ABU ALI SECURITY SYSTEMS UPGRADE AND FIRE STATION PROJECT

SURVEY REPORT
INSTRUMENT:
LOCATION: Fire Water Line P2 & P3 Bottom Of Trench
Refrence Point/ Benchmark
BM-No Easting Northing Elevation
Bench Mark Location: Near Adminstration Buildation
3617-10 368648.447 3020705.163 1.883
Design Coordinates Actual Coordinates Difference Coordinates Difference in
ITEM NO Design Actual Remarks
Easting Northing Easting Northing Easting Northing Elevation Elevation Eelevation
1 368587.510 3020680.835 368587.512 3020680.812 0.002 -0.023 0.55 0.54 0.01 P2
2 368591.888 3020695.133 368591.891 3020695.134 0.0032 0.0014 0.55 0.543 0.007 P3

Surveyor Civil Engineer QC-Civil


Name Name: Sajid Ahmad Name
Sign Sign Sign
Date Date: 12 March 2023 Date