Cable Installation For Toxic H2S Gas Detector
Cable Installation For Toxic H2S Gas Detector
Excavation volume
Reference Drawing
No. Description Total Length (m) Total Volume (m3)
Civil Underground Layout Cable Routing Layout
1 Excavation 93.10 121.03 11-GTPOGT-C-0505 11-GTPOGT-I-1578-002
115.87 173.81 11-GTPOGT-C-0507 11-GTPOGT-F-2100-012
134.89 202.34 11-GTPOGT-C-0508 11-GTPOGT-F-2100-011
118.60 228.70 11-GTPOGT-C-0511 11-GTPOGT-F-2100-009
135.01 578.79 11-GTPOGT-C-0513 11-GTPOGT-F-2100-010
Total 597.47 1,304.67
Note:
Cable routing
1
2
Underground cable routing from new JB at WWTP to existing FGS Marshalling Cabinet at Local Instrument Room
WO-020(1)-D
3
Underground cable routing from new JB at WWTP to existing FGS Marshalling Cabinet at Local Instrument Room
WO-020(1)-D
3
Underground cable routing from new JB at WWTP to existing FGS Marshalling Cabinet at Local Instrument Room
WO-020(1)-D
4
Underground cable routing from new JB at WWTP to existing FGS Marshalling Cabinet at Local Instrument Room
WO-020(1)-D
5
Underground cable routing from new JB at MEG package to existing FGS Marshalling Cabinet at Local Instrument Room
WO-020-D
7 8
6
Local Instrument Room
CIVIL DRAWING
Trench path
2
2
3
3
4
5
4
7 8