MRP Run for Single Item

Purpose

The aim of material requirements planning is to tailor available capacities and receipts on time to suit
requirements quantities. You can use MRP or consumption-based planning for this purpose. Single-
item multi-level requirement planning is performed for plant KP03.

Prerequisite

The trading goods (190) is planned at plant level. There is now a requirement for the material 190 in
plant KP03.

Procedure

Log onto the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori
launchpad displays.

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
1
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

Open Schedule MRP Runs (F1339).

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
2
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

The Application Jobs screen displays.

Choose Create.

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
3
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

On the New Job screen, make the following entries:

For 1. Template Selection section:


● Job Template: Material Requirement Planning (MRP)

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
4
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

● Job Name: <MRP for KP03>

Choose Step 2.

For 2. Scheduling Options section:


● Start Immediately: <select>

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
5
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

Choose Define Recurrence Pattern.


On the Scheduling Information screen, make the following entries:

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
6
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

● Start Immediately: X

● Recurrence Pattern: Single Run

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
7
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
8
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

Choose OK.

Choose Step 3.

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
9
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

Choose 4 Parameters and make the following entries:

● Plant: 1010

● Material: TG11

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
10
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

● Changed BOM Components: select

● Planning Mode: 1

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
11
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

Choose Check at the bottom right.

Choose Schedule.

A message appears: You can go ahead and schedule the job.

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
12
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

To check the job’s status, enter KP03 in the search box and choose Go at the top right section of the
screen.

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
13
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

The new job is created and is displayed in the Application Jobs table when refreshed.

Result

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
14
Mickael QUESNOT © SAP CLOUD PUBLIC EDITION

Mickaël QUESNOT © - Copyright

https://www.linkedin.com/in/mickaelquesnot/
15