ELECTROMECHANICAL CONT. L.L.C.

CHILLED WATER PIPING SYSTEM PRESSURE TEST REPORT


Project Name IGYM SPORT ACEDMY LLC
Location Unit No NKM-B-1016 & 1017-LG Floor
Area NKAHEEL MALL - DUBAI
Piping System CHWpipe
Type Of Joint PPR
Testing instrument Digital Pressure Calibrator
Pressure Gauge Sr No PG-0 12
FCU Details Stub out 2 no
Testing Pressure
Testing Medium

First Check Final Check


Date 11-11-2023 Date 12-11-2023
Time 09:00AM Time 11:30AM
Pressure 13 Bar Pressure 13 Bar

Duration 24 Hours
Test Report No Leakage in System
Status OK

Signature of witnessing test