Professional Documents
Culture Documents
Module 2
Sand Piles
• These pile are formed by making hole in ground
and fill with the sand and well rammed.
• The sand to be used should be moist at time of
placing.
• Bore hole diameter usually 30 cm.
• length of sand pile is kept about 12 times its
diameter.
• The top of sand pile is filled with concrete.
• Sand pile are placed at 2 to 3 m spacing.
• Load test should be carried out determining the
bearing capacity of sand pile.
• Properly compacted sand pile can carry load up to
100 tone/m2 or more.
Pile Driving
• Process by which a pile is forced or
driven into the ground without
excavation or borings
• Piles are commonly driven by means of
hammer supported by a crane or by a
special device known as pile driver
• The hammer is guided between two
parallel steel members known as leads
• The leads are carried on a frame in such
a way that they can be supported in a
vertical position of an inclined position
Classification Based on Method of Installation
• Driven pile • Factor for selection of pile driving method
• Driven and cast-in-situ pile • Type of soil at site
• Bore and cast-in-situ piles • Costs of pile driving equipment
• Availability of fluid pressure
• Screw piles
• Material of pile
• Jacked pile
• Length of pile
• Ground water level
Classification Based on Method of Installation
• Driven pile • Driven pile
• Driven and cast-in-situ pile • These pile are driven into ground by applying blow with a
heavy hammer.
• Bore and cast-in-situ piles • Timber, steel and precast concrete pile are installed by
driving.
• Screw piles
• Jacked pile
• Drop hammer.
• It is the simplest method of pile driving.
Pile Hammer • A hammer is dropped on the head of the pile and is
guided during its fall by suitable staging.
• Jacked pile
Classification Based on Method of Installation
• Driven pile • Bore And Cast-in-Situ Piles
• Driven and cast-in-situ pile • These pile are formed by excavating a hole into the
ground and then filling it with concrete..
• Bore and cast-in-situ piles
• Screw piles
• Jacked pile
Classification Based on Method of Installation
• Screw Piles
• Driven pile • Made up of hollow cast iron or steel shaft
• Driven and cast-in-situ pile • External diameter of the shaft may vary from 15-
30cm
• Bore and cast-in-situ piles
• Helix or screw base at its base
• Screw piles
• If separate blades are provided , the blades may be
• Jacked pile made of cast iron
• The supporting power of screw pile is considerable,
and the pulling power is also large
• Screw piles can be driven without disturbing adjacent
structures
• Piles are screwed into the soil manually using capstan
bars or by motive power
Classification Based on Method of Installation
• Jacked pile
• Driven pile
• These piles are jacked into the ground by applying
• Driven and cast-in-situ pile a downward force by a hydraulic jack.
• Bore and cast-in-situ piles
• Screw piles
• Jacked pile
Under Reamed Piles
• These piles are developed by C.B.R.I for serving foundation for
black cotton soils, filled up ground and other type of soil
having poor bearing capacity.
• An under reamed pile is bored cast-in-situ concrete pile having
one or more bulbs or under reamed in its lower level.
• The bulb or under reamed are formed by under reaming tool.
• Diameter of pile is 20 to 50 cm and bulb diameter is 2-3 times
of diameter of pile.
• Length of pile is 3 to 8 m and spacing between piles are 2 to 4
m.
• Load carrying capacity can increase by making more bulb at
the base.
• The vertical spacing between two bulb is varies from 1.25 to
1.5 times diameter of bulb.
• For black cotton soil the bulb is increase bearing capacity and
also provide anchorage against uplift.
Under Reamed Piles
• Construction of Under Reamed Piles
• The equipment required for the construction of pile are,
• 1. Spiral auger - for boring
• 2. Under reamer - for making bulb
• 3. Boring guide -to keep the hole vertical
Bored Compaction Piles
• Modification of under reamed piles
• Used for foundation of structures of various types such
as residential and industrial buildings, overhead tanks,
towers, substations, gantry foundations, underground
tanks, over bridges etc.
• Combines the advantages of both bored and driven
piles by compacting freshly laid concrete and soil around
obtaining increased load carrying capacity over normal
piles.
• Suitable for loose to medium silty/sandy soils specially
with high water table.
• The reinforcement cage is not placed in the bore hole
before concreting
• After the concreting s over, the reinforcement cage is
driven through the freshly laid concrete
Coffer Dam
• Temporary enclosure in a river, lake etc
• Build around a working area for the purpose of excluding water during
construction
• Pumping is needed while constructing
• Made of earth materials, timber or steel sheet piling
• Types of Coffer Dam:
• Cantilever sheet pile coffer dam : suitable fro small heights
• Susceptible to large leakage and flood damage
• Braced Coffer Dam : Economical , small to moderate height
• Embankment protected Coffer Dam- no height limitation, occupy large base area
• Double wall coffer dam- suitable for moderate height
• Cellular coffer dam- suitable for moderate and large heights
Braced Coffer Dam
• Cutting Edge:
• Sharp edge which is provided at the lower end of the well or open and
pneumatic caisson for accelerating sinking operation is called cutting
edge.
• It is made up steel or it is made in R.C.C.
• The cutting edge should be sharp so as to penetrate into the soil and it
should resist the various stresses caused by blows, boulders, blasting, etc.
• A sharp vertical edge is generally provided to the outside face of the
caisson. Edge facilities the rate of sinking.
Caissons : Well Foundation
• Well Curbs
• It is made of concrete or brick.
• Cutting edge of well or caisson is attached to well
curb.
• During sinking operation well curb impart to the well
steining and facilities the formation of bottom
• Bottom Plug
• After final grounding of the well to the required
foundation level, a concrete plug is provided.
• The bottom plug transfer the entire load to the
ground.
• The bottom plug functions as an inverted dome
supported along the periphery of the steining.
• As it is not feasible to provide reinforcement at the
bottom, it is generally made thick and a rich
concrete mix (M20) is used.
Caissons : Well Foundation
• Sand Filling
• The bottom plug concrete is cured and after
curing, the well is filled with sand in saturated
condition.
• Steining
• Steining is constructed in concrete or masonry
work.
• Use of steining is to provide dead load during
sinking operation.
• Topping
• Covering provided over the well or caisson is
called as topping.
• Sand is filled in between topping and bottom plug.
Topping also acts as a part of shuttering for laying
the well cap.
Caissons : Well Foundation
• Pneumatic Caisson
Caissons : Well Foundation
• Box caisson
• This type of caisson is similar to open caisson except that it is closed at bottom.
• The caisson is cast and cured on land and when required, it is launched in water
and towed to the site for sinking.
• the caisson is sunk by filling sand, gravel, or concrete in the empty space inside.
• The place where the caisson base is to rest must be leveled and as such box
caissons are used in places where the strata of sufficient bearing capacity is
available near the ground.
• In normal practice, the soft natural bottom soil of the river bed is dredged out to
some depth and the trench thus formed is filled with sand to have a leveled base.
• The function of the sand layer is to uniformly distribute the superimposed loads
over the soil below and thus avoid tilting of the caisson.
• Pneumatic caisson:
• This type of caisson is closed at top and open (during construction) at the bottom.
• The water is excluded from the caisson chamber by means of compressed air.
Timbering in Trenches
• When the depth of trench is large or when the subsoil is
loose ,the sides of trench may cave in.
• The problem can by adopting a suitable method of
timbering
• Timber of trenches ,sometime also known as ‘shoring’
consists of providing timber planks or boards and struts to
give temporary support to the sides of the trench
Timbering in Trenches
• Various methods of timbering:-
• Stay bracing
• Box sheeting
• Vertical sheeting
• Runners system
• Sheet piling
Timbering in Trenches
Stay bracing Box Sheeting
• When the trench soil is firm and the depth of This Method is used when excavation is to be carried
excavation does not exceed 2.0 meters, this out in loose soil and when the depth of excavation
method is used for supporting the sides of a trench does not exceed 4 meters.
Timbering in Trenches