HINDUSTAN PETROLEUM CORPORATION LTD

JOB SAFETY ANALYSIS REPORT

Name of Location MPSPL-TBS Sr No 1


Job description VCS, VHF System Maintenance and OFC Testing Date 5/30/2022
Name of contractor HPCL- Telecom Dept. Time 10:30
Exact location of work TBS Control Room and Telecom Room
Name of Supervisor Pradeep Sadasivuni Date 5/30/2022
Sr. Name Designation Signature

Prepared By 1 Pradeep Sadasivuni Asst. Manager Operations

Approved By 2 Vinaya Swapnil Narvekar Manager Operations


Job sequence/Steps Potential hazards Recommendations
(1)Usage of PPEs safety shoes ,helmets,goggles
etc(2)proper information sharing & updates with control
Room(3)Countersign of Shift Incharge in the
General Injury,Communication gaps Permit(4)Permit status carried forward to next shift through
HOTO verbally & in written.

Use PPE -Helmets, Gloves and Safety Shoes.


Availability of Tools/PPE INJURY

LEL 0.00%