Professional Documents
Culture Documents
1 Project Manager
2 Site Manager
3 QC Manager
4 Technical Manager
5 Electrical Engineer
6 H&S Engineer
7 Labor
2|P age
TABLE OF CONTENTS
1-PURPOSE……………………………………………………………..4
2-SCOPE…………………………………………………………………4
3-REFERENCES………………………………………………………..9
4-DEFINITIONS AND ABBREVIATIONS………………………………….9
5-PROCEDURE SYSTEM……………………………………………..9
5.1-GENERAL CONDITIONS…………………………………………..9
5.2-METHOD OF INSTALLATION……………………………………10
6-RESPONSIBILITIES……………………………………………….16
7-ATTACHMENT…………………………………………………….16
3|P age
1- PURPOSE
The purpose of method statement is to explain the scope of work for each activity and on this
method statement we are elaborating the process of installing for PVC , metal conduits and
accessories activities. In order to give the site engineers and supervisors on the site an induction
about the steps of installation for conduits and accessories procedure that will be carried on the
site. This section involves execution of the work and components for conduits and accessories.
2- SCOPE OF WORK
This "Method Statement" covers installation of PVC, metal conduits, fittings, and the
requirements of the checks to be carried out. This procedure is to be read in conjunction with
relevant document and checklist (attached) outlining the responsibility and quality verification to
be performed by various parties. This procedure defines the method used to ensure that all PVC
conduit and boxes and associated accessories are correct and acceptable.
4|P age
PVC,METAL conduits and some accessories
5|P age
DETAIL 1: Flush Mounted PVC conduit Installation Detail
6|P age
DETAIL 2: Surface Mounted PVC conduit Installation Detail
7|P age
DETAIL 2: Surface Mounted metal conduit Installation Detail
8|P age
3-REFERENCES
This document has been prepared with reference to the following documents:
Definitions of the terms and Legend for the abbreviations used in this document and its
attachments are listed in the following. Any additional terms and abbreviations, which are used in
a specific attachment, shall be defined in the related document:
BS British Standard
MP Management Procedure
5- PROCEDURE SYSTEM
All workers are to attend safety induction training conducted by Contractor and given specific
training on the safe installation methods by the supervisor of AE ARMA-ELEKTROPANC
It will be ensured that approved shop drawing is available with supervisor.
It will be ensured that approved material required to carry out work will be available.
9|P age
Prior to commencement of work, areas and access will be inspected to confirm that the site is
ready and safe to commence the work.
All relevant documentation and material applicable to particular section of works will be checked
by site engineer before commencement of work.
Physical verification of materials will be carried out for any damages prior to taking from
warehouse.
The site engineer/supervisor will give the necessary instructions to the tradesman and provide
necessary construction/shop drawings.
The site engineer/supervisor will also check that tools and equipment’s available are in
compliance to contract and safety requirements.
The site engineer will arrange necessary means for loading and/or mobilization of materials
10 | P a g e
6-HEALTH &SAFETY RISKS and CONTROLS
6.2 - Precautions
According to the safety regulations and Quantity Control Procedures following conditions are provided.
All equipment and tools are checked for they are free of errors and fully operational
All equipment and tools with defects are to be removed from the working area
All defects with electric and electrical equipment will be corrected
Trained people worked.
Use always PPE
6.3-PPE Record
AE ARMA-ELECTROMANIC
Project: BWC HOTEL
Hand Foot Eye Hand Hearing Hi-Viz Vest Respiratory Fall Arrest
YES / NO YES / NO YES / NO YES / NO YES / NO YES / NO YES / NO YES / NO
Position Date
Produced By
Signature Name
11 | P a g e
Received By Position Date
6.4-Risk Matrix
Increasing Probability
A B C D E
Never heard of Has occurred Incident has Happens Happens
in in occurred several times several times
Construction Construction during per year in per year on
Works Works operations during location
industry industry operations
1 None
2 Slight
Consequence
3 Minor
4 Localized
5 Major
6 Massive
Categories
Manage for continuous Incorporate risk reduction Intolerable
improvement measures
People (P)
0 No Injury No injury or damage to health
1 Slight Injury Not detrimental to individual employability or to the performance of
present work
2 Minor Injury Detrimental to the performance of present work, such as curtailment of
activities or some days absence to recover fully up to a maximum of
one week.
3 Major Injury Leading to permanent partial disablement or unfitness to work or
detrimental to performance of work over an extended period, such as
long-term absence
4 Single Fatality Single fatality or victim with permanent total disablement or unfitness
for work. Also includes the possibility of multiple fatalities (maximum of
3) in close succession due to the incident, e.g. explosion
5 Multiple Fatalities May include four fatalities in close succession due to the incident, or
multiple fatalities (four or more) each at different points and/or with
different activities
Assets (A)
0 No Damage No damage to equipment
1 Slight Damage No disruption to process. Minimum cost of repair.
2 Minor Damage Possible brief disruption to the process. Isolation of equipment for
repair.
3 Localized Damage Construction site/building partly down. Process can (possibly) be
restarted.
4 Major Damage Partial loss of construction site/building. Construction site/building shut
down.
12 | P a g e
5 Extensive Damage Total loss of construction site/building. Extensive damage.
Environment/Society-cultural (E)
0 No Effect No financial consequences. No environmental risk
1 Slight Effect Negligible financial consequences. Local environmental damage within
the fence and within systems.
2 Minor effect Contamination. Damage sufficiently large to affect the environment.
Single exceedance of statutory or prescribed criteria. Single complaint.
No permanent effect on the environment.
3 Localized Effect Limited loss of discharges of known toxicity. Repeated exceed of
statutory or prescribed limit and beyond fence/neighborhood.
4 Major Effect Severe environmental damage. SE required to take extensive
measures to restore the contaminated environment to its original state.
Extended exceedance of statutory or prescribed limits.
5 Massive effect Persistent severe environmental damage or severe nuisance
extending over a large area. In terms of commercial or
recreational use or nature conservancy, a major economic loss
for SE. Constant high exceedance of statutory or prescribed
limit.
Reputation (R)
0 No Impact No public awareness
1 Slight impact Public awareness of the incident may exist. There is no public concern.
2 Limited effect Some local public concern. Some complaints received. Slight media
and/or local political attention with potentially negative aspects for SE
operations.
3 Considerable Impact
Regional public concern. Numerous complaints. Extensive negative
attention in local media. Slight national media and/or local/
regional/national policies with potentially restrictive measures and/or
impact on grant of licenses. Mobilization of action groups.
4 National Impact National public concern. Continuing complaints. Extensive negative
attention in the national media and/or regional/national policies with
potentially restrictive measures and/or impact on grant of licenses.
Mobilization of action groups.
5 International impact International impact – international public attention. Extensive negative
attention in international media and national/international politics.
Potential to harm access to new areas, grants of licenses and/or tax
legislation. Concerted pressure by action groups. Adverse effects to SE
operations in other countries.
6.5-Hazard Checklist
13 | P a g e
H-02.04 Personnel Below Grade H-11 Environmental Hazards
14 | P a g e
TASK HAZARDS RISKS CONTROLS
H-02.03
Equipment falling Major or lost Heavy and unsafe
from height time injury to equipment’s like
Installation of Conduit and
head, legs, drills will be cord
accessory
arms or to prevent falls.
internal
organs
H-04.01
Improper use of Eye injury, PPE will be used
tools cuts, Hand Tools must be
injury used in
accordance with
manufacturer's
instructions
H-150.1
Suitable eye
Eye injury protection to be
worn where there
Dust, Particles is a risk of eye
injury, Goggle
when drilling.
H-02.01
Scaffold to be
constructed to
avoid gaps where
Injury to materials may fall
persons, through During
Falling objects erection, working
or dismantling of
the scaffold
workers shall not
be worked in the
area directly
below the
15 | P a g e
H-11.01
Adverse weather Injury to If there is high
conditions persons, wind and storm
work to be
suspended
Only trained
Major or lost .
time. Injury to
Unauthorized
head, legs,
access
arms or
internal
organs
10- RESPONSIBILITIESA
Trade Contractor Electrical Works Chief Engineer will be responsible for ensuring that the workers involved in the
task are familiar with the requirements of this method statement. A site H&S Inspector will be assigned to check
on the work in order that the correct safe working practices are being followed and that all necessary precautions
have been fully implemented.
11-ATTACHMENT
16 | P a g e