Professional Documents
Culture Documents
The installation of ropenet for rockfall protection involve the following steps:
1. Site Preparation :
Remove all surface vegetation including trees & shrubs in the cutting where
ropenetting has to be done. Loose boulders have to be removed in block
condition on the slope of the rock cutting including removing of loose
rock/undulations & dressing the side slope to facilitate spreading of
bouldernet.
The precast beam along with the anchoring chords are embedded inside the
trench by M10 concrete of 0.3 m depth. After the curing of the concrete the
trench is filled with the backfill muck with moderate compaction.
In case of polymer ropenet a dowel bar of 1.0 to 1.5 m depth & 16 mm dia.
is used for top anchorage. The dowel bars with the hook at the top for
anchoring the vertical chords of the polymer ropenets are driven inside the
anchor trench. The trench is backfilled with the excavated material.
2. Lacing of adjacent ropenets : After the top anchoring of the ropenets
the adjacent nets are laced so as to form a continuous net.
In case of steel wire ropenets specially designed galvanized steel spiral locks
are used for lacing. One spiral lock for each mesh of net is used.
Incase of polymer ropenets the nets are overlapped for 300 mm & laced with
polymer lacing twine of 3 mm.
A drill hole of 20 mm dia. is made with the help of a jack hammer upto a
depth of 1 m in a staggered manner. Each hole is filled with 3-4 cement
capsules & the bolts are driven to the desirable depth. The nuts are
tightened on the threaded portion of the anchor bolts after the epoxy coated
washer plate of 200 mm x 200 mm x 6 mm are placed over the ropenet.
Some alternate methods of top & bottom anchoring can also be adopted so
as to suit the site conditions.
Reference Installations
Southern Railway
Steel Wire Ropenet - 3500 Sq.m. in Trivandrum Section