Doc No RP-EHS-F013

Mock Drill Report Rev, Dt 1, 16May2019

Site / Plant Name Abha and Alok SOLAR FARM LTD, Badisid, 20MW

Mock Drill Date 06.10.2022 Mock Drill 12:00 AM


Time

1. Type of Mock Drill Mockdrill on Electrical Shock

2. Nature of emergency Incident Management

Mr. Giriraj Purohit Renew Power

Mr. Navranjan Singh Param Renewables

Mr. Sawai Singh Param Renewables

Mr. Laxman Office Boy


Observers’ Name
Mr. Maga Ram Helper
Designation:

Mr. Vikram Singh Winsol Engineers

Mr. Sanjay Saini Winsol Engineers

Mr. Durga Singh Jagdamba Security

3. First information given by Mr. Navranjan Singh


Emergency Warning/
4. Communication Heard all over Communicated to working group verbally
the site. (as per scope applicable)
5. Evacuation of Entire site or part
Part of the site
of the site ordered
6. A Responsible or in Charge
Sawai Singh
present at assembly point
If yes, Name/Designation Head count not applicable
7. Head count taken at assembly
point.
Head Count details

8. Rescue of affected person carried


Mr. Maga Ram
out effectively
9. Emergency Commander /Rescue
Adequate
Team reaction is adequacy
10. Emergency escape routes are free
Un obstructed
from obstruction
Description Time

First Information 12:01 AM


11. Details of the Drill
Communication spread 12:02 AM

First Man arrived at the Incident point 12:04 AM

The information in this document is the property of ReNew Power Ltd. and may not be copied or communicated to a third party, or used for any purpose
other than that for which it is supplied without the express written consent of ReNew Power Ltd. Page 1 of 2
Doc No RP-EHS-F013
Mock Drill Report Rev, Dt 1, 16May2019

Team arrived 12:07 AM

Vehicle Arrived 12:08 AM


Technician rescued and Vehicle reached to the
12:30 AM
nearest hospital
Briefing given 13:30 PM

All Clear siren given 15:00 PM

12. No. of First Aiders Responded 1

13. No of Fire Fighters are responded Not Applicable

S.N Fire Extinguisher type Number

14. Fire Extinguishers used

15. Fire Extinguished start & end


NA
time
16. Areas of strength Communication

17. Areas needs Improvement Handling situation

Remarks
1. Security Guard should be more vigilant and report on time
2. Driver should be aware of Site Map and Hospital Location
3. Team Responded well during the Mockdrill

Prepared by Name Designation Signature


Giriraj Purohit Engineer-SAM

The information in this document is the property of ReNew Power Ltd. and may not be copied or communicated to a third party, or used for any purpose
other than that for which it is supplied without the express written consent of ReNew Power Ltd. Page 2 of 2

You might also like