You are on page 1of 19

R7 Canal Appartments

on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE


PROGRAMME :

CONTIGUOUS PILE WALL SHORING SYSTEM:

Perimeter No of days
Section Diameter Length No Piles Depth No of Days No of Days Allowed
M M (Two rigs)
Section -1(R) 600mm 496.00 792 11.5
Section -2(R) 750mm 44.00 65 13.5 86
Section -1(canal) 600mm 410.60 656 13.5
951
ANCHORING

No of No of days
Section Anchor Level Anchor Spacing Anchors No of Days No of Days Allowed

1st level (Two mech.)


Section -1(R) 2.3m 1.89 m 264
Section -2(R) 2.3m 1.89 m 27 20
Section -1(canal) 2.3m 1.89 m 219
510
PILING(PROVISIONAL)

No of days
Pile dia No of piles Depth (Max.) No of Days No of Days Allowed

900mm 1120 18 to 21.5M 93


1,120

PILING TESTING

Working Load
Pile dia (tons) Test Load (tons) Nos No of Days No of days Allowed
Working Load Testing
900mm 12 15

Excavation 183,000 cu.m 37 30

Mobilisation Period 15

Specified 150 days incld.Mobilisation period Total No of Days 259


R7 Canal Appartments
on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE
PROGRAMME :

SECANT PILE WALL SHORING SYSTEM

Perimeter No of days
Section Diameter Length No Piles Depth No of Days No of Days Allowed
M M (Two rigs)
Section -1(R) 600mm 496.00 #REF! 11.5
Section -2(R) 750mm 44.00 266 13.5 130
Section -1(canal) 600mm 410.60 #REF! 13.5
951
ANCHORING

No of No of days
Section Anchor Level Anchor Spacing Anchors No of Days No of Days Allowed

1st level (Two mech.)


Section -1(R) 2.3m 1.89 m #REF!
Section -2(R) 2.3m 1.89 m 156 20
Section -1(canal) 2.3m 1.89 m #REF!
#REF!
PILING(PROVISIONAL)

No of days
Pile dia No of piles Depth (Max.) No of Days No of Days Allowed

900mm 1120 18 to 21.5M 93


1,120

PILING TESTING

Working Load
Pile dia (tons) Test Load (tons) Nos No of Days No of days Allowed
Working Load Testing
900mm 12 15

Excavation 183,000 cu.m 37 30

Mobilisation Period 15

Specified 150 days incld.Mobilisation period Total No of Days 303


Octavian Tower
on Plot No: BB.B01.015, 016, Dubai, UAE

Office Accommodation for the Employer's

The Following Minimum requirements shall be Provided:


Qty Rate Amount
Room N Description
1 Architect 16 850 13,600
2 Civil/Stru.Engineer 16 850 13,600
3 Conference room 32 850 27,200
4 Mech+Elect Eng. 32 850 27,200
5 Toilet with shower 5 850 4,250
6 Kitchen 6 850 5,100
7 Store/Sample room 24 850 20,400
8 Covered Parking - 7 no 3mx5.5m 115.5 450 51,975
Project Manager
FurnitureReadymade Executive Desk 1 4000 4,000
Executive Chair 1 1500 1,500
Arm chairs 1 1000 1,000
Filing Cabinet 1 1500 1,500
Cupboard 1 3000 3,000
Wastepaper Basket 1 150 150
PC 1 6500 6,500
Laser printer(A4) 1 1500 1,500
Wall Mounted Pin Board 1 500 500
Telephone 1 9,000
Air-conditioning(1.5ton) 1 2000 2,000
Engineer
FurnitureReadymade Executive Desk+six drawers & leathe 2 8000 16,000
Conference Table 1 12000 12,000
Executive Chair 1 1500 1,500
Arm chairs 1 750 750
Filing Cabinet 1 5000 5,000
Cupboard 1 3000 3,000
Office Table 1 3000 3,000
Revolving Chair 1 2000 2,000
Side Table 1 1000 1,000
Wastepaper Basket 1 250 250
PC 1 6500 6,500
Laser printer(A4) 1 1500 1,500
Telephone 1 6000 6,000
Air-conditioning(1.5ton) 1 1500 1,500
Meeting room

Visitors chairs 10 750 7,500


White Board 1 600 600
Wall Mounted Pin Board 1 500 500
Air-conditioning(1.5ton) 2 2000 4,000
Photocopier 1 15000 15,000
Fax 1 2000 2,000
Octavian Tower
on Plot No: BB.B01.015, 016, Dubai, UAE

Telephone 1 16,000
Internet Connection(for 2PCs) 2 44,500
Digital Camera 2 3500 7,000
networking 3
Auto CAD 2 18000 36000
UPS System 3 350 1050
Networking 3 500 1500
Server 1 15000
Sample room
Wooden racks 3 1500 4,500
Pantry(Type-1A & Meeting Room)
Sink and Drainign board 1 1000 1,000
Cooker 1 1500 1,500
Refrigerator 1 8000 8,000
Chilled Water dispenser 1 750 750
Cupboard 1 1500 1,500
Utensils 1 1500 1,500

Maintanance Cost No.of


/ month months
Office Boy ( 1 Nos) 3000 10 30,000
Office attendant 4500 10 45,000
Refreshments 2000 10 20,000
Consumables & Stationary 3000 10 30,000

Total Engineer's Office 548,375


R7 Canal Appartments
on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE

PRELIMINARIES

S.No Description of Work Check List Unit Rate Amount

1 Provision of Office facilities for Engineer and their ✘ Item incld


Maintenance.

2 Provision of Office facilities for Contractor and their ✘ Item incld


Maintenance.

3 Provision of Electricity for our works during the ✘ Item 192,000


contract period.

4 Provision of Water supply for our works during the ✘ Item 24,000
contract period.

5 Provision of Site Fencing around plot area with ✘ Item incld


Entrance gate & Exit gates

6 Provision of Sign board ✘ 2 Nos incld

7 Provision of Performance Bond, Advance Payment, ✘ Item 24,000


Tender Bond

8 Provision of Insurances like all risk, workman ✘ Item 15,000


compensation, Machinery etc

9 Provision of Fire fighting & First Aid facilities on ✘ Item 12,000


site.

10 Provision of Municipality permits ✘ Item 20,000

11 Provision of Monthly progress reports and ✘ Item 12,000


photographs

12 Provision of Sanitary facilities on site ✘ Item 12,000

13 Provision of Shop drawings / As built drawings ✘ Item incld

14 Consultant's over time charges ✘ Item 45,000

15 Provision of Watchman for site security ✘ Item incld

16 Ascertaining the location and Identification of ✘ Item incld


existing services by carrying out trial pits.

17 Provision of Safety, Health and Welfare ✘ Item Incld

18 Provision of cleaning person/office attendant for ✘ Item incld


Engineer's office

19 Provision of test certificates of cranes and ✘ Item 6,000


equipment.

20 Provision of mobilisation & Demobilisation ✘ Item 20,000

21 Provision of temporary gatch for equipment ✘ Item 20,000


movement

22 Provision of telephone facilities on site ✘ Item incld

23 Site survey ✘ Item 5,000

To Collection
407,000
Piling Summary:

Pile Capacity
Pile Type Pile Dia Pile Nos (ton) COL Concret level Toe Level Pilel ength
P1 800 15 380 -12.65 -10.75 -26 13.35
P2 1200 108 800 -17.25 -14.75 -28 10.75
P3 1200 8 770 -13.85 -10.75 -26 12.15
P4 1200 10 770 -13.35 -10.75 -26 12.65
P5 1000 2 550 -12.85 -10.75 -26 13.15
P6 1000 2 400 -12.85 -10.75 -26 13.15
P7 600 21 260 -11.95 -10.75 -26 14.05
166
Reinforcement Shall not be lessthan 1%
Pilel ength
Time Towers
on Plot No 7 and 8, Abu Dhabi, UAE

1,076 525 564,900


43,439 22 955,658
160,276 22 3,526,072
189,630 18 3,413,340
8,459,970

Shoring
978 20,905 20,445,090
50,000
20,495,090

Piling
6 80,000 480,000
746 18,160 13,547,360
238 23,495 5,591,810
136 26,825 3,648,200
23,267,370

Tesing
12 40,000 480,000
56 4,500 252,000
1,120 30 33,600
168 4,500 756,000
1,521,600
Time Towers
on Plot No 7 and 8, Abu Dhabi, UAE

20,000
216,000
60,000
200,000
288,000
36,000
192,000
102,000
12,000
8,000
200,000
460,000

1,794,000

Site works
8,459,970
20,495,090
23,267,370
1,521,600
53,744,030

53,744,030
1,794,000
55,538,030
Time Towers
on Plot No 7 and 8, Abu Dhabi, UAE

1,076 455 489,580


43,439 22 955,658
160,276 22 3,526,072
189,630 18 3,413,340
8,384,650

Shoring
978 29,180 28,538,040
50,000
28,588,040

Piling
6 80,000 480,000
746 18,325 13,670,450
238 23,720 5,645,360
136 27,130 3,689,680
23,485,490

Tesing
12 25,000 300,000
56 4,500 252,000
1,120 30 33,600
168 4,000 672,000
1,257,600
Time Towers
on Plot No 7 and 8, Abu Dhabi, UAE

42,000
864,450
172,000
536,000
583,750
270,000
50,000
899,000

3,417,200

Site works
8,384,650
28,588,040
23,485,490
1,257,600
61,715,780

61,715,780
3,417,200
65,132,980
R7 Canal Appartments
on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE
Type-1(Road side) 60cm dia Contiguous Piles Perimeter 496.0 m
Ex.ground Level 23.25 M DMD
No of Reinforced Piles = 792 Nos Excavation Level 13.31 M DMD
No of Non-Reinforced Piles = 0 Nos Toe level 9.75 M DMD
Total Piles = 792 Nos Road side R
Platform level = 21.25 M BM 301 kn.m
Pile Toe Level = 9.75 M S.F 120 Kn
Cut-off level = 20.65 M Anchor 1 160 @ 1.89 m
Concreting level = 21.25 M
Boring Length = 11.500 m
Concreting Length = 11.500 m
Cut-off Length = 10.900 m
Pile Diameter = 0.600 m
Concrete Wastage = 20%
Concrete Cover = 0.075 m
Reinforcement Details
Main Bars Length Over lap Helicals
Type T1 8 T 25 mm , 12 m 0.00 m Type H1 T 10 @ 150 mm 10.90 m
Type T2 8 T 25 mm , 0m 0.00 m Type H2 T 10 @ 150 mm 0.00 m
Type T3 8 T 25 mm , 0m 0.00 m Type H3 T 10 @ 150 mm 0.00 m

Description Qty Total Qty Rate Amount


Concrete 4.2 3326.4 450 1,496,880.00
Steel Reinforcement
Main Bars 0.380928 301.69 3450 1,040,830.50
0 0.00 3450 0.00
Helicals 0.0758 60.03 3450 207,103.50
0 0.00 3450 0.00
Tie Back Anchor 264.00 7000 1,848,000.00
Spacers 4 Per row Summary
4.00 16 12672 0.75 9,504.00 Cost of matls & others 6,187,305.20
Tying Wire 4,752.00 Mobilization 67,000.00
Cube Testing 402 10 4,020.00 Workmanship 3,643,200.00
Anchor Testing 27 2000 54,000.00 9,897,505.20
Concrete Panels 992 200 198,400.00
Universal Beams 250 1250 312,500.00
Steel Testing 3,617.20
Couplers 8 6336 0 0.00
Bentonite 0.0698 55.282 0 0.00
Debris Di 4.65 3682.8 35 128,898.00 Rate per pile 12,496.85
Independent Insp. 71 700 49,700.00 Rate per lm from col 1,146.50
QA/QC & Safety 71 500 35,500.00 Rate per lm for boring 1,086.68
Electricity 71 0 0.00
Water 162.1 0 0.00
Guide Wall 496.00 750 372,000.00
Capping Beam 496.00 850 421,600.00
Workmans 11.500 9108 400 3,643,200.00 Total shoring Amount 20,209,884.95
Mobilisation 792 0 67,000.00
9,897,505.20 Rate/LM 21,260.14
R7 Canal Appartments
on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE
Type-1(Road side) 75cm dia Contiguous Piles Perimeter 44.0 m
Ex.ground Level 23.25 M DMD
No of Reinforced Piles = 65 Nos Excavation Level 13.31 M DMD
No of Non-Reinforced Piles = 0 Nos Toe level 7.75 M DMD
Total Piles = 65 Nos Road side R
Platform level = 21.25 M BM 456 kn.m
Pile Toe Level = 7.75 M S.F 157 Kn
Cut-off level = 20.65 M Anchor 1 191 @ 1.89 m
Concreting level = 21.25 M
Boring Length = 13.500 m
Concreting Length = 13.500 m
Cut-off Length = 12.900 m
Pile Diameter = 0.750 m
Concrete Wastage = 10%
Concrete Cover = 0.075 m
Reinforcement Details
Main Bars Length Over lap Helicals
Type T1 12 T 25 mm , 12 m 0.00 m Type H1 T 10 @ 150 mm 12.90 m
Type T2 12 T 25 mm , 3m 0.00 m Type H2 T 10 @ 150 mm 0.00 m
Type T3 12 T 25 mm , 0m 0.00 m Type H3 T 10 @ 150 mm 0.00 m

Description Qty Total Qty Rate Amount


Concrete 6.8 442 450 198,900.00
Steel Reinforcement
Main Bars 0.571392 37.14 3450 128,133.00
0.142848 9.29 3450 32,050.50
Helicals 0.117697 7.65 3450 26,392.50
0 0.00 3450 0.00
Tie Back Anchor 27.00 7000 189,000.00
Spacers 6 Per row Summary
4.00 24 1560 0.75 1,170.00 Cost of matls & others 738,135.55
Tying Wire 585.00 Mobilization 67,000.00
Cube Testing 54 10 540.00 Workmanship 438,750.00
Anchor Testing 3 2000 6,000.00 1,243,885.55
Concrete Panels 88 200 17,600.00
Universal Beams 24 1250 30,000.00
Steel Testing 540.80
Couplers 12 780 0 0.00
Bentonite 0.1268 8.242 0 0.00
Debris Di 8.45 549.25 35 19,223.75 Rate per pile 19,136.70
Independent Insp. 11 700 7,700.00 Rate per lm from col 1,483.47
QA/QC & Safety 11 500 5,500.00 Rate per lm for boring 1,417.53
Electricity 11 0 0.00
Water 24.2 0 0.00
Guide Wall 44.00 750 33,000.00
Capping Beam 44.00 950 41,800.00
Workmans 13.500 877.5 500 438,750.00
Mobilisation 65 0 67,000.00
1,243,885.55
R7 Canal Appartments
on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE
Type-1(Canal side) 60cm dia Contiguous Piles Perimeter 410.6 m
Ex.ground Level 23.25 M DMD
No of Reinforced Piles = 656 Nos Excavation Level 13.31 M DMD
No of Non-Reinforced Piles = 0 Nos Toe level 9.75 M DMD
Total Piles = 656 Nos Road side N
Platform level = 23.25 M BM 301 kn.m
Pile Toe Level = 9.75 M S.F 120 Kn
Cut-off level = 22.65 M Anchor 1 160 @ 1.89 m
Concreting level = 23.25 M
Boring Length = 13.500 m
Concreting Length = 13.500 m
Cut-off Length = 12.900 m
Pile Diameter = 0.600 m
Concrete Wastage = 20%
Concrete Cover = 0.075 m
Reinforcement Details
Main Bars Length Over lap Helicals
Type T1 8 T 25 mm , 12 m 0.00 m Type H1 T 10 @ 150 mm 12.90 m
Type T2 8 T 25 mm , 3m 0.00 m Type H2 T 10 @ 150 mm 0.00 m
Type T3 8 T 25 mm , 0m 0.00 m Type H3 T 10 @ 150 mm 0.00 m

Description Qty Total Qty Rate Amount


Concrete 4.8 3148.8 450 1,416,960.00
Steel Reinforcement
Main Bars 0.380928 249.89 3450 862,120.50
0.095232 62.47 3450 215,521.50
Helicals 0.088273 57.91 3450 199,789.50
0 0.00 3450 0.00
Tie Back Anchor 219.00 7000 1,533,000.00
Spacers 4 Per row Summary
4.00 16 10496 0.75 7,872.00 Cost of matls & others 5,459,094.20
Tying Wire 3,936.00 Mobilization 67,000.00
Cube Testing 378 10 3,780.00 Workmanship 3,542,400.00
Anchor Testing 22 2000 44,000.00 9,068,494.20
Concrete Panels 822 0 0.00
Universal Beams 208 0 0.00
Steel Testing 3,702.70
Couplers 8 5248 60 314,880.00
Bentonite 0.0818 53.661 0 0.00
Debris Di 5.45 3575.2 35 125,132.00 Rate per pile 13,823.92
Independent Insp. 59 700 41,300.00 Rate per lm from col 1,071.62
QA/QC & Safety 59 500 29,500.00 Rate per lm for boring 1,023.99
Electricity 59 0 0.00
Water 157.4 0 0.00
Guide Wall 411.00 750 308,250.00
Capping Beam 411.00 850 349,350.00
Workmans 13.500 8856 400 3,542,400.00
Mobilisation 656 0 67,000.00
9,068,494.20
R7 Canal Appartments
on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE
Type-1(Neighbour side)75cm dia Secant Piles Perimeter 157.0 m
No of Reinforced Piles = 133 Nos Ex.ground Level 0M
No of Non-Reinforced Piles = 133 Nos Excavation Level -13.075 M
Total Piles = 266 Nos Toe level -17.5 M
Platform level = 0 M N
Pile Toe Level = -17.5 M BM 780 kn.m
Cut-off level = -0.6 M S.F 245 Kn
Concreting level = 0 M Anchor 1 91 @ 2.40 m
Boring Length = 17.500 m Anchor 2 304 @ 1.80 m
Concreting Length = 17.500 m
Cut-off Length = 16.900 m
Pile Diameter = 0.750 m
Concrete Wastage = 10%
Concrete Cover = 0.075 m
Reinforcement Details
Main Bars Length Over lap Helicals
Type T1 13 T 40 mm , 12 m 0.00 m Type H1 T 10 @ 150 mm 16.90 m
Type T2 13 T 40 mm , 8m 0.00 m Type H2 T 10 @ 150 mm 0.00 m
Type T3 13 T 40 mm , 0m 0.00 m Type H3 T 10 @ 150 mm 0.00 m

Description Qty Total Qty Rate Amount


Concrete 8.75 2327.5 460 1,070,650.00
Steel Reinforcement
Main Bars 1.6251 216.63 2300 498,249.00
1.026 136.45 2550 347,947.50 8m cutbar 78.92 Kgs
0 0.00 2300 0.00
Helicals 0.1522 20.25 2300 46,575.00 Anchors
0 0.00 2300 0.00 Anchor 1 67.00 7000 469,000.0
Tie Back Anchor 156 0 1,181,000.00 Anchor 2 89.00 8000 712,000.0
Anchor Testing 16.00 2000 32,000.00 1,181,000.0
Spacers 6 Per row Summary
5.00 30 3990 0.75 2,992.50 Cost of matls & others 3,726,213.55
Tying Wire 1,496.25 Mobilization 67,000.00
Cube Testing 468 20 9,360.00 Workmanship 2,094,750.00
Beams for top 2m 81 0 0.00 5,887,963.55
Concrete Panels 314 0 0.00
Steel Testing 5,293.30
Couplers 13 1729 60 103,740.00
Bentonite 0.165 43.89 0 0.00
Debris Disposal 11 2926 35 102,410.00 Rate per pile 44,270.40
Independent Insp. 48 700 33,600.00 Two Rigs Rate per lm from col 2,619.55
QA/QC & Safety 48 500 24,000.00 Rate per lm for boring 2,529.74
Electricity 48 0 0.00
Water 128.8 0 0.00
Guide Wall 157.000 750 117,750.00
Capping Beam 157.000 950 149,150.00
Workmanship 17.500 4655 450 2,094,750.00
Mobilization 67,000.00 Total Shoring Amount 7,269,072.15
5,887,963.55 Rate/LM 38,258.27
R7 Canal Appartments
on Plot No: 682-1400, 1401, Dubai Sports City, Dubai, UAE
Type-2(Road side) 100cm dia Secant Piles Perimeter 33.0 m
No of Reinforced Piles = 21 Nos Ex.ground Level 0 M DMD
No of Non-Reinforced Piles = 21 Nos Excavation Level -14.075 M DMD
Total Piles = 42 Nos Toe level -19 M DMD
Platform level = -2 M R
Pile Toe Level = -19 M BM 1150 kn.m
Cut-off level = -2.6 M S.F 315 Kn
Concreting level = -2 M Anchor 1 91 @ 2.55 m
Boring Length = 17.000 m Anchor 2 372 @ 2.55 m
Concreting Length = 17.000 m
Cut-off Length = 16.400 m
Pile Diameter = 1.000 m
Concrete Wastage = 10%
Concrete Cover = 0.075 m
Reinforcement Details
Main Bars Length Over lap Helicals
Type T1 20 T 40 mm , 12 m 0.00 m Type H1 T 10 @ 150 mm 16.40 m
Type T2 20 T 40 mm , 8m 0.00 m Type H2 T 10 @ 150 mm 0.00 m
Type T3 20 T 40 mm , 0m 0.00 m Type H3 T 10 @ 150 mm 0.00 m

Description Qty Total Qty Rate Amount


Concrete 14.75 619.5 460 284,970.00
Steel Reinforcement
Main Bars 2.5001 53.00 2300 121,900.00
1.5784 33.15 2550 84,532.50 8m cutbar 78.92 Kgs
0 0.00 2300 0.00
Helicals 0.2102 4.41 2300 10,143.00 Anchors
0 0.00 2300 0.00 Anchor 1 14.00 7000 98,000.0
Tie Back Anchor 28 0 210,000.00 Anchor 2 14.00 8000 112,000.0
Anchor Testing 3.00 2000 6,000.00 210,000.0
Spacers 8 Per row Summary
5.00 40 840 0.75 630.00 Cost of matls & others 885,708.60
Tying Wire 315.00 Mobilization 67,000.00
Cube Testing 126 20 2,520.00 Workmanship 428,400.00
Beams for top 2m 19 1250 23,750.00 1,381,108.60
Concrete Panels 66 200 13,200.00
Steel Testing 1,185.60
Couplers 20 420 60 25,200.00
Bentonite 0.2813 11.8125 0 0.00
Debris Disposal 18.75 787.5 35 27,562.50 Rate per pile 65,767.08
Independent Insp. 12 700 8,400.00 Two Rigs Rate per lm from col 4,010.19
QA/QC & Safety 12 500 6,000.00 Rate per lm for boring 3,868.65
Electricity 12 0 0.00
Water 34.7 0 0.00
Guide Wall 33.000 750 24,750.00
Capping Beam 33.000 1050 34,650.00
Workmanship 17.000 714 600 428,400.00
Mobilization 67,000.00
1,381,108.60
Beam/Channel Shoring
Perimeter 100.00 LM spacing 100.00
1m 104.00

Channels 305 x 100 x 46.2


Beams 497 x 191 x 74 kg/m
Spacing 1.8m
Alternate channels and beams 52.00 Nos
Depth of Excavation 8.95 m ( from (+)23.25 to (+)14.31m DMD )
B.M 208 K.m
S.F 95.00 Kn
Anchor 138 Kn
Quantity Rate Amount
D-Channels 52 7000 364,000.00 4,440.00
Beams (road side) 52 5500 286,000.00 1,000.00
Bracing 18 4500 81,000.00
Concrete Panels 100 10 200 200,000.00
Anchors 52 6500 338,000.00
Anchors test 6 2500 15,000.00
Gravel 52 75 3,900.00
Mobilisation Incld BOQ
1,287,900.00
Nad Al Sheba Race Course Development
Dubai, UAE
Type-6 120cm dia
No of Piles = 467 Nos
Platform level = 0.000 M DMD
Pile Toe Level = -33.500 M DMD
Cut-off level = -1.500 M DMD
Concreting level = 0.000 M DMD
Boring Length = 33.500 m Working Load 650 Tons (C)
Concreting Length = 33.500 m Tons (S)
Cut-off Length = 32.000 m Tons (T)
Pile Diameter = 1.200 m Ton-m (M)
Concrete Wastage = 10%
Concrete Cover = 0.075 m
Reinforcement Details
Main Bars Length Over lap Helicals
Type T1 24 T 25 mm , 12 m 2.00 m Type H1 T 12 @ 150 mm 32.00 m
Type T2 24 T 20 mm , 12 m 0.00 m Type H2 T 12 @ 150 mm 0.000 m
Type T3 24 T 20 mm , 12 m 0.00 m Type H3 T 12 @ 150 mm 0.000 m

Description Qty Total Qty Rate Amount


Concrete 41.75 19,497 300 5,849,100.00 C40 grade with durability
Steel Reinforcement
Main Bars 1.143 534.28 2350 1,255,558.00 Uncoated Steel
0.727 339.51 2350 797,848.50
0.727 339.51 2350 797,848.50 Steel Quantity 1550.94

Helicals 0.723 337.64 2350 793,454.00


0 0.00 2350 0.00
0 0.00 2350 0.00
Spacers 12 Per row Summary
11.00 132 61644 0.75 46,233.00 Cost of matls & others 10,937,824.84
Tying Wire 23,116.50 Mobilization 150,000.00
Cube Testing 2340 10 23,400.00 Workmanship 9,386,700.00
Durability Testing 336 600 201,600.00 20,474,524.84
Miscellaneous 336 0 0.00
Steel Testing 15,509.40
Couplers 36 16812 0 0.00
Bentonite 0.79875 373.01625 350 130,555.69
Debris Disposal 53.25 24867.75 35 870,371.25 Rate per pile 43,842.67
Independent Insp. 89.0 0 0.00 Rate per lm from col 1,370.08
QA/QC & Safety 89.0 500 44,500.00 Rate per lm for boring
Sleeve Pipe 1.5 m Rate per lm for concrete 1,115.67
36 m 16812 m 2.5 42,030.00
Electricity 89.0 0 0.00
Water 1094.2 0 0.00
Setting Out & As built 467 100 46,700.00
Workmanship 33.500 15644.5 600 9,386,700.00
Mobilization 150,000.00
20,474,524.84 Total Piling Amount 73,528,960
Nad Al Sheba Race Course Development
Dubai, UAE
120cm dia With Permanent Casing
No of Piles = 501 Nos
Platform level = 0.000 m Length of permanent casing
Pile Toe Level = -33.500 m 23
Cut-off level = -1.500 m
Concreting level = 0.000 m
Boring Length = 33.500 m Working Load Tons (C)
Concreting Length = 33.500 m Tons (S)
Cut-off Length = 32.000 m Tons (T)
Pile Diameter = 1.200 m 0 Ton-m (M)
Concrete Wastage = 10%
Concrete Cover = 0.090 m
Reinforcement Details
Main Bars Length Over lap Helicals
Type T1 24 T 25 mm , 12 m 2.00 m Type H1 T 12 @ 150 mm 32.00 m
Type T2 24 T 25 mm , 12 m 0.00 m Type H2 T 12 @ 150 mm 0.000 m
Type T3 24 T 25 mm , 12 m 0.00 m Type H3 T 12 @ 150 mm 0.000 m
Description Qty Total Qty Rate Amount
Concrete 41.7 20891.7 550 11,490,435.00
Steel Reinforcement C40 grade with durability
Main Bars 1.1428 572.78 2450 1,403,311.00
1.1428 572.53 2450 1,402,698.50 Uncoated Steel
1.1428 572.53 2450 1,402,698.50
Helicals 0.7026 351.99 2450 862,375.50 Steel Quantity 2069.83
0 0.00 2450 0.00
0 0.00 2450 0.00
Spacers 12 Per row Summary
9.00 108 54108 1.25 67,635.00 Cost of matls & others42,834,335.58
Tying Wire 67,635.00 Mobilization 150,000.00
Cube Testing 1881 12 22,572.00 Workmanship 10,070,100.00
Durability Testing 105 700 73,500.00 53,054,435.58
Pumping water
from bore hole 712 75 53,400.00
Steel Testing 20,698.30
Casing 10 mm 0.2984 3,438.46 7200 24,756,912.00
Coating 3.8013 43802.69 0 0
Couplers 24 12024 0 0.00
Bentonite 0.7965 399.0465 350 139,666.28
Debris Disposal 53.1 26603.1 35 931,108.50 Rate per pile 105897.07701
Independent Insp. 89 0 0.00 Rate per lm from col 3309.2836564
QA/QC & Safety 89 500 44,500.00 Rate per lm for boring 3161.1067763
Sleeve Pipe 1.5 m
36 m 18036 m 2.5 45,090.00
Electricity 89 0 0.00
Water 1170.6 0 0.00
Setting Out & As built 501 100 50,100.00
Workmanship 33.500 16783.5 600 10,070,100.00
Mobilization 150,000.00
53,054,435.58

You might also like