Professional Documents
Culture Documents
Pipeline Integrity
Reparation
Possible loss of product
Environmental impact
Public safety….
General corrosion
(internal, external, pitting,…)
Contact damage caused by third
party activities
(excavator tooth, anchor,...)
Geotechnical failures
(landslides, floods, etc.)
Stress Corrosion Cracking (SCC)
Others
(material & equipment failure,
operator error, etc.)
3
Environmental impact
Uncontrolled Degradation
Pipeline burst
Uncontrolled Degradation
Corroded Pipe
Corroded Pipe
Corroded Pipe
The
concrete
coating
Weld Line
6 oclock
Corroded Pipe
Pit Depth =
Pit Depth = 0.0972 in
0.109 in
Pit Depth =
0.0811 in
Corroded Pipe
20 Maret 2007
21 Maret 2007 15
● Pipeline assessment
● Inspection management
● Defect and repair assessment
● Rehabilitation and maintenance
19
• Aim :
Ensure risks are controlled
within acceptable limits Risk
Probability Consequence
Acceptable Limit :
– depends on legislation and corporate policy
– considers health, safety, environment, attitude of society and economic
realities
– Business interuption
Pipeline Integrity Management
Contoh : Pipeline
Risk Result
Control of Risk
– Downgraded operations
Consideration of failure
– Appropriate design - modes, possible
consequences, ease to test /
monitor and inspect
Control of Risk – Inspection RBI
Control requires:
- identification of the
degradation
- sufficient time to
implement remedial
action
- remedial action!
• Reduction of Uncertainty
- Control requires projection of future integrity
- Risk increases with time due to increasing uncertainty whether
degradation or instantaneous failure mode
- Inspection re-calibrates uncertainty levels
Limitations :
• ability of inspection method
to identify failure mode
• cannot prevent catastrophic
time independent failures (eg
rupture due to backhoe / ship
impact etc)
RBI CONCEPT
Testing
Limitations
– Valve testing • does not capture all failure modes
• indirect measures of failure modes
– CP system operation
• mostly testing is not predictive
– Hydrostatic strength
Control of Risk - Planned Repairs
Planned Repairs
Advantages
• usually cost effective for control of degradation modes
Limitations
• only mitigates slow acting inspect-able degradation
• reactive
• usually less cost effective than prevention
Emergency procedures
Limitations
• reactive not preventive
• only limits consequence of failure
• added value often underestimated
Control of Risk –
Downgraded Operations
Production restrictions
Advantages Limitations
• most cost effective solution for • cannot mitigate risks unknown at
controlling known risks design stage
• cannot take advantage of new
technologies
Design
Feedback
Pipeline
Risk Data
Other
Downgraded Emergency Planned Monitoring undetectable
Preservation Inspect & testing
Operation Preparedness Repair degradation
mechanisms
Analysis
Pipeline Inspection
Based Management
Other
Downgraded Emergency Planned Monitoring undetectable
Operation Preparedness
Preservation Inspect & testing degradation
Repair
mechanisms
Analysis
Thank You