PROFORMA - 'A'
TO ACCOMPANY THE ESTIMATE FOR SANCTION AS PER CIRCULAR No. PWD 17
AIM 73, DATED 02-07-1973
A. ALIGNMENT AND PREPARATION OF ESTIMATE
B CLASSIFICATION
9 While preparing the Estimate whether average rates Common S.R. for the year 2021-22
based on major classification in the trial pits is arrived considering issue rates of Cement /
at? steel for 2nd Quarter of FY 2022-23.
PROFORMA - 'B'
TO ACCOMPANY THE ESTIMATE FOR SANCTION AS PER CIRCULAR No. PWD 17
AIM 73, DATED 02-07-1973
A DESIGN
1 Is section of the canal designed for approved Yes, enclosed.
discharge capacity in the reach and are designed
calculations enclosed to the Estimate
2 With reference to the slopes provided for the sides of Yes.
the canal is stable and optimum.
3 Are there any reaches where hard strata is met with? In water prism portion minimum 1:1
If so whether steeper slopes for canal sides have been side slope is proposesd. 1/2 :1 side
proposed on economic or other considerations. slope is proposed in hard rock above
water prism.
4 Are swelling type of soil met with? If so whether the Yes.
cohesive non swelling layer has been provided and is
optimum with reference to the canal in full cutting?
5 Are the widths of I.P and S.R as per the approved S.R. of 3.65 m width and I.P. of 1.8 m width are
design standards and whether their inner toes are kept proposed for BD's & S.R. of 3.05 m width and
at a margin of three meters from the edge of the canal I.P. of 1.2 m for width are proposed for Laterals
in full cutting? & Sub Laterals.