consumption of the vibrator’s motor is achieved, thus indicating good input energy from the
vibrator probe to the stone. Typically, the target current consumption shall be taken equal to
the vibrator free-standing current reading plus at least 40 Amperes.
For projects requiring the improvement of large areas, it is desirable to subdivide the total area
into approval or acceptance zones of the order of 100x100 feet.
7.5.4.1 Documentation
During stone columns installation works, a document shall be produced for each column, with
the following minimum content:
Deep soil mixing is used for a variety of applications including excavation support, soil
stabilization, settlement reduction, foundation support, and mitigation of liquefaction potential.
Deep soil mixing is performed under many proprietary names, acronyms and processes
worldwide. However, the basic concepts and procedures are similar for all techniques. Different
techniques exist differing in the following main aspects:
• Location of the mixing action: at the end of the drilling tool (E) or along the shaft (S)
Irrespectively of the technique adopted, deep soil mixing uses the in-situ soil, making this
method typically more economical than removal and replacement. This is because little to no
spoil is generated, thus eliminating the high cost of spoil disposal. Thanks to these
characteristics, this method provides an economic benefit when compared to other conventional
soil improvement methods. However, costs involved in this type of application depend on several
project factors including size, weight, and flexibility of the structure, depth, and shear strength
of the compressible layer, the risks, and consequences of failure and the effects of lowering the
groundwater table.
The limitations of wet deep soil mixing are the relative high cost of mobilization of the mixing
equipment plus the cost of the associated auxiliary batch plants. Because of this reason, wet
deep soil mixing is generally uneconomical for small projects. Extensive geotechnical exploration
of the area is generally required prior to wet deep soil mixing operations. Bench scale testing
must be conducted and may require several months to complete.
On the other hand, a possible limitation in the application of dry methods is that the full strength
of the columns is not mobilized when the pH of the groundwater is acidic, or the content of
carbon dioxide (CO2) is high.
Low strength development shall also be anticipated when mixing non-reactive cohesive soils
(clays lacking pozzolans). The air-driven injection process may accumulate large quantities of
air in the ground potentially causing heave of the adjacent ground surface. This problem can be
eliminated by adding mixing paddles to the mixing tool and/or substantially increasing the mixing
time. The creep strength of the columns and the shear strength of the stabilized soil is time
dependent. Therefore, several months may be required to perform the laboratory bench scale
testing target.
The average shear strength of the stabilized soil shall be at least three to five times the initial
shear strength for dry deep soil mixing to result economical.
In general, there is a lack of well-developed design methodologies available for both wet and
dry deep soil mixing, as well as no standardized method of quality control testing, making design
verification difficult and subjective.
Applicability
Wet deep soil mixing methods have been used to stabilize soil to provide an improved foundation
bearing capacity and for seismic stabilization. The most common usage is for settlement control
and/or shear strength improvement under embankments.
The problems associated with disposal of the waste material are generally considerably reduced
with respect to other methods. Although this depends to the percentage of additives used and
the moisture content of the in-situ soils. Spoil generation can range from thirty to one hundred
percent depending on project specifics, equipment and methods used, and in-situ moisture
content.
These columns are stiffer and relatively less compressible than the surrounding soil; therefore,
carry a greater portion of the applied load thus reducing total and differential settlement. The
amount of settlement reduction is a function of the area replacement ratio and the stress
concentration ratio, which is a function of the column stiffness compared to the untreated soil.
Dry deep soil mixing columns are also used to reinforce existing soils by increasing the mass
shear strength, thus increasing the stability of embankments and slopes. Typically, the columns
are placed in a grid pattern under the embankments and in interconnected rows under the slope
to provide resistance to bending.
Another typical application of lime, cement, or lime-cement columns is to increase the stability
of anchored sheet pile walls. The columns increase the passive earth pressure at the toe of the
wall. In addition, columns placed behind the wall can reduce the lateral earth pressure acting on
the sheet piles.
Using lime or lime-cement columns can reduce the consolidation time required beneath a
roadway embankment by increasing the permeability or stiffness of the columns.
Construction Considerations
The construction process is similar to a drilling process, which is ideal in noise and vibration
sensitive areas. However, specific and detailed considerations about the soil’s chemical
composition and preliminary testing of the soil-reagent mixtures are required for the correct
application of this technique.
Table 7.5: Threshold values of soil chemical parameters: Favorable Soil-Chemistry Factors
The samples shall then be tested for unconfined compressive strength at various curing times to
determine strength gains with time.
Test results shall be compared to the typical results presented in Table 7.6.
Design Principle
Deep soil mixed columns are designed similarly to stone columns, based on the ‘unit cell’
concept. When used for settlement reduction, area replacement ratios on the order of 0.2 to 0.3
shall be targeted for triangular or square column patterns, respectively. Larger area replacement
ratios are indicative of more stringent settlement criteria.
Large area deep soil mixing columns are suitable to support structures provided that stability
(bearing, sliding and overturning) and performance (total and differential settlement)
verifications are satisfied.
Deep soil mixing columns are suitable to mitigate the potential for liquefaction by either confining
the liquefiable material in-between columns, or by increasing the Cyclic Resistance Ratio (CRR)
of the treated soil.
The transfer of the applied load to the soil mixed columns to the in-situ soils depends on the
relative stiffness of the soil mixed columns to the in-situ soils as well as the spacing and diameter
of the soil mixed columns themselves. Because the stone columns and the in-situ soils settle
approximately equally (‘equal strain assumption’), the stone columns generally carry a larger
portion of the load than the surrounding soils.
The total undrained shear resistance of the stabilized soil is assumed to correspond to the sum
of the shear strengths of the column and the soil between the columns and is evaluated based
on the following formula:
(8)
Where:
τf = Undrained shear strength of soil mixed column
Cu = Undrained shear strength of soil between columns
Area replacement ratios of 0.20 to 0.33, and stress ratios of between 4 and 6, are typically
adopted for either block or column-type patterns (see Figure 7.18).
Quality Assurance
The properties of the improved ground require verification to ascertain whether the requirements
of the project are being met.
Laboratory (bench scale) testing shall be conducted to verify that proposed construction methods
and mixes comply with project specifications. After completion of the mixing, either in-situ
testing or laboratory testing on retrieved cores shall also be performed.
The in-situ testing shall consist of cone penetrometer testing (CPT), dilatometer testing (DMT),
standard penetration testing (SPT), or pressuremeter testing (PMT).
a) b)
Figure 7.20: Jet grouted diaphragm (a) or slab (b)
Figure 7.22: Jet grouting single fluid system: main steps and monitor details
Figure 7.23: Jet grouting double fluid (air) system: main steps and monitor details
In a double fluid (water) jet grouting system the disaggregation of the soil is achieved by a high
energy water jet while cementing is simultaneously obtained by a separate grout jet (Figure
7.24).
Figure 7.24: Jet grouting double fluid (water) system: main steps and monitor details
Figure 7.25: Jet grouting triple system: main steps and monitor details
Materials
Unless otherwise specified, the properties of the materials shall comply with European standards
(e.g. EN 1008, ENV 197-1).
Mixtures composed of water and cement are usually adopted. Hydraulic binders other than
cement can also be used. In water/cement mixes the water/cement ratio by weight shall range
between 0.5 and 1.5. Water reducing, stabilizing, plasticizing, waterproofing or anti-washing
admixtures can be added to the water/cement mix. Other materials, such as bentonite, filler and
fly-ash can also be added to the mix. When bentonite is to be used in the mix, a water/bentonite
suspension shall be prepared before adding cement.
Any recognized potable water is acceptable for the preparation of jet grouting mixes. Water from
sources other than recognized potable water suppliers shall be analyzed in order to ensure that
it will have no adverse effect on the setting, hardening or durability of the mix and, where
applicable, will not promote corrosion of the reinforcement.
If the cement does not comply with the standard ENV 197-1, appropriate tests shall be performed
to ensure that the setting time, hardening, strength and durability requirements, as stated by
design specifications, are met.
Care shall be taken to ensure that no large particles are present in the jetting materials, as they
can block the nozzles.
Acceptance criteria and water testing methods shall conform to EN 1008.
Where reinforcement consists of steel bars, the material shall comply with EN 1992-1-1- clause
3 and 6 as appropriate. Where material other than steel bars is used for reinforcement, it shall
comply with national standards or with design technical specifications.
Design Principle
7.7.3.1 General
Typical jet grouting applications include:
• providing foundations for structures;
• underpinning existing foundations;
• creating low permeability barriers;
• creating retaining or supporting structures;
• complementing other geotechnical works;
7.7.3.2 Geometry
The cross-sectional dimensions of a jet grouted element depend on the jet grouting system, on
the jetting parameters and on the soil type and its heterogeneity.
Unless noted otherwise within the project specifications, the design shall consider the
construction tolerances indicated in paragraph 7.7.4.3and 7.7.4.4.
The following shall be clearly shown on design drawings:
7.7.3.4 Permeability
Where jet grouting works are employed to control groundwater, the results depend on the
geometric accuracy of the elements and on the permeability of the jet grouted material.
Permeability requirements shall be defined in the design in terms of type of tests to be performed
at site and acceptance criteria. The design shall specify requirements both on the jet grouted
material permeability, and of the overall jet grouted structure (e.g. diaphragm wall)
permeability. The overall permeability of a jet grouted structure shall be evaluated considering
the effects of deformation due to excavation or other loading conditions at full scale.
Construction Considerations
The most common jet grouting execution methods consist of:
• Jet grouted column execution method. The phases of execution usually consist of:
o drilling a borehole of a predetermined length;
o introducing to the end of the borehole a monitor connected to the jet grouting
string. This is unnecessary in some cases as the string and monitor may be used
for drilling;
o jetting of the disaggregating and cementing fluid(s) through the monitor,
simultaneously withdrawing and rotating the rods, with pre-established
withdrawal and rotational speed, pump pressure and flow rate for each fluid.
• Jet grouted panel execution method. For a jet grouted panel, the phases of execution are
the same as defined for jet grouted columns, with the exception that during jetting the
rods are withdrawn without rotation or rotated of limited angles.
If required by soil conditions, based on the findings of the geotechnical report, alternative
execution methods may be adopted, both for column and panel processes. Among alternatives
the most used method is pre-jetting. It should be noted that an element can also be executed
in sequential steps: the treatment for a given length from the borehole collar is completed first
and allowed to gain strength. Then, after redrilling the treated soil, the process is repeated at a
deeper section, and so on, until the design length of the treatment is reached.
The following sections provide requirements and recommendations for the various construction
phases of a jet grouting process.
7.7.4.3 Drilling
Drilling can be performed with air or water or muds or grouts or foams as flushing media. If
required for hole stability, casing shall be used.
The deviation of the drilling starting point from the theoretical location shall be less than 50 mm,
if not otherwise stated by the design specifications.
Drilling shall not exceed an inclination of 2% from the theoretical axis, if not otherwise stated
by the design specifications.
The annular space between the drilled hole and the jet grouting string shall allow a free flow of
the spoil return to the borehole collar.
7.7.4.4 Jetting
Jet grouting operations shall be executed and supervised by trained and experienced personnel.
In underpinning applications, it shall be ensured that contact is formed between the top surface
of the jet grouted column and the underside of the foundation.
Jet grouting shall be executed with a thickness between the upper nozzle and the ground surface
ranging from 0.5 m for vertical columns to 2.0 m for horizontal jetting, to avoid possible local
hydrofracturing, and shall be reduced only in the presence of a restraint to the surface, such as
a slab or a wall.
For horizontal jet grouting the collar of the borehole shall be plugged as soon as jet grouting is
completed.
In case of jet grouting interruptions, the re-start shall be undertaken using procedures (to be
detailed in the execution method statement) that are intended to ensure the continuity of the
element.
Equipment
The jet grouting equipment usually comprises:
• the drilling rig;
• the jet grouting rig (often same as drilling rig) provided with the jet grouting string, the
monitor and the devices able to drive the jet grouting string at predetermined rotation
and translation speeds;
• the mixing and pumping plant supplying the jet grouting fluid (or fluids);
• the high pressure lines connecting the jet grouting pump to the rig;
• equipment to monitor pressures, fluids flow rates and volumes, rate of rotation and
withdrawal, depth.
The jet grouting equipment shall be able to perform the jet grouting operations assuring:
• the translational and rotational movement of the jet grouting string with the designed
speed;
• the supply to the jet grouting string of the fluids coming from the plant, at the required
pressure and rate of flow.
The length of the jet grouting string, and the height of the relevant mast, shall not be shorter
than the length of the designed jet grouted element. If required by the large depths or by access
limitations, the string shall be divided into a number of elements, in order to minimize the need
to interrupt the jet grouting operation.
The jet grouting string shall include:
• for the single fluid system: one conduit conveying the high-pressure cement mix to the
monitor;
• for the double fluid system: two conduits separately conveying the two fluids (air and
cement mix, or water and cement mix respectively) to the monitor;
• for the triple fluid system: three conduits to allow for the high-pressure water, the
compressed air and the cement mix to the monitor.
The monitor shall comprise:
• for the single fluid system: one or more circular nozzles for jetting the grout. Multiple
nozzles are located at the same level or at different levels, with constant mutual
staggered angles;
• for the double fluid (air) system: one or more double nozzles (located at the same level
or at different levels, with constant mutual staggered angles) to allow the simultaneous
jetting of air and grout. The air nozzle is an annulus around the circular nozzle for grout;
• for the double fluid (water) system: one or more nozzles for high pressure jetting of water
and one or more deeper nozzles for sending the cement mix;
• for the triple fluid system: one or more double nozzles to allow the simultaneous jetting
of air and water and one or more simple nozzles located at a deeper level to allow the
grout injection.
In general, the air-water and grout nozzles for each couple are set at 180° apart. Multiple couples
are installed at constant mutual angles.
The jet grouting mixing and grouting plant, for the different systems, typically comprises:
• for the single fluid system: cement and other materials storage, colloidal mixing plant,
agitator tanks, high pressure grout pump;
• for the double fluid (air) system: as for the single fluid system plus an air compressor;
• for the double fluid (water) system: as for the single fluid system plus a high pressure
water pump;
• for the triple fluid system: as for the double fluid (water) system plus an air compressor.
Quality Assurance
7.7.6.1 General
The following characteristics of jet grouted elements shall be monitored for control purposes:
• geometry;
• strength, deformability, permeability or density of the jet grouted material.
It is generally impractical or impossible to measure the dimensions and material properties
directly on a statistically significant number of jet grouted elements. The minimum quality control
of jet grouting shall consist of reporting the jet grouting parameters and observing the spoil
return on all elements.
In jet grouting works, after the first few elements have been produced, measures of the
dimensions and material properties shall be taken on a limited number of elements to establish
the relationship between the jet grouting parameters and the element properties.
Where comparable experience (as defined by EN 1997-1- clause 1.5.2) on the same jet grouting
system in similar ground conditions is available, testing after execution may be omitted, if the
design specifications do not require it and provided that monitoring of jet grouting parameters
is applied to the jet grouted elements of the work.
performing cross-hole tests. Small strain (e.g. strains < 10-4) stiffness moduli (E and G)
can be directly obtained from the velocity measurements from cross-hole tests with a
good reliability;
• Static cone penetration test (CPT). The geometry of a jet grouted element can be
assessed by CPT's performed through the element before grout hardening. This method
applies mainly to jet grouted elements created in soil with high penetration resistance
compared with the low resistance of the fresh grouted material;
• Other test methods. In specific cases and following design specifications, SPTs (standard
penetration tests), dynamic cone, or pressure meter may be used to check jet grouting
results.
• When coring is performed, the inclination of the coring axis shall be measured, and the
location and inclination of the jet grouted element axis shall be previously measured.
Coring shall be performed only after that hardening of grout has completely occured. The
method of coring, the equipment used and the size of the cores shall be selected with the
final aim of recovering representative samples. Special precautions are necessary when
coring jet grouted elements in clayey/silty soils, in heterogeneous soils (containing
cobbles for instance) or if the jet grouted material is of low strength.
Recommendations for mechanical tests are listed below:
• Where in situ tests are used to measure the mechanical characteristics of the jet grouted
material (e.g. pressuremeter or any other test requiring drilling), the position of the
measuring tool shall be defined referring to the element geometry and lay-out;
• Compression tests shall be performed on samples with height to depth ratio of 2.0;
• Compressive strength of jet grouted structures shall be assessed by testing four samples
taken from the structure for each 1000 m3 of its volume, if not otherwise specified by
the design;
• Where mechanical properties are obtained from tests on cores, impact of sampling
technique, trimming and test procedures shall be considered in results interpretation;
• Brazilian tests and shear tests on jet grouting cores can be an alternative to compressive
tests if duly motivated;
• Mechanical tests shall be performed after set of the jet grouted material, considering both
the construction requirements and the influence of the nature of the soil on the hardening
time of the jet grouted material (longer hardening time in clayey soils is typically
experienced);
• Samples taken for mechanical tests shall be stored under controlled moisture and
temperature conditions and not exposed to direct sunlight.
Recommendations for permeability tests are listed below:
• The overall watertightness of jet grouted structures shall be assessed by pumping tests
and/or piezometric readings;
• The overall watertightness of a jet grouted structure around and/or below an excavation
in Geotechnical Categories 2 and 3 (EN 1997-1:2004) shall be assessed by pumping tests
and piezometric readings before any excavation below the original ground water level is
undertaken;
• The permeability of the elements shall be measured by borehole water tests.
7.7.6.5 Monitoring
Monitoring of the jet grouting parameters during the performance of jet grouting works is
essential for the quality control of the results.
For applications in geotechnical categories 2 and 3 (EN 1997-1:2004), the following parameters
shall be recorded:
• pressures and flows of the fluids;
• translation and rotation speed of the monitor.
When jet grouting works have to be performed in situations where there is a high risk of
unacceptable deformations of adjacent structures, a real-time monitoring (e.g. displacements,
rotations and/or deformations) of structures and an alarm system shall be designed and
implemented.
For underpinning applications, the buildings to be underpinned shall be monitored by repeated
levelling or by automatic settlement sensors.
7.7.6.6 Documentation
The following documents shall be available on site prior to the main jet grouting works:
• technical specifications;
• execution drawings;
• method statement;
• a geotechnical report describing the subsoil conditions;
• technical specification of the jet grouting plant;
• a description of the characteristics of the construction materials;
• a report on preliminary field trials (if any).
The jet grouting execution drawings shall contain the following information:
• the soil profile;
• the shape of the elements;
• the number of the elements, a clear reference number for each;
• the location and orientation of each element, and tolerances on position;
• the location of possible underground obstructions, services and drainage;
• the execution sequence, where relevant.
Records of the jet grouting execution shall be compiled for future reference. They shall cover,
for each element:
• the jet grouting injection parameters (possibly continuous monitoring vs time);
• comments on the spoil return;
• unexpected features;
• date and time of execution.
Where in-situ preliminary field trials have been performed, a detailed report shall be prepared,
including all the results obtained with reference to the prevailing soil conditions and the size of
the jet grouted elements to be constructed.
The jet grouting execution plan and all records shall be kept after the completion of the works.
Compaction Grouting
The technology of injection to consolidate and re‐compress soil, known in the technical literature
as compaction grouting, is a solution aimed at compacting and amassing soft or altered,
decompressed soil.
This technology was developed and used mainly to resist settling of structures and buildings;
today compaction grouting is a valid solution for application in situations such as:
• stabilizing, consolidating and recovery of existing foundations, structures and buildings
• consolidating soil characterized by poor load‐bearing capacity
• filling in cavities or blockage of soil that is particularly “open” or porous.
Permeation Grouting
Permeation grouting is used to improve the mechanical and permeability properties of soil, rocks
and brick or concrete work. From a functional point of view, two types of interventions can be
identified:
• temporary intervention, to make excavation possible in unstable soil or under water table;
• permanent intervention for the consolidation of foundation soils, the creation of
watertight structures, or the structural restoration of brick or concrete works.
8 POSITIONING
All positioning tasks shall be carried out in accordance with company standard
28753.ENG.PLI.STD “Onshore Positioning”.
Before the commencement of the works an Operating Procedure shall be submitted to Company
for acceptance one month prior to the start of mobilization.
The documentation as indicated in the following sections shall be produced during execution of
the works.
10.1 SCHEDULES
A Bar Chart Schedule showing manpower required by time interval for each activity and reflecting
percent of schedule completion by time interval. A detailed schedule, weekly, of day-to-day
operations showing planned manpower loadings for major activities shall be provided.