PEMBANGUNAN STASIUN PENGUMPUL

LAPANGAN JATIASRI
No. Dok. : JAS-EPC-SP-DYN-20-R1-PR-004
FAT PROCEDURE
Rev. : A
Halaman : Hal 1 dari 10
Ini yang di FAT jenis pompa apa?

PT. PERTAMINA EP / REGIONAL 2 – FUNGSI


NAMA PEMILIK PROYEK :
PROJECT ZONA 7
NAMA PROYEK : PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI

LOKASI : SP JATIASRI

NO. KONTRAK : 002/PEP.80000/SP3MP/2022-S0

Prosedur yang disubmit ini agar disesuaikan dengan


pompa yang akan di FAT
-> dibawah ini prosedur untuk FAT centrifugal pump

Issued for
B 30 Oct 2023 Approvak TN TN IR AK PUR
28 AGUSTUS Issued For
A 2023 Approval TN TN IR AK PUR
DIPERIKSA DISETUJUI DIPERIKSA DISETUJUI
KONSORSIUM
REV. TANGGAL DESKRIPSI DISIAPKAN PT. WAHANAKARSA SWANDIRI – PT. ALDABERTA
DYNAPRO PUMPS ASIA INDONESIA
FAT PROCEDURE JAS-EPC-SP-DYN-20-R1-PR-004
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 REV.A
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Hal 2 dari 10

TABEL REVISI

REV. BAB HAL DESKRIPSI KOMENTAR REVISI/TANGGAPAN

Additional FAT Procedure


Fuel Tank and Valve
B Accessories
FAT PROCEDURE JAS-EPC-SP-DYN-20-R1-PR-004
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 REV.A
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Hal 3 dari 10

DAFTAR ISI

FAT PROCEDURE…FOR PUMP….………………………………………………..…………..……Lampiran 1


FAT PROCEDURE FOR FUEL TANK AND VALVE ACCESSORIES………….………………..Lampiran 2
Nama...

Nama...
yang di FAT centrifugal Pump atau Fire Pump?
FAT PROCEDURE FOR FUEL TANK AND VALVE ACCESSORIES

FAT Leak Test procedure for fuel tank 1000 L

1. Tank is filled with water to the brim, using PDAM Water up to nozzle level limit in the tank.
2. After the tank is full of water, leak test is carried out on the discharge welded joint, drain, and
the entire tank shell and tank body using a lime marker to make it easier to find out any
indications of leakage.
3. After the leak test, the tank is held for 1 x 24 hours, and 100% visual test is carried out.
4. After holding 1x 24 hours, there is no leakage and testing is acceptable, then the water is
drained and dried, then the inside tank shall be coated with diesel oil so as not to expand.
5. Review / approval of report documents must be completed and copies submitted to all parties
involved.

FAT test procedure for accessories valve

Aleum Swing Check Valve:

1. Prepare the Check Valve and Blind Flange for testing,


2. Close the valve section that will be tested on one side.
3. Position the Check Valve standing / vertical so that the seat or disc is closed.
4. Fill the Check Valve with water in the part covered by the flange until it is full.
5. Give pressure and holding time according to their class and Data Sheet also API 598 table 3 &
tabl 4.
6. Visually check for leaks from the other side that is not covered with a flange.

Aleum Butterfly Valve:

1. Prepare the Butterfly Valve and Blind Flange for testing,


2. Close the valve section that will be tested on one side.
3. Position the Butterfly Valve standing / vertical so that the seat or disc is closed.
4. Fill the Butterfly Valve with water in the part covered by the flange until it is full.
5. Give pressure and holding time according to their class in the Data Sheet and API 598.
6. Visually check for leaks from the other side that is not covered with a flange.

Valmatic Air Release Valve:

1. Prepare the Air Release Valve and Vlok Ring for connection to the testing tool.
2. Connect the Vlok Ring and Male Connector using seal tape.
3. Position it standing/vertically to detect leaks.
4. Give pressure and holding time according to the their class rating in the valve data sheet.
5. Check visually for leaks throughout the valve.