Professional Documents
Culture Documents
This document is the property of Sydney Program Alliance and may not be copied, distributed or used without the express written consent of Sydney Program Alliance
Sydney Program Alliance Lecture Notes:
Structural Design Criteria, Analysis and Design
Methodology
An unincorporated alliance between Roads and Maritime Services (RMS), John Holland Group (JHG), Freyssinet
and Jacobs to undertake a program of work in and around the Sydney Harbour Bridge Precinct. Individual work
packages will be scoped and priced with the resultant TOC being provided to the Alliance Leadership Team for
approval.
John Holland Group has been appointed as the Principal Contractor and as such the John Holland (JH) Integrated
Management System (IMS) will prevail whenever there are discrepancies between this document and the John
Holland IMS.
Within this document the terms Sydney Program Alliance (SPA) and John Holland (JH) / John Holland Group (JHG)
are interchangeable.
Distribution List
This document will be available on the document management system in an electronic version only.
If required it will be made available to subcontractors as part of their contract documents. The document
will either be issued in full or relevant information extracted and supplied as a ‘subby pack’.
The controlled master version of this document is available for distribution as appropriate and
maintained on the document management system being used on the project. All circulated hard copies
of this document are deemed to be uncontrolled.
Disclaimer
This document is meant to be a quick reference guide.
It is up to the reader to use and make their own engineering judgement as to the accuracy of this document
applicability to any design.
Table of Contents
1 Introduction ...........................................................................................................6
1.1 Bridges Overview ...................................................................................................... 6
1.2 Functions / Types of Bridges ..................................................................................... 6
1.3 Scope of Document ................................................................................................... 6
1.4 Standard Units........................................................................................................... 6
1.5 Aesthetic and Visible Criteria ..................................................................................... 7
1.6 Engineering Standards .............................................................................................. 7
1.6.1 Order of Precedence ........................................................................................... 7
1.6.2 Standards and Reference Documents ................................................................. 7
2 Design Parameters ................................................................................................9
2.1 General ..................................................................................................................... 9
2.2 Design Life ................................................................................................................ 9
2.3 Geometric Requirements ........................................................................................... 9
2.3.1 Bridge widths / clearances ................................................................................... 9
2.3.2 Edge Protection ................................................................................................. 10
2.3.3 Deck Drainage................................................................................................... 11
2.4 Durability ..................................................................................................................11
2.4.1 Concrete Exposure Classification and Cover to Reinforcement ......................... 11
2.4.2 Provision for Future Cathodic Protection ........................................................... 12
2.4.3 Use of Stainless Steel ....................................................................................... 12
2.4.4 Steel Exposure Classification and Corrosion Rates ........................................... 12
2.5 Utilities......................................................................................................................12
3 Design Loads....................................................................................................... 13
3.1 Dead Loads ..............................................................................................................13
3.2 Superimposed Dead Loads ......................................................................................13
3.3 Road Traffic Loads ...................................................................................................13
3.3.1 Standard Vehicle Loads .................................................................................... 13
3.3.2 Heavy Load Platform (HLP) Loads .................................................................... 13
3.3.3 Distribution of Road Traffic Loads Through Fill .................................................. 14
3.3.4 Construction ...................................................................................................... 14
3.3.5 Centrifugal Loads .............................................................................................. 14
3.3.6 Braking Loads ................................................................................................... 15
3.3.7 Fatigue Load Effects.......................................................................................... 15
1 Introduction
These lectures cover the requirements for general bridges that comprise:
For bridges outside the above ranges or bridges of a complex construction nature, including cable stayed,
suspension, balanced cantilever, incrementally launched, stress ribbon and arch bridges, the provisions of AS5100
shall be supplemented by other appropriate standards and specialist technical literature..
This Structural Design Criteria is applicable to the detailed design of the above structures.
2 Design Parameters
2.1 General
This section covers the requirements for the detailed design of the structural aspects of the Bridge Structures.
The minimum design life specified in the SWTC is taken to include the inspection and maintenance period as
outlined in Maintenance Diaries (developed for each bridge) with a sample included in Appendix G. Table
2- identifies the major structural components and lists the respective design life that is to be adopted for each
element of a Bridge, NOT within a rail corridor:
1. Road Traffic Barriers. These barriers come in different Performance Levels. A procedure to assist in the
selection of an appropriate barrier performance level is given in AS5100.1 (Appendix A). The barrier geometry,
including treatment of bridge approaches and end treatments is specified in AS5100.1 (section 14.6).
2. Pedestrian / cyclist barriers. The requirements for these barriers are outlined in AS5100.1 (section 16).
3. Kerbs and Medians. These are rarely encountered on bridges as edge protection, however, where required,
they will need to comply with the requirements of the Austroads Road Design Guidelines. For pedestrian
bridges, generally the front face of the kerb is to be located 150mm minimum away from the front face of the
handrail.
4. Safety Screens. Safety Screens are a physical barrier that provides protection against direct contact with
exposed 1500 V dc OHW equipment. The requirements for these screens are outlined in the relevant ASA
standards.
5. Protection Screens. Protection screens are generally installed on bridges to restrict objects from falling off or
being thrown off bridges. The requirements for these screens are generally determined by the relevant
Authority. Where required, the details are to be in accordance with AS5100.1 (section 16.4 and BTD 2012/01).
For clarity, the title BTD 2012/01“SAFETY SCREENS” is incorrect and should be “PROTECTION
SCREENS”.
6. Noise Barriers. These barriers are for noise mitigation and the requirements are subject to specialist
assessments carried out. The design will generally be directed by Urban Design and Aesthetic considerations.
In general, however, the deck drainage system should be designed to ensure that a minimum amount of water
flows across deck joints. To achieve this requirement, generally a maximum width of flow from a 10 year ARI storm
is limited to within the shoulder width. Where scuppers are required, they will be sized and located to ensure that
the width of flow criterion is satisfied on the bridge deck.
Scuppers can be free draining except within class I waterways. Scuppers within class I waterways will be drained
via a drainage pipe and discharged in accordance with longitudinal drainage plans.
2.4 Durability
A Durability Assessment Memorandum should be prepared and included as an Appendix to each design report.
The memorandum should be developed and amended during the detailed design stages, taking into account further
environmental and sample test data and analyses taken for verification of the initially assumed exposure conditions.
The durability requirements presented at various stages of design development may therefore be amended.
Designers are to make reference to BTD 2014/02 for the requirements associated with the preparation of a
Durability Plan and BTD 2008/12: Provision for Concrete Structures in Acid Sulphate Soils in determining exposure
classification.
Designers should also make reference to ASA Standard T HR CI 12002 ST Durability Requirements for Civil
Infrastructure.
Bridge structures shall be designed to enable items such as bearings, expansion joints and seals, railings and
drains to be maintained or replaced.
Items that cannot be readily accessed for maintenance or replacement shall be designed to function for the
minimum design life of the structure with no maintenance.
In relation to Atmospheric Exposure for a 120 year design life structure, ASA Standard T HR CI 12002 ST Durability
Requirements for Civil Infrastructure suggests:
“As a guide for maintenance class 5, assets with a design life of 120 years and 40 MPa concrete a
minimum cover of 50 mm would be expected to prevent carbonation to the depth of the
reinforcement within the design life”.
This equates to the provision of an additional 5mm of cover to reinforcement. Specific durability assessments
should be made for such structures, including review of materials and specifications to be adopted.
All cast in items that cannot be maintained are also to be stainless steel.
2.5 Utilities
Where required, or where anticipated, provision is to be made for the attachment of utility services, as permitted by
the relevant authority.
The attachment of utility services is to comply with the requirements of AS5100.1, clause 20.
Confirmation of all existing and future proposed utility requirements should be made with the relevant authorities.
These include, but are not limited to the following:
3 Design Loads
The bridge designs are to be in accordance with the Standards and Reference Documents previously outlined. The
following loads should be considered in the design of the bridges:
Deck wearing surfaces and additional concrete to compensate for prestress girder hogs or for geometric
requirements will be taken as superimposed dead loads for the purposes of determining design loads.
A future allowance for services of 0.25 kPa should be included. Other services allowances are calculated on a
bridge-by-bridge basis.
3.3.4 Construction
Construction vehicles are to be assessed and any nominated vehicle configurations are to be shown on the
drawings.
Sample construction vehicles adopted for the Pacific Hwy Upgrade project W2B are as follows:
• 651 Scraper
• 773 Rock Truck (Caterpillar)
The loading diagrams for the critical vehicles including axle loads and dimensions are provided in Figure 3-.
Note:
In addition to the above, train derailment load effects are to be also considered acting on bridge superstructures as
noted in AS5100.2, clause 11.5. There are two Derailment Load cases as noted in clauses 11.5.2 and 11.5.3.
The distribution of Rail Traffic Loads shall be in accordance with the requirements of AS5100.2, clause 9.6.
The deflection limits of a rail bridge shall comply with the requirements of AS5100.2, clause 9.10.
Notwithstanding the above, ASA have Light Rail civil design and construction standards T LR CI 12500 ST and T LR
CI 12520 ST that adopts 125LA / 100LA loads. This is derived in accordance with AS5100.2 (section 9.3) by
multiplying the 300LA load by a factor of 0.42. In addition to this, there are only 9 axles (one simulated locomotive
axle plus two groups of 4 trailing axles of 100LA loading).
For barriers, the design criteria, including loads (ULS with a load factor of 1.0) are to be in accordance with
AS5100.2, clause 12 and Table 12.2.2.
Anchor bolts for the barriers shall be designed with a load factor of 1.05 to ensure that the barrier system fails prior
to failure of the anchor bolts to ensure a ductile failure mechanism.
The bridge deck is to be designed for a minimum load of 1.1 times the design ultimate capacity of the barrier, again
to ensure a ductile failure mechanism.
Expansion Joint treatment and end barriers shall be designed in accordance with the requirements of AS5100.2,
clause 12.4.
Pedestrian and cyclist barrier loads shall be in accordance with AS5100.2, clause 12.5.
Deflections due to pedestrian and cyclist path loads shall be assessed for the SLS load case in accordance with the
requirements of AS5100.2, clause 8.4.
Typical values for the Canal Road Bridge are shown below.
The Regional wind speeds (and site wind speeds) are determined based on AS1170.2 table 3.1 for the various
regions. For Sydney (region A2), the regional wind speeds are:
The design wind speeds for the Canal Road Bridge have been calculated to be:
• Vs = 37 m/s
• Vu = 48 m/s
Transverse wind load shall be calculated in accordance with AS5100.2, clause 17.3. For the Canal Road Bridge,
the transverse wind load is calculated as:
• Cd, for (b/d = 46.0/4.0 = 11.36) = 1.0 (refer to AS5100.2 Figure 17.3.3)
• At = Area of structure under consideration, refer to AS5100.2 clause 17.3.2.
• Wt = 0.821 x At
• Wt* = 1.382 x At
Vertical wind loads shall be determined in accordance with AS5100.2 clause 17.5. For the Canal Road Bridge, the
vertical wind load is calculated as:
3.7.2 Earthquake
Earthquake design loads and analysis methods are to be determined in accordance with AS5100.2 cl.15 (Force-
based approach) and AS1170.4 – 2007 (Dynamic analysis).
The Force-based design procedure (most common approach) is defined in AS5100.2, clause 15.3 and is
summarised below:
• Determine the bridge earthquake design category and design performance level (clauses 15.4 and 15.5)
• Determine the probability factor and the hazard factor (clause 15.6)
• Determine the site subsoil class and the acceleration spectral shape factor (clauses 15.7 and 15.8)
• Calculate the design action coefficient for earthquake response (clause 15.9)
• Calculate the earthquake forces and their distribution (clause 15.10). Adopt clause 15.11 if Dynamic
Analysis is adopted, see below.
• Determine the required design strength of bridge members (clause 15.4), determine the abutment forces
(clause 15.15) and provide structural detailing for earthquake effects (clause 15.16)
Earthquake forces determined from Dynamic Analysis is defined in AS5100.2, clause 15.11. This states that the
analysis is to be carried out in accordance with the requirements of AS1170.4 with exceptions defined in AS5100.2,
clause 15.11.
Displacement-based earthquake design principles are outlined in AS5100.2, Appendix B. In addition, where
approved by the relevant authority, a displacement-based design may be undertaken using a non-linear static
pushover analysis if:
This load is to be applied at any inclination between horizontal and (upward) vertical applied at any potential impact
points on the superstructure, concurrent with minimum permanent downward vertical load acting on the support
multiplied by 0.75. The impact force will be taken to act at the level of the soffit of the superstructure.
• Location
• Height above sea level
• Average reference temperature. This is referenced back to local average temperatures, generally obtained
from the Bureau of Meteorology (BOM). For Sydney, this temperature is generally taken as 20 degrees
Celsius.
A compaction pressure of 20 kPa during construction from backfilling behind abutments prior to erection of girders
shall be applied.
In addition to loads, filling and compaction of fill behind abutments results in lateral displacements of abutments.
The sequence of construction will have an impact on the design detailing of the bearing mortar pads and the
bearings themselves that support the girders at these abutments.
Actual displacement values (elastic and long term) will be normally derived from geotechnical assessment
modelling (“Plaxis” or “LPile” or similar). Typical values for abutments supported on piles are between 5 - 10mm
(elastic) and 10 – 20mm (long term).
• Forces resulting from water flow. This requires both SLS and ULS assessment and requires input as
follows:
o Flood levels
o Associated flood water velocities
• Scour assessment at both SLS and ULS conditions.
Water flow loads are to be determined in accordance with AS5100.2 Cl.16, with the following clarification to Cl.16.6
Forces due to debris:
The depth of the debris mat (Cl.16.6.1) is to be taken as half the flow depth including general scour, but not local
scour around piers and abutments, between the limits of 1.2 m and 3.0 m.
The cases for debris acting on piers (Cl.16.6.2) is to be taken as depicted in Figure 3.7.6.1A and Figure 3.7.6.1B.
Figure 3-7.6.1A: Example of the full length of debris mat acting on a single pier (or abutment) only (i.e. Span
1/2 + Span 2/2 < 20 m)
Figure 3-7.6.1B: Example of 60% of the length of the debris mat acting on each of two adjacent piers (i.e. 1.2
x Span 2 < 24 m)
The average return intervals for water flow loads are as follows:
• Serviceability = As defined in AS5100.1, clause 8.3 and Table 11.1 with a load factor equal tom 1.0.
• Ultimate = As defined in AS5100.1, clause 8.3 for floods up to and including the 2000 yr ARI flood.
In addition to water flow and debris forces, the following additional water forces are to be considered:
3.7.6.2 Scour
Bridges that span creeks and flood plains are susceptible to scour erosion at the pier and abutment substructures.
It is generally required that the bridge must be designed to withstand the scour that occurs at the structure for the
100 year ARI flood event, and 2000 ARI year flood events, for SLS and ULS respectively. Estimations of scour
depth are to be included in each bridge design report.
Scour generally comprises of two components as follows (however construction activity related scour could also
occur):
• Piers – design taking into effects 100yr and 2000yr scour as appropriate, ignoring scour protection.
• Abutments (wall type) – design taking into effects 100yr and 2000yr scour as appropriate, ignoring scour
protection.
• Abutments (spill-through embankment type) – if the design assuming the 100yr scour depths does not
work, scour protection may be designed for the 100 year ARI flood event and an embankment of not
steeper than 1:1 may be assumed to remain after the 100 year ARI flood event for the design. If this
cannot be demonstrated hydrologically, the scour protection shall be designed for the 100yr flood event
(level and rock size).
• The substructure shall be designed taking into account scour as specified in the Hydraulic Memo specific
to each bridge. For events greater than the 100 year flood event, inclusive of the 2000 year flood event –
scour at abutments is assumed to be an equal height in front and behind the abutments.
An equivalent static load shall be calculated in accordance with AASHTO LRFD Bridge Design Specifications. The
new bridge superstructure soffit levels are to match the existing bridge soffit levels to ±50 mm. The new bridge pile
cap levels (top and bottom) are to match any existing adjacent bridge pile cap levels as a minimum.
Vehicle impact on piers is to be assessed in accordance with the requirements of AS5100.2, clause 11.2.
This is a ULS load and is defined as the application of a static load of 2700kN acting in any direction in a horizontal
plane and applied 1.2m above ground level, with a load factor of 1.0.
Consideration of these loads is generally restricted to structures located within 20m of a rail track (taken as the
centre-line of rail tracks).
1. Collision loads on support elements. These are calculated in accordance with the requirements of AS5100.2,
clause 11.4.2 and are split into two categories as follows:
a. Supports within 10m of track centre-line (clause 11.4.2.3).
b. Support elements located between 10m and 20m from track centre-line (clause 11.4.2.4).
2. Collision loads on any other bridge or structural components within 10m of the centre-line of the rail track
(clause 11.4.3). For clarity, this is also split into two categories as follows:
a. Elements that are within 10m horizontally and 5m vertically of the centre-line of the nearest railway
track.
b. Elements above 5m and up to 10m vertically above the rail track level.
3. Collision loads within the bridge due to derailment. Unless the bridge is designed for collision loads from a
derailed train anywhere within the bridge, containment is to be provided as outlined in clause 11.4.4.2. Any
primary structural element higher than 2.0m above the rail tracks shall be designed for the collision loads
outlined in clause 11.4.3. Deviation from these requirements, including redundancy provisions for stay cables
and hangers will require approval of the relevant authority.
4. Additional requirements for bridges adjacent to railway lines are contained within ASA standard T HR CI 12030
ST, clause 18.
5. Collision Protection requirements are outlined in AS5100.1, clause 15.
a. For collision from rail traffic there are specific requirements for the protection of bridge supporting
elements as noted in clause 15.3.2. There are two approaches for pier protection as follows:
i. Use of frangible piers (clause 15.3.3).
ii. Piers other than frangible piers. This includes piers protected by deflection walls (clause
15.3.4). Design requirements for deflection walls is discussed in clause 15.3.6.
b. Protection of abutments are covered in clause 15.3.5.
c. Protection from waterway collisions is covered in clause 15.4.
3.7.9 Fire
Fire load requirements are outlined in AS5100.1, clause 22.
In addition, bridges may require having a fire resistance level specified by the relevant authorities. As an example,
ASA standard T HR CI 12030 ST, clauses 27.7 and 28.10 requirements.
Road Bridges:
Rail Bridges
Where this is not practical due to the length or width of the bridge or constraints in the design of the OHW system,
agreement to attach OHW supports shall be obtained from the rail infrastructure manager (RIM).
Requirements shall be in accordance with the requirements of ASA T HR CI 12030 ST, clause 15.
As noted in ASA T HR CI 12030 ST, clause 24, in electrified areas the design of underbridges and associated
elements such as walkways, refuges, safety and protection screens, shall provide for earthing and bonding of
metallic components in order to mitigate touch potential hazards and corrosion of steel. Note: Electrified areas
cover the section of railway provided with 1500 V dc overhead wiring, nominally bounded by Hamilton in the north,
Kiama in the south, Bowenfels in the west and Glenlee in the south west. The design requirements for earthing and
bonding of all under-bridges in the electrified areas shall comply with the requirements set out in T HR EL 12005 ST
Bonding for 1500 V DC Traction Systems.
The design for earthing and bonding of all overbridges and footbridges in the electrified area shall comply with the
requirements in T HR EL 12005 ST Bonding for 1500 V DC Traction Systems. Earthing and bonding requirements
for low voltage shall be in accordance with ASA T HR EL 12004 ST Low Voltage Distribution and Installations
Earthing.
10. PE + earthquake
* Not as per AS5100.2, however PC specified this additional load case to be checked as the bridges are required to
be open to traffic under 1 in 100 year ARI flood events.
Refer to BTD 2008/10 for Bridge Deck Joint Selection, Design, Installation and Maintenance.
Opening Movements
ULS PE (Creep and Shrinkage) + ULS Thermal (cold) + SLS Opening must not exceed 125 mm
Braking
ULS PE (Creep and Shrinkage) + ULS Thermal (cold) Opening must not exceed 85 mm
Closing Movements
SLS PE (Creep and Shrinkage) ULS Thermal (hot) + SLS Braking Opening must not close to zero
Notes:
3.8.4 Bearings
The bearings will be designed under the following horizontal load cases:
1. SLS PE (Creep and Shrinkage) + SLS Thermal (worst case under hot or cold)
• The bearing design need not include earthquake loads, however for BEDC I and BEDC II bridges the use
of friction to transfer loads through the bearings may be used.
• Braking loads to be designed for on a bridge-by-bridge case basis. If bearings cannot resist braking forces,
a buffer bearing may be provided at the abutments with the load resisted by passive pressure.
4 Design Process
The design process is generally dictated by the client with deliverable stages and requirements noted in the SWTC.
This generally comprises the following stages:
At this stage the geometric form and behaviour of the bridge is determined. This stage basically locks in the bridge
concept for development during Detailed Design. This submission forms the basis for inter-discipline coordination.
Changes affected beyond this stage pose major project risks. Approval from the client to proceed beyond this stage
is required.
• Bridge Alignment (both horizontal and vertical). This is developed in association with the road designers and
includes:
o Required bridge width between kerbs
o Requirements for walkways.
o Clearances
o Constraints
o Utilities requirements
o Maintenance access requirements, such as requirement for access benches and access stairs at
abutments
• Bridge form including:
o Site envelope requirements
o Span configuration
o Superstructure type and required depths
o Substructure envelopes
o Containment and edge protection types
• Bridge behaviour including:
o Vertical Load Paths
o Longitudinal Load Paths
o Transverse Load Paths
o Articulation:
▪ Joint locations
▪ Substructure / Superstructure Interface and bearing types
• Review Environmental Compliance requirements and have these incorporated within the design.
• Develop Design Criteria.
• Determination of the proposed construction methodology.
• Preparation of a Preliminary Design Report.
• Detailed design of the bridge superstructure and substructure. This will take into account the inputs
received from the other disciplines including (but not limited to):
o Topographic survey results.
o Geotechnical investigation and interpretive assessment.
o Hydraulic assessment
o The results of this design are typically captured in a design actions summary within the report.
• Detailed design of any precast concrete pretensioned girders including calculation of girder hogs and
bearing mortar pads. This is used in order to determine set-out levels for the bridge substructure as well as
concrete deck thicknesses along the length of the bridge.
• Incorporation of Durability requirements (including identification of appropriate specifications) identified by
the SWTC, Standards and any specific Durability Assessments (including testing) carried out. It is
common for the inclusion of a preliminary maintenance diary with this stage submission.
• Carry out a Safety-in-Design, Constructability, Risk and Human Factors Workshop with mitigation
measures included within the design.
• Incorporation of all stakeholder comments that were based on the Preliminary Design submission.
• Formal approval from the client is generally not required to continue beyond this stage.
• All relied upon inputs have been checked, signed off and details incorporated into the design.
• All details are completed including addition of all reinforcement, modelled and drafted in accordance with
the requirements of the SWTC.
• All durability details are incorporated into the design including any modified specifications required and
finalised maintenance diaries. This may also include a list of Hold and Witness Points (taken from the
specifications) that get included within the construction team’s ITP’s.
• Carry out an updated Safety-in-Design, Constructability, Risk and Human Factors Workshop with final
mitigation measures included within the design and risks to be passed on to the contractor identified and
reported.
• Incorporation of all stakeholder comments that were based on the Detailed Design submission.
• Certification process completed with certificates received and included in the submission as follows:
o Designer certification
o Proof Checking / Independent Verification certification
This issue is generally limited to a drawing issue (including any 3D models) only. There is generally no IFC report
with the submission.
6.1 Geometry
Refer to the Initial Detailed Design (IDD) issue General Arrangement drawings for the geometry and layout of each
bridge.
The analysis methodology as described in the following sections is relevant for simply supported prestressed super
tee girder bridges. The substructures differ between bridges, however the general methodology described can be
applied to all.
As all the girders are simply supported, a simple grillage of the girders and deck only will be used. It is anticipated
that only one grillage model per type of girder be used and the same results used for the different substructures. A
separate model shall be run for the shear and torsion analysis (see Table 6-1 for section properties).
The grillage should have transverse members running perpendicular to the main members even if the bridge is on a
skew.
The deck grillage will be setup horizontally, with the cross fall across the deck and vertical curvature ignored
(vertical curvature will be considered in the sub structure model). Both the longitudinal and transverse members are
modelled in the same plane.
Longitudinal girder members: each composite beam will be modelled as a spine beam along the beam centreline.
The longitudinal spine beams will be given section properties appropriate to the construction staging of the bridge.
Transverse slab members: the deck slab will be modelled as discretely spaced transverse members spanning
between the girders. The transverse members at the edge will follow the horizontal curvature of the deck (if any) to
represent the correct tributary area.
The members will have rigid offsets located from the longitudinal girders to the centreline of the webs. The spacing
of transverse members is chosen to be 10% of the girder length or 2.5m max. A reduced spacing to say 1m should
c = 2i? be used at the end of the girders to ensure accurate shear force output at the design location.
Use cracked I section properties for deck (Ie =0.5Ig). The same stiffness reduction value is used to determine the
effective stiffness of the slab in both directions. The torsional stiffness of the transverse member is assumed to be
0.5J where J = b.d3/3. The transverse member is a portion of a slab, and the torsional stresses derived in the model
are effectively bending moments in a direction other than the principal directions. Therefore, the same effective
stiffness will be used i.e. 0.5J.
Edge member: Additional dummy members will be placed along each longitudinal edge of the carriageway for the
application of barrier loads. The edge barriers are jointed to prevent composite structural action i.e. acting like a
longitudinal stiff member.
End diaphragm (if applicable): use cracked I section properties (I e=0.5Ig). Torsional stiffness is either zero, or use
0.1J (allowing for a cracked section). If the torsional stiffness is used, check that the section can carry the torsion
forces derived from the model or the results will be invalid.
• n = Esteel / Econc
• For the analysis of long term shortening effect, 0.5 Ig of concrete section will be used for the columns and
piles. This assumption should be reviewed by checking extent of transformed cracked section.
6.2.1.2 Loads
Apply each load case separately to the model, i.e. only use one live load lane for one load case rather than
combining several live load lanes for one load case. By doing this, it will allow the loads to be combined to provide
the worst load cases for both superstructure design, and also substructure reactions. Note, using the moving load
generator, it is simpler to have each scenario considering one, two or three lanes.
The reactions from this model are applied to the separate substructure models.
The link slabs will be designed using an equivalent bending moment derived from the rotation of the girders due to
live load, as shown in Figure 6-2. The length of the member is the length of the debonded zone.
6.2.2 Substructure
The substructure will be analysed using three simple models.
A simple line model with spring supports will be used to determine the distribution of the longitudinal loads (i.e.
creep, shrinkage, thermal and braking) between supports.
Each horizontal spring has the longitudinal stiffness derived from the support frame and shear stiffness of bearings
i.e. Ktotal from 1/Ksupport frame + 1/Kbearings = 1/Ktotal
The output reactions are then inputs as each load into the 3D substructure models.
Substructure support frames are modelled as 3D frames with Winkler springs as appropriate for the soil profile at
each bridge. The longitudinal analysis of the substructure frames is treated separately, with the loads applied being
the reactions from the longitudinal load distribution model.
The frames are set up with the members shown in Figure 6-4.
Outriggers: Rigid outriggers from the crosshead are modelled to apply the reactions from the superstructure grillage
to account for unbalanced loads. The lengths of the outriggers are from the centreline of the piers to the bearing
centrelines, also taking into account the tolerances from girder installation. This tolerance is in RMS specification
B110, Table B110.1, and is the greater of 0.06% L or 10 mm. The out of tolerance limit of bearing installation is ±
20 mm. The larger of these tolerances shall be used, and not added.
Steel tubes with concrete plugs: To take into account the non-composite action between the steel tube and
concrete at the ends of the plug, the capacity of the cased piles shall be assumed to be:
The capacity of the pile is to be taken as the superimposed capacities of the concrete and steel, and the true
composite capacity only calculated if the pile demands are required. Corrosion of the steel tube should be taken
into account in the calculation of the capacity.
Winkler springs are to be removed to take in to account the effects of scour. A sensitivity analysis should be
undertaken with 50% and 200% spring values.
If precast crossheads are used, the out of tolerance of the piles are ± 25 mm for the cast-in-situ column extensions,
and ± 75 mm for piles. This out of tolerance should be taken into account in the capacity of the pile to crosshead
connections.
For horizontal loads in the transverse direction, the substructure frames are to be connected with a single rigid
spine beam representing the superstructure to distribute the transverse loads between the piers and abutments.
Alternatively, a 3D spine model including the bearing elements may be used to simulate longitudinal and transverse
load distribution between substructure frames, in place of the three simple models described above.
7 Design Methodology
PROTECTED
BREAKING
LOADS
EARTH
PRESSURE