You are on page 1of 15

7-December-2020

DOMEL GAYO-SAPL

07/12/2020
Osama Abunema

By Moinudheen.Mohammed at 11:33 am, Dec 09, 2020


SI No. Submittal Ref. Rev. Reference Comments

Method of Statement for repairing Page 3/7, Section 2 - C32 will only be use for missing parapet and or complete parapet wall & shall not be use on ALL
1 NHC-KAT-PMO-MS-CI-0019 0 1
missed welding plate, missed steel other repairs.
reinforcement, mis-aligned welding
Page 5/7, Section 6 - A Repair for damage corner of slab/wall up to 500mm x 500mm shall use weberep 331 tx or
plate of precast elements. 2 equivalent approved materials together with the approved bonding agent. Area for repair must be sorrounded by clean
edges removing dust, oil & loose materials.
Page 5/7, Section 6 - Epoxy anchoring of missing steel must ensure that NO embedded MEP pipes, conduits , etc. must be
3
damaged or displaced.

4 Page 6/7, Section 7, item # 1 - No chipping gun shall be use for removal on wrongly installed steel plates.

Page 6/7, Section 7, item # 1 - Not to use red oxide, for optimum bonding & compatibility with weber 331 TX apply
5
weberep 370PF on steel plate. Weberep 360FFR for superficial repair and plaster.

6 Page 6/7, Section 7, item # 2 - Not to use OPC C32, use weberep 331 tx or other approved material.

7 Page 6/7, Section 7 - Curing of repaired section for a minimum of three (3) days using cool clean water.

Prepared By : DOMEL GAYO Signature : Date: 7-December-2020


29 November 2020

Created By: Abdul Sattar Meraj Din 1 of 1 11/29/2020


PROJECT NAME

RISK ASSESSMENT Ministry of Housing Project

Page 1 of 6

DESCRIPTION OF TASK REPAIRING OF PRECAST ELEMENTS WELDING / CONCRETING

SEVERITY CONSEQUENCE RATING SEVERITY OUTCOME

STEP 1: Using the matrix, carry out an initial assessment to determine TRAGIC 5 10 15 20 25 5 FATALITY
the risk rating of hazard(s) of the work activity (note: this is without
any control measures. CRITICAL 4 8 12 16 20 4 MAJOR INJURY/ILLNESS

STEP 2: Using the matrix result from step 1 if the risk rating is tragic SERIOUS 3 6 9 12 15 3 SERIOUS INJURY/ILLNESS
or critical then the hazard must be eliminated, or work activity
prohibited and an alternative method found. If the risk rating is MEDIUM 2 4 6 8 10 2 MINOR INJURY/ILLNESS
medium, then safety control measures are required to carry out the
activity. MINIMAL 1 2 3 4 5 1 NO INJURY

STEP 3: Re-assess step 2 if the risk rating remains medium then you 1 2 3 4 5
must provide alternatives and or additional safety controls until the risk LIKELIHOOD
rating enters into the low category and work activity can be proceed. VERY VERY ALMOST
UNLIKELY LIKELY
UNLIKELY LIKELY CERTAIN

SCORE PRIORITY FACTOR RATING


11-25 ACTION NEEDED IMMEDIATELY VERY HIGH (VH)

7-10 ACTION TO BE TAKEN WITHIN 12 HOURS HIGH (H)

3-6 ACTION TO BE TAKEN WITHIN 48 HOURS MEDIUM (M)

1-2 ACTION TO BE TAKEN WITHIN 7 DAYS LOW (L)

Repairing of Parapet wall


PROJECT NAME

RISK ASSESSMENT Ministry of Housing Project

Page 2 of 6

HAZARD & RISK IDENTIFICATION

HAZARDS WHO CAN BE RISKS L S RR CONTROL MEASURES L S RR RESPONSIBILITY


IDENTIFIED HARMED

SETTING-UP

A competent/certified that has


adequate knowledge, training
ProjectManager
Physical Injuries. and experience shall be
Project Manager
Incompetent Welder Workers Burns 2 3 6 appointed to carry our hot 1 2 2
Shift Engineer
Occupational Illness works.
Foreman
Internal competency certification
is required.

The space/area around the


fabrication yard shall be clear
Workers,
and free from any risk of injury
Poor housekeeping. Engineers, Shift Engineer
Physical Injury. to all workers.
Obstruction around the Operators, HSE 2 3 6 1 2 2 Foreman
Collision. Regular housekeeping is
workplace. Personnel, Welder
required.
Managers, Visitors
Unnecessary materials shall be
removed immediately from site.

Workers,
Engineers, Incorrect signs and
Ensure all applicable signs and
Inadequate/incorrect Operators, HSE information can lead to Shift Engineer
2 3 6 information are posted in most 1 2 2
Notices and Signs. Personnel, injuries or even damage Foreman
visible location.
Managers, Visitors to property.

Repairing of Parapet wall


PROJECT NAME

RISK ASSESSMENT Ministry of Housing Project

Page 3 of 6
Ensure welding/cutting
equipment is inspected by a
Fire Hazard competent person.
Welding Machine not Burns. Ensure cables free from cuts and Shift Engineer
Welders, Helpers. 2 3 6 1 2 2
inspected. Damage to Equipment joints. Foreman
Injuries Earthing is required.
Provision of drip tray for all
welding machine.
Ensure all employees received
proper training on correct usage
of PPE.
Ensure all employees received
No induction. training on safe working
Injuries. Project Manager
No toolbox talks Welders, Helpers, procedures.
Damage to Property Shift Engineer
PPE Engineers, 3 3 9 Ensure all employees received 2 2 4
Occupational illness and Foreman
Job specific training Foreman. induction training.
disease. HSE Personnel
Training to be given on risk
assessment.
Certificates and site-specific
license only to be issued after
training.

Site Safety orientation /


Induction.
Site Safety Rules must be
followed.
Workers unaware of Injury Training. Supervisor
potential hazard Employees at work Property damage
3 3 9 Random Toolbox talk. 2 1 2 Foreman
involved in the work zone Illness Task safety Briefing for critical HSE team
site. Environmental impact activity.
Personal Protective Equipment.
(PPE)
Adequate Supervision.

Repairing of Parapet wall


PROJECT NAME

RISK ASSESSMENT Ministry of Housing Project

Page 4 of 6

Use correct lifting techniques, all


operatives / workers should be
trained in the safe method of
lifting.

Ensure two-man lift is enforced


for reaching or carrying heavier
Injury
Workers involved in items. Supervisor
Manual Handling Damage to property 3 3 9 2 1 2
task Foreman
Muscle strains, sprains
Split loads to make them lighter
and safer to handle.

Be aware of handling large or


bulky items.

OPERATION

All welding and cutting cables


Burns.
Welders, helpers, shall be completely insulated. Shift Engineer
Electric Shock Physical and internal 3 3 9 1 3 3
and other workers. Ground connections are required. Foreman
injuries or even death.
Fire Extinguisher near the area.

Suitable Fire Extinguisher must


be available near the workplace.
No combustible materials shall
Damage to Property. be present near the workplace. Shift Engineer
Welders, helpers, Regular Housekeeping.
Fire Hazard Burns. 2 3 6 1 3 3 Foreman
and other workers. Welding screens shall be
Loss time. Welder
provided. Proper stacking of
materials
Regular inspection of hoses and
cables.

Repairing of Parapet wall


PROJECT NAME

RISK ASSESSMENT Ministry of Housing Project

Page 5 of 6

Operation training mechanical


mixer
Pre use checks for mixer / power
Workers, Visitors, Explosion
tools
Consultant, Clients, Fire Shift Engineer
Trained operator uses
Mechanical Hazard HSE Rep., Injuries 3 3 9 1 3 3 Foreman
Ensure safety guards are in place
Engineers, Damage to property Welder
Regular maintenance check
Managers Shock
Job specific PPE
Supervision of competent person

Working platform inspection by


competent person
Ground surface check
Injury Double body harness usage
Shift Engineer
Illness Edge protection system at roof
Fall from height Workers, Foreman 3 3 9 1 3 3 Storekeeper
Property damage slab Fall protection
Foreman
Fatality Work at height training
Protruding bars protection
Increased supervision
Caution signages

Regular inspection of all


components.
Explosion
Remove damage components Shift Engineer
Welders, HSE Rep., Fire
Damaged Components 2 3 6 immediately and replaced. 1 3 3 Foreman
Engineers, Injuries
Ensure all components is in good Welder
Damage to Property
condition.

Repairing of Parapet wall


PROJECT NAME

RISK ASSESSMENT Ministry of Housing Project

Page 6 of 6
Use of appropriate PPEs (e.g.
safety gloves, safety boots, safety
glass, Nose mask, earmuffs, etc.)
Adequate supervision for workers.
Only competent persons should
Health Illness Shift Engineer
Chemical Exposure Workers 2 3 6 be assigned for this activity. 1 3 3
Foreman
Training and Toolbox talks.
Direct exposure must reduce.
MSDS should follow
Chemical handling training
Refer to SAPL comment sheets for all work compliance

Assessed By (NAME) Signature Date

Sardar Najeerudeen 08-10-2020

Repairing of Parapet wall

You might also like