Name of the Site: 220KV GRID POWER IMPORT AT PANIPAT


REFINERY

Customer: M/s BHARAT HEAVY ELECTRICALS LTD

Sub Station: 220KV GRID POWER IMPORT AT PANIPAT


REFINERY

Scope of Work: 220/33KV BAYS COMMISIIONING

Project: KZ97

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 1 of
Visit Document

Visit Document

Contents
MINUTES OF MEETING 3

VISIT DETAILS 4

LIST OF OPEN POINT 29

COMMISSIONING COMPLETION CERTIFICATE 30

CUSTOMER FEEDBACK FORM ON GE T&D SERVICES 31

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 2 of
Visit Document

Minutes of Meeting

Minutes of Meeting held between M/s GE T&D (Chennai), M/s BHEL &
M/s IOCL on dated: 30-11-2023 at 220KV IOCL PANIPAT REFINERY
HARYANA.

Organization Represented by Signature


Mr. P.N.V.VARA
M/s GE T&D(Chennai)
PRASAD
M/s BHEL Mr. MUKESH KUMAR

M/s ADANI

Customer Service Call Objective:


Service Request (Please tick√)
Substation& Applicati
Commissi Trouble Relay Refurbis-
Circuit on /
oning Shooting Testing hment
Settings
220/33KV √
Work Accomplished:
Substation Circuit/product Work done Remarks
TESTING &
220KV IOCL 220/33KV BAYS COMMISIIONING
PANIPAT
REFINERY

Attachments to this Document (Please tick)


 Commissioning certificate
 Open points
 Comments by Customer

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 3 of
Visit Document

Visit Details
Project : KZ97
Site : 220KV GRID POWER IMPORT IOCL REFINERY
Customer : M/s BHEL
Panel / Relay Type : GE CRP

MOM held between M/S IOCL, M/s BHEL & M/s GE T&D INDIA LTD-
(Chennai) at 220KV IOCL PANIPAT REFINERY.

M/s IOCL M/s BHEL M/s GE T&D

M/s GE T&D SAS Engineer Mr. P.N.V.VARA PRASAD visited at 220KV IOCL
PANIPAT REFINERY on 23-08-2023 for the 220kV Bays commissioning
work.

The following works have been carried out under presence of M/s BHEL, M/s
IOCL & M/s GE T&D-(Chennai) representative.

The following points are completed in 220KV Bay D-01 Spare transformer-1

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9), Earth switch(Q81,
Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9) Earth
switch(Q81,Q89, Q8) are checked in SCADA, corresponding Alarm & event
checked in SCADA, and same was witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (Q81, Q89,
Q8) signals configured, corresponding alarm & event in checked in SCADA,
and same was witnessed by M/s BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 4 of
Visit Document

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same was witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same was
witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

6. Trip relays 86A, 86B reset command checked from SCADA, and same was
witnessed by M/s BHEL.

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same was witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-02 Transformer-1

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9), Earth switch(Q81,
Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9) Earth switch (Q81,
Q89, Q8) are checked in SCADA, corresponding Alarm & event checked in
SCADA, and same was witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (Q81, Q89,
Q8) signals configured, corresponding alarm & event in checked in SCADA,
and same was witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same was witnessed by M/s BHEL.
4. Synchro check for CB parameters are configured in SCADA, and same was
witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 5 of
Visit Document

6. Trip relays 86A, 86B reset command checked from SCADA, and same was
witnessed by M/s BHEL.

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same was witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-03 Grid incomer line-1

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9, 89X), Earth switch
(Q81, Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9, 89X) Earth
switch(Q81, Q89, Q9, 89XE) are checked in SCADA, corresponding Alarm
& event checked in SCADA, and same was witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9, 89X) and Earth switch (Q81,
Q89, Q8, 89XE) signals configured, corresponding alarm & event in checked
in SCADA, and same was witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 1000/1A PT


220KV/110V in SCADA, and same was witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same was
witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

6. Trip relays 86A & 86B reset command checked from SCADA, and same was
witnessed by M/s BHEL.

7. Auto Reclose function tested and found ok same was witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.
For For For
M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 6 of
Visit Document

The Following Points are completed in 220KV Bay D-04 Transformer-2

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9), Earth switch (Q81,
Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9) Earth switch (Q81,
Q89, Q8) are checked in SCADA, corresponding Alarm & event checked in
SCADA, and same witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (89AE,
89BE, 89LE) signals configured, corresponding alarm & event in checked in
SCADA, and same witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same


witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same witnessed by M/s BHEL.

6. Trip relays 86A, 86B reset command checked from SCADA, and same
witnessed by M/s BHEL.

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-05 Spare transformer-2

1. Remote operations for Breaker (52), Isolator (Q1, Q2, Q9), Earth switch (Q81,
Q89, Q8) and status of Breaker (52), Isolator (Q1, Q2,Q9) Earth switch (Q81,
Q89, Q8) are checked in SCADA, corresponding Alarm & event checked in
SCADA, and same was witnessed by M/s BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 7 of
Visit Document

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (Q81, Q89,
Q8) configured, corresponding alarm & event in checked in SCADA, and
same was witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same was witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same was
witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

6. Trip relays 86A, 86B reset command checked from SCADA, and same was
witnessed by M/s BHEL.

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same was witnessed by M/s BHEL.

8. Protection relay signals testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-07 Bus coupler

1. Remote operations for Breaker(52), Isolator (Q1, Q2), Earth switch (Q81,
Q82) and status of Breaker(52), Isolator (Q1, Q2) Earth switch(Q81, Q82)
are checked in SCADA, corresponding Alarm & event checked in SCADA,
and same was witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2) and Earth switch (Q81, Q82)
configured, corresponding alarm & event in checked in SCADA, and same
was witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 2000/1A PT


220KV/110V in SCADA, and same was witnessed by M/s BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 8 of
Visit Document

4. Synchro check for CB parameters are configured in SCADA, and same


witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

6. Trip relays 86A, 86B, reset command checked from SCADA, and same was
witnessed by M/s BHEL.

7 Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-08 Spare transformer-3

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9), Earth switch (Q81,
Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9) Earth switch (Q81,
Q89, Q8) are checked in SCADA, corresponding Alarm & event checked in
SCADA, and same witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (89AE,
89BE, 89LE) signals configured, corresponding alarm & event in checked in
SCADA, and same witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same


witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same witnessed by M/s BHEL.

6. Trip relays 86A, 86B reset command checked from SCADA, and same
witnessed by M/s BHEL.
For For For
M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 9 of
Visit Document

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-09 Transformer-3

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9), Earth switch (Q81,
Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9) Earth switch (Q81,
Q89, Q8) are checked in SCADA, corresponding Alarm & event checked in
SCADA, and same witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (89AE,
89BE, 89LE) signals configured, corresponding alarm & event in checked in
SCADA, and same witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same


witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same witnessed by M/s BHEL.

6. Trip relays 86A, 86B reset command checked from SCADA, and same
witnessed by M/s BHEL.

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 10 of
Visit Document

The Following Points are completed in 220KV Bay D-10 Grid incomer line-2

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9, 89X), Earth switch
(Q81, Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9, 89X) Earth
switch(Q81, Q89, Q9, 89XE) are checked in SCADA, corresponding Alarm
& event checked in SCADA, and same was witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9, 89X) and Earth switch (Q81,
Q89, Q8, 89XE) signals configured, corresponding alarm & event in checked
in SCADA, and same was witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 1000/1A PT


220KV/110V in SCADA, and same was witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same was
witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

6. Trip relays 86A & 86B reset command checked from SCADA, and same was
witnessed by M/s BHEL.

7. Auto Reclose function tested and found ok same was witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-11 Transformer-4

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9), Earth switch (Q81,
Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9) Earth switch (Q81,
Q89, Q8) are checked in SCADA, corresponding Alarm & event checked in
SCADA, and same witnessed by M/s BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 11 of
Visit Document

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (89AE,
89BE, 89LE) signals configured, corresponding alarm & event in checked in
SCADA, and same witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same witnessed by M/s BHEL.

4. Synchro check for CB parameters are configured in SCADA, and same


witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same witnessed by M/s BHEL.

6. Trip relays 86A, 86B reset command checked from SCADA, and same
witnessed by M/s BHEL.

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-12 Spare transformer-4

1. Remote operations for Breaker(52), Isolator (Q1, Q2, Q9), Earth switch (Q81,
Q89, Q8) and status of Breaker(52), Isolator (Q1, Q2, Q9) Earth switch (Q81,
Q89, Q8) are checked in SCADA, corresponding Alarm & event checked in
SCADA, and same witnessed by M/s BHEL.

2. Interlocks of Breaker (52), Isolator (Q1, Q2, Q9) and Earth switch (89AE,
89BE, 89LE) signals configured, corresponding alarm & event in checked in
SCADA, and same witnessed by M/s BHEL.

3. Metering values of BCU reporting with the CT ratio of 500/1A PT


220KV/110V in SCADA, and same witnessed by M/s BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 12 of
Visit Document

4. Synchro check for CB parameters are configured in SCADA, and same


witnessed by M/s BHEL.

5. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same witnessed by M/s BHEL.

6. Trip relays 86A, 86B reset command checked from SCADA, and same
witnessed by M/s BHEL.

7. Voltage selection logic configured as per the approved scheme, tested and
found ok and same witnessed by M/s BHEL.

8. Protection relay signal testing completed and same was witnessed by M/s
BHEL.

The Following Points are completed in 220KV Bay D-06 Bus bar Protection

1. Remote operations for Isolator (Q1, Q2), Earth switch(Q15, Q25, Q81, Q82)
and status of Isolator (Q1, Q2) Earth switch(Q15, Q25, Q81, Q82) are
checked in SCADA, corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

2. Interlocks of Isolator (Q1, Q2), Earth switch (Q15, Q25, Q81, Q82)
configured, corresponding alarm & event in checked in SCADA, and same
was witnessed by M/s BHEL.

3. Metering values of BCU reporting with the ratio of PT 220KV/110V in


SCADA, and same was witnessed by M/s BHEL.

4. Digital inputs and digital outputs of BCU have been configured as per
approved scheme and corresponding Alarm & event checked in SCADA, and
same was witnessed by M/s BHEL.

5. Protection relays signals testing completed and same was witnessed by M/s
BHEL.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 13 of
Visit Document

The Following Points are completed in 33KV Bay Existing incomer LIB-1

1. Relay protection signals testing completed and same was witnessed by the
customer M/s. BHEL.

The Following Points are completed in 33KV Bay Existing incomer LIB-2

1. Relay protection signals testing completed and same was witnessed by the
customer M/s. BHEL.
2. CB (52) Remote operations & signals testing completed and same was
witnessed by the customer M/s. BHEL.

COMMON POINTS

DEVICE USER NAME PASSWORD


MAIN SERVER Dcs_user Welcome!2
STANDBY SERVER Dcs_user Welcome!2
EWS & DRPC Dcs_master Welcome!1
GATEWAY-1 Dcs_user Welcome!2
GATEWAY-2 Dcs_user Welcome!2
OWS-3 Dcs_user Welcome!2
SMT Root Kz97@123#
Server & OWS HMIs Operator Kz97@123#

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 14 of
Visit Document

Common Points:-

1) Main server, standby server, main gateway and standby gateway are installed with
DS Agile 7.7.1.8 Aview base and found working satisfactory.
2) As per the approved system architecture network formation completed and found
satisfactory.
3) HI Vision software installed for NMS and working satisfactory.
4) Auto DR Configuration completed and working fine.
5) As per the approved signals list T104 – Gateway-1 & 2 configuration completed and
same was Gateway-1 tested up to the LDC.
6) XEROX DOC-2000 network printer is installed for all network PC.
7) SERTEL make GPS is installed for time synchronization and all IED’s are time synched
with the same SNTP Master and working fine.
8) Line bay AR timing :- 1.000 to 1.020 Sec
9) IMS reports are configured as per M/s ADANI request and same was working fine.
10) Final DB: - 7.100.6.0_BUILD1RC_KZ97_IOCL_PANIPAT_EN.1.52 loaded in all BCU,
Main & standby Servers and gateway main & standby servers.
11) Final backups all are saved in Local Disk-D: Final Back up Folder.

M/s GE T&D SAS Engineer left the site on 30.11.2023.

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 15 of
Visit Document

List of Open Points


Project : KZ97
Site : 220KV GRID POWER IMPORT AT PANIPAT REFINERY
Customer : M/s BHEL

End Client : M/s IOCL


Panel / Relay Type : GE CRP

Sl. Remarks
Description of Open Points
No.
Aux BCU DI & AI signal
1 From field side wiring not completed
testing with SCADA
Islanding panel need to
2
configure
OWS-7, EWS & DR PCs are
3 Power supply need to be provide M/s. BHEL Scope
installed
33kV SS-63 PR SAS-1 bay
4 Field wiring not completed M/s. BHEL Scope
testing Partially completed
OWS-4 HMI not installed in
5 Table was not arranged M/s. BHEL Scope.
PR control room
OWS-5 & OWS-6 HMI not
6 installed in PNCPP Control Furniture was not ready
Room
D-02, D-04, D-09, D-11
7 TRAFOs FOS & ODS not ICD files are not provided customer M/s. BHEL
configured

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 16 of
Visit Document

Commissioning completion certificate

P.O REFERENCE KZ97

M/s BHEL
CUSTOMER

220KV GRID POWER IMPORT AT


STATION NAME
PANIPAT REFINERY
220kV:
D-01, D-02, D-03, D-04, D-05, D-07 BUS
COUPLER, D-08, D-09, D-10, D-11, D-
Bay’s Involved
12, D-06 220kV BUSBAR
33kV:
SS-63 PR LIBS-1 & LIBS-2
TESTING COMPLETED ON 30-11-2023

D-03, D-04, D-09, D-10, BUS BAR -1 &


COMMISSIONING 2 BAYS ARE CHARGED.
COMPLETED ON D-02, D-07, D-11 BAYS ARE READY
FOR CHARGE.

SIGNATURE OF THE
CUSTOMER WITH SEAL

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 17 of
Visit Document

Customer Feedback Form on GE T&D Services


Customer : Mr. MUKESH KUMAR
Organization : M/s BHEL
Site : 220KV GRID POWER IMPORT AT PANIPAT
REFINERY
GE T&D Engineer : P.N.V.VARA PRASAD

PRESENT Service: (Please tick () the appropriate box)


Yes No
Do you feel that the job was handled time consciously?

Are you happy with services of this Engineer ?

Any suggestions for the engineer to improve

Did the service engineer briefed up on the Catalogue of Services


(Viz.Retrofit,Training )

Did the Service engineer handover the catalogue for Retrofit / Training

GENERAL:
Excellent Average Poor

Response Time

Quality of Response

Quality of Site Service

Quality of Relay repair

Any Suggestion to Improve:

Customer Name :
Designation :
Seal of the Customer:

For For For


M/s GE T&D India Ltd M/s BHEL M/s IOCL

P.N.V.VARA PRASAD MUKESH KUMAR

Page 18 of