Agenda

Reference No : 16

Project Name : WALTERMART PANIQUI Date : October 27, 2017

Purpose : MANAGEMENT MEETING

Venue : PROJECT SITE Time : 10:30 AM

Circulation : WMSCMI / CMGI / LAPAA / TRANSCENDPRO / DPC / EXCEL / JOM / AVC / ESTI

Overall % Weekly Accomplishment as of October 19, 2017

Item No. Notes

I. DESIGN/OWNER'S ISSUE
A. Cooling Tower/Pedestal Base Body
B. Presentation of Approach for Duct Penetration to Truss at Front Body
C. Updated Tenant Cut-outs for Utility Provisions WMSCMI
D. Relocation of Exhaust Air Drill for Common Toilet Body
E. Updates/Coordination for delivery of equipments:
e.1 Weida Weida Phil.
e.2 Others
F. Others Body

II. CONSTRUCTION ITEMS

Page 1 of 2

FORM NO.: CM 000-001


A. Project Reporting TranscendPro
1.0 Update on the Structural works
1.1 Roof Framing for Power Center & Front AHU Room
1.2 SOG
1.3 Precast / RC Perimeter Wall
1.4 Site Devt.
1.5 STP
2.0 PLDT/MTTC Room Update TPRO / AVC
3.0 Excel Roof Update on Roofing Works Excel
4.0 AVC Update on Electrical Works AVC
5.0 DPC Update on Mechanical Works DPC
6.0 TPRO Update on P/S and FP works TPRO

B. Others Body

III. ADJOURNMENT

Prepared and transcribed by:

CONSTECH Management Group, Inc.

Page 2 of 2

FORM NO.: CM 000-001