PROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INCONESIA

Owner Consultant Management Main Contactor

GDS WSP
PT. ACSET INDONUSA
Nomor : 006/AI/NDP/STC Wooden Formwork for Pilecap Revisi No : N.A

METHOD OF STATEMENT

PURPOSE
To specify the requirements of civil construction including excavation, filling, and aligned
activities complying with the contract document, specification, and scope of work and approved
drawings/documents

SCOPE
This Method Statement applies to all the civil works - Excavation including ground preparation,
setting out, backfilling, soil compaction, concreting, wood formwork - related to the construction of
building as per project requirements, referring with approved Civil and MEP drawing.

ROLES & RESPONSIBILITY


The primary responsibility of carrying out all the activities mentioned in this procedure rests with
the site- in-charge unless mentioned otherwise.
Project Leader:
Overall execution and administration of the project as per contract requirements, specifications and
the for preparation and updating of PQP. Directly control the Site Engineers and Supervisors.

Project Operation Manager: Assess manpower, equipment or other resources required to ensure timely
completion of the project. Monitor availability of all materials as per schedule. Inform the Project
Leader for any non-availability of materials to take proper action. Carry out receiving inspection in
coordination with the QA/QC Engineer.

Site Engineer: Ensure that the drawings and documents are up to date and the latest drawing is
available and is being utilized in the project site works. Filled-up the check-sheet and submit the
necessary IR to the QA/QC function when the work is ready for inspection.

QA/QC Engineer: Responsible for the monitoring and implementing of quality related matters and
ensure the works are being executed with the approved Project Quality Plan.

Safety Officer: Responsible for monitoring and implementation of safety related matters such as
work permits, First Aid, PPE, approval of diversions, follow the safety and traffic regulations by all
the workmen during the construction, according to the approved project HSE plan. First Aid boxes are
readily available with HSE officer.

Supervisor/Foreman:Plan and obtain required manpower and resources in coordination with the
project operation manager. Carry out all activities as per the planned schedule to achieve target dates.
Coordinate with respective disciplines of work and liaise with the site engineer for day to day
activities. Inform Discipline Engineer regarding site inspections when it is ready. Ensure pre task
briefing is to be conducted prior to start of work at each session.

Worker:Works shall be executed as per direction of Supervisors/Foremen for all activities as per
the planned schedule to achieve target. Coordinate with respective
disciplines of work and liaise with the Supervisors/Foremen for day to day activities. Ensure pre task
briefing is conducted prior to start of work at each session.

Page 1 of 6
PROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INCONESIA
Owner Consultant Management Main Contactor

GDS WSP
PT. ACSET INDONUSA
Nomor : 006/AI/NDP/STC Wooden Formwork for Pilecap Revisi No : N.A
REFERENCE DOCUMENTS
Contract Document & Bill Of Quantities.
Civil structural and architectural drawing issued for construction.

INSPECTION & TESTING


Site inspection/approval shall be in accordance with the approved Inspection and Test Plan for all
activities.

WORK PERMITS
All necessary work permits shall be obtained prior to the commencement of any activity at site and
shall remain valid throughout the entire duration of the operation. Safety Barriers and Site sign boards
will be installed prior to the work commencement.

HEALTH, SAFETY AND ENVIRONMENTAL PROCEDURES

Requirements of Health, Safety and Environmental for the project shall be in accordance with
approved Project HSE Plan.Before commencing of any work, the required and applicable work permits shall
be checked and ensure all requirements of WP are compiled and they are valid until completion of the
activity and as per approved HSE plan.

All personnel accessing their site will wear the mandatory PPE. All workmenship and staff shall
wear the mandatory and job specific Personnel Protective Equipment's. Pre-task briefing shall be
conducted on every day before starting the work. Experienced and HSE inducted workmen shall be deployed
for the work. All personnel shall be cautioned while working near any live lines such as power cable,
water lines, drainage lines,etc.

Prior to commencement of work all workers shall be given pre-task briefing. Hazards identified for
the activity shall be disseminated during pre-task briefing, especially for underground services, slip &
trip, improper access, excavation tools handling, no access or
aggress, vehicle collision, heat exhaustion, which shall be identified and documented separately by
permit to work system as per approved HSE plan.

First aid stations complete with all first aid equipment and trained first aiders shall be
maintained for the initial care. Safety and security procedures shall be implemented as a minimal,
warning signs and barricades, railing and other safeguards shall be provided as required by the nature
and location of the work.

Page 2 of 6
PROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INCONESIA
Owner Consultant Management Main Contactor

GDS WSP
PT. ACSET INDONUSA
Nomor : 006/AI/NDP/STC Wooden Formwork for Pilecap Revisi No : N.A
1. References

1.1 Technical Specifications

2. Resources
2.1 Materials
2.1.1 Readymix Concrete
2.1.2 Reinforcement Bar
2.1.3 Lean Concrete
2.1.4 Sand
2.1.5 Brick
2.1.6 Mortal
2.1.7 Brick Formwork
2.1.8 Stack Wood
2.1.9 Lubricant oil
2.1.10 Bonding Agent
2.2 Equipment
2.2.1 Excavator
2.2.2 Concrete mixer
2.2.3 Concrete vibrator
2.2.4 Bar bender
2.2.5 Bar cutter
2.2.6 Concrete pump

3. INSTRUCTION OF WORK
3.1 Preparation at work
3.1.1 Measure and install bow plank at the pilecap need to be digging.
3.1.2 Area clearing of the material which obstacle jobs.
3.1.3 Check whether utility may obstacle with the digging job.
3.1.4 If yes, coordinate with Site Engineer and Consultant to solve the problem.
3.1.5 Reposition task should be permitted competents personel and consultant.
3.2 Digging soil work, cut off pile and lean concrete.
3.2.1 Soils are being used to dig by excavator and manual digging should be accordance shop
drawing.

Page 3 of 6
PROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INCONESIA
Owner Consultant Management Main Contactor

GDS WSP
PT. ACSET INDONUSA
Nomor : 006/AI/NDP/STC Wooden Formwork for Pilecap Revisi No : N.A
3.2.2 Output of soil digging keep a side or transfer to design area for temporary. Then
collect back and backfill back with compaction.
3.2.3 Cut of pile meet the level plan

3.2.4 Demolish the spun pile and ensure the strand 50cm*1.02 with 508mm, rectangle pile off
the ground 150mm.

3.2.5 Lean concrete with thickness 100mm.

3.3 Wooden Formwork, Rebar and Casting work


3.3.1 To identify elevation on the underground and ground level
Page 4 of 6
PROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INCONESIA
Owner Consultant Management Main Contactor

GDS WSP
PT. ACSET INDONUSA
Nomor : 006/AI/NDP/STC Wooden Formwork for Pilecap Revisi No : N.A
3.3.1.1 Installation of reinforming bar for the pile cap and tie beam, should be ready and
completed with mark and align building.
3.3.1.2 Fabricate and assembly rebar at the indicated designation area. For the pilecap,
column and tie beam.it shall be met the BBS bar bending schedule planning.
3.3.1.3 Wood Formwork is being used and combined with plywood and hollow support. It should
be fixed by solid, rigid, not movement. Plywood could not be reused more than 4
times.
3.3.1.4 Backfill dan Digging the soil to reach for the and install brick formwork.
3.3.1.5 Installation of pilecap, column, and tie bar with cover concrete.
3.3.1.6 Do backfill soil in the edge side and compacted as per layer 30cm.
3.3.1.7 Assembly rebar slab on the site.
3.3.1.8 Before concreting, all the reference should mark and installed with rigid
condition. To clean up everything irrelevant substances.
3.3.1.9 Plywood surface should be rolled up lubricant before pouring concrete.
3.3.1.10 Casting of pile cap, tie beam and slab to be use readymix as design indicated
completed with slump test and cylinder sample.
3.3.1.11 During casting shall be available concrete pump vibrator.
3.3.1.12 After complete casting, should be complete overlay goni or geotextile for the
curing during seven days. To prevent crack and sinkage of the casting.
3.3.1.13 On the completion all the tools and materials must be kept in proper designated
area.

Page 5 of 6
PROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INCONESIA
Owner Consultant Management Main Contactor

GDS WSP
PT. ACSET INDONUSA
Nomor : 006/AI/NDP/STC Wooden Formwork for Pilecap Revisi No : N.A

The under-mentioned pilecap table is provided code of technical dimension :

4. Safety
4.1 Safety kick-off meeting
4.2 PTW Cold and Hot and JSA
4.3 Safety Signs

5. Attachments
5.1 Shop drawing Pilecap
5.2 Trail Mix test Concrete fc’33.2 MPA on 7th to 28th Days

Page 6 of 6
NOTE :

4000

600 1400 1400 600

600
1400 D25-150

D25-300
B
4000

D25-300
- KEY PLAN

D25-150
D25-150
1400

D25-150 D13-150 LINK

GRADIE
NT
1:12
600

PC9A DETAIL
SCALE 1:50 - - - -
By Drawing Description Rev Date

SHOP DRAWING
CLIENT / LAND OWNER:

GDS IDC SERVICES

4000 LEAD / M&E CONSULTANT:


HDR Consulting Pte. Ltd.
350 Orchard Road
#18-01/02 Shaw House
Singapore 238868
75 F1 D25-150 75 T: +65 6864 9950
F: +65 6491 1259
ARCHITECT:
F1' D25-150 3HPArchitects Pte. Ltd.
75

Blk. 162 #04-3555 Bukit Merah Central


75

Singapore 150162
T: +65 6235 8333
F: +65 6733 0809

LOCAL CONSULTANT:

VERTICAL BAR F3' D25-300 F5 D13-150 LINK PT. HASKON CITRA PERDANA
F4 D25-900 F3 D25-300 Jl. Mas Surya Negara 1, Kawasan Industri Terpadu Kabil
Kompleks Citranusa Niaga Blok A2 No. 5-7
Batam 29467 - Indonesia
CONCRETE CAST IN SITU
2000

T: +62 778 711116 - 711265


1725

F: +62 778 711115

F2 D25-150 LEED CONSULTANT:


Building System and
Diagnostics Pte. Ltd.
EXISTING PILE BAR 22 Veerasamy Road,
F2' D25-150 TO BE EXPOSED
Singapore 207328
T: +65 6560 0702
F: +65 6795 0020
50
150

MAIN CONTRACTOR :
PT. ACSET INDONUSA TBK
ACSET BUILDING

600 1400 1400 600 100mm THK JL. Majaphit No.26


Petojo Selatan - Gambir

LEAN CONCRETE member of ASTRA


Jakarta, Indonesia 10160
Telp : (021) 3511961
Fax : (021) 3441413
E-mail : corporate.secretary@acset.co

PROJECT :
SQ. 500mm CONCRETE PILE PROPOSED 3-STOREY
DATA CENTER BUILDING DEVELOPMENT
AT NONGSA - BATAM ISLAND, INDONESIA

SECTION B-B TITLE

SCALE 1:50 CONCRETE PILE CAP PC9A DETAILS AND SECTION

Approved Plot Size Date


A3 27 NOV 2023
-
Scale Rev.
Designed
1:50 00
- Refer To. 10330442-CS-GF-541
Drawn
Drawing no. SD-AI-STR-DCB-GF-006
-