Method of Statement for repairing Page 3/7, Section 2 - C32 will only be use for missing parapet and or complete parapet wall & shall not be use on ALL
1 NHC-KAT-PMO-MS-CI-0019 0 1
missed welding plate, missed steel other repairs.
reinforcement, mis-aligned welding
Page 5/7, Section 6 - A Repair for damage corner of slab/wall up to 500mm x 500mm shall use weberep 331 tx or
plate of precast elements. 2 equivalent approved materials together with the approved bonding agent. Area for repair must be sorrounded by clean
edges removing dust, oil & loose materials.
Page 5/7, Section 6 - Epoxy anchoring of missing steel must ensure that NO embedded MEP pipes, conduits , etc. must be
3
damaged or displaced.
4 Page 6/7, Section 7, item # 1 - No chipping gun shall be use for removal on wrongly installed steel plates.
Page 6/7, Section 7, item # 1 - Not to use red oxide, for optimum bonding & compatibility with weber 331 TX apply
5
weberep 370PF on steel plate. Weberep 360FFR for superficial repair and plaster.
6 Page 6/7, Section 7, item # 2 - Not to use OPC C32, use weberep 331 tx or other approved material.
7 Page 6/7, Section 7 - Curing of repaired section for a minimum of three (3) days using cool clean water.
Page 1 of 6
STEP 1: Using the matrix, carry out an initial assessment to determine TRAGIC 5 10 15 20 25 5 FATALITY
the risk rating of hazard(s) of the work activity (note: this is without
any control measures. CRITICAL 4 8 12 16 20 4 MAJOR INJURY/ILLNESS
STEP 2: Using the matrix result from step 1 if the risk rating is tragic SERIOUS 3 6 9 12 15 3 SERIOUS INJURY/ILLNESS
or critical then the hazard must be eliminated, or work activity
prohibited and an alternative method found. If the risk rating is MEDIUM 2 4 6 8 10 2 MINOR INJURY/ILLNESS
medium, then safety control measures are required to carry out the
activity. MINIMAL 1 2 3 4 5 1 NO INJURY
STEP 3: Re-assess step 2 if the risk rating remains medium then you 1 2 3 4 5
must provide alternatives and or additional safety controls until the risk LIKELIHOOD
rating enters into the low category and work activity can be proceed. VERY VERY ALMOST
UNLIKELY LIKELY
UNLIKELY LIKELY CERTAIN
Page 2 of 6
SETTING-UP
Workers,
Engineers, Incorrect signs and
Ensure all applicable signs and
Inadequate/incorrect Operators, HSE information can lead to Shift Engineer
2 3 6 information are posted in most 1 2 2
Notices and Signs. Personnel, injuries or even damage Foreman
visible location.
Managers, Visitors to property.
Page 3 of 6
Ensure welding/cutting
equipment is inspected by a
Fire Hazard competent person.
Welding Machine not Burns. Ensure cables free from cuts and Shift Engineer
Welders, Helpers. 2 3 6 1 2 2
inspected. Damage to Equipment joints. Foreman
Injuries Earthing is required.
Provision of drip tray for all
welding machine.
Ensure all employees received
proper training on correct usage
of PPE.
Ensure all employees received
No induction. training on safe working
Injuries. Project Manager
No toolbox talks Welders, Helpers, procedures.
Damage to Property Shift Engineer
PPE Engineers, 3 3 9 Ensure all employees received 2 2 4
Occupational illness and Foreman
Job specific training Foreman. induction training.
disease. HSE Personnel
Training to be given on risk
assessment.
Certificates and site-specific
license only to be issued after
training.
Page 4 of 6
OPERATION
Page 5 of 6
Page 6 of 6
Use of appropriate PPEs (e.g.
safety gloves, safety boots, safety
glass, Nose mask, earmuffs, etc.)
Adequate supervision for workers.
Only competent persons should
Health Illness Shift Engineer
Chemical Exposure Workers 2 3 6 be assigned for this activity. 1 3 3
Foreman
Training and Toolbox talks.
Direct exposure must reduce.
MSDS should follow
Chemical handling training
Refer to SAPL comment sheets for all work compliance