You are on page 1of 11

5.

02- F01 HAZARD IDENTIFICATION & RISK ASSESSMENT

PRE- START CHECKLIST

Date: 12-05-2023
Project Name: Sea World Abu Dhabi
Time: 11:00 AM
Description of Task / Activity: SWAD _ Trays Installation
Risk Assessment No: 002 Rev No.

Emp No. Name


Risk Assessor: Karim MAhmoud
Construction Manager: Ibrahim Adel
PORJECT MANGER: Hossam Hamouda
Safety Department:
Engineer: Himanshu Karayat
SUBJECT MATTER EXPERT: Joseph Xavier
1 Manpower Required for Task:
SWAD _ Trays Installation
2 Work Notification Status:
3 Estimated / Planned Start Date: 09-05-2023
4 Duration of Activity: 7 days
5 Night work and Equipment: N/A
6 Equipment and Materials: As per MOS
7 Overhead Services / Underground: N/A
Sequence of Works Activity:
8 Subcontractors to be Used: Non
9 Interface with Public: N/A
10 Adjacent Activities & Interface with YES
other Sub Contractors:
11 Logistics, Loading, Delivery: N/A
12 Specific PPE Required: As per MOS
13 Environmental: N/A
14 Elevated Positions: yes
15 Confined Space Entry: N/A
16 Hoarding / Fencing / Barricading/ N/A
Demarcation:
17 Access / Egress: YES
18 Security Requirements: As per project main contractor requirements
19 Traffic: As per project main contractor requirements
20 Permit to Work Required Details: Mechanical Works PTW
21 Work Near Water: N/A
22 Hazardous Substances: N/A
23 Excavations: N/A
24 Lifting Equipment / Machinery: N/A
25 Special Emergency Arrangements: NA

5.02- F01 HAZARD IDENTIFICATION & RISK ASSESSMENT


Page 1 of 8 Rev. 4 [18-Apr-2019] CRM Controlled Document

Description of Task / Activity: SWAD _ Trays Installation


Risk Assessment No: Rev No.
26 Additional Comments: MSRA to be communicated with all the involved persons by supervision Staff
and MS & RA should be revised if work method, materials/equipment’s are
changed.

Page 2 of 8 Rev. 4 [18-Apr-2019] CRM Controlled Document


Project Name: Sea World Abu Dhabi Project Code:
Description of Task / Activity: SWAD _ Trays Installation
Risk Assessment No. 002 RA Rev No.
Task Site Location: Yas Island, Abu Dhabi, UAE

RISK/LOSS POTENTIAL ASSESSMENT MATRIX


PROBABILITY of recurrence?
SEVERITY of occurrence Severity Almost Certain Very Likely Likely Unlikely Very Unlikely
Rating 1 or more times a Once every 10 Once in a lifetime/ 100
Once per month Once per year
week years years
Catastrophic
Multiple Fatalities / Low
5 High 25 High 20 High 15 Med 10
Environmental release with detrimental effects requiring external emergency services/ 5
>10m AED
Major
Med Low
Single Fatality/Multiple LTI’s/ Major Illness or Injury, disability/ 4 High 20 High 16 High 12
Environmental release with minimal off site impact/ 1-10m AED
8 4
Moderate
Single LTI/ Serious but non-permanent injury or ill health Med Med Low
3 High 15 High 12
Work days lost/ Restricted Workday 9 6 3
On site release requiring environmental emergency plan to be activated/ 100k-1m AED
Minor
Corrective Medical Treatment. Med Med Med Low Low
2
No work restrictions/ 10 8 6 4 2
Local on-site environmental release treated locally/ 10-100k AED
Negligible
First Aid Case/ Minor cuts & bruises or sickness/Preventive OR Diagnostic Medical Low Low Low Low Low
1
Treatment. 5 4 3 2 1
Nuisance release with no adverse impact/ 1-10k AED
Probability Rating 5 4 3 2 1

1 3 3

Page 3 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
Description of Task / Activity: SWAD _ Trays Installation
Risk Assessment No: 002 RA Rev No.
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
• Contractor must be onboard with
project WW requirements.
• Operatives must complete project HSE +WW inductions.
• All should have their medical insurance cards & Emirates
ID with them.
• All should enter to the site with the Mandatory & Job
specific PPEs. Refer their Mandatory PPE & Job specific
PPE in the Method statement.
• DSTI to be conducted by supervisor near to the work spot
Hazard: prior to start any activity.
• Unauthorized entry • Supervisor & workers should visually inspect their work
Site / Work • Not aware of Hazard / area, equipment, plants, materials etc. prior to start their
Preparatory controls. activity.
Works for
• Slip, trip & fall • Hit with • Ensure that all tools have been inspected and color
01 INSTALLATION 2 3 6 Y 1 3 3 CES & GFTS
moving coded/tagged to ensure that the plant department
Cables Trays
machinery inspected them prior to issue
(Handling Area)
Consequence: • Guide the movement of delivery vehicles and control
• Injury from construction work operatives;
• Unauthorized persons not allowed in work area
• Barricade the work area, communicate to the nearby
activities and watch for any moving machineries at the
work spot.
• Ensure safe access/egress into & out of the area
• Ensure effective lighting requirements installed. Min 50
Lux
• All vehicle movement in construction area either with
revolving amber light or under the control of flagman
when reversing.
Lifting Cables Hazard General measures
trays Manual Handling,  Proper material handling
Slip-Trip  PPE’s.
3 3 9
damaged tools and  Supervisors and OHS team to monitor manual handling.
Page 4 of 8 lead cable, untrained operator Rev. 4 [18-Apr-2019]
Training, Tool box talk to all operatives
CRM Controlled Document  Supervisor and HSE Officer ensure The surface is dry, clean and
02 Consequences free of any materials to prevent falls and slips Y 1 3 3 CES & GFTS
personal Additional Measures
injuries , Cuts, bruises  Lift any heavy equipment as much as possible using mechanical
Description of Task / Activity: SWAD _ Trays Installation
Risk Assessment No: 002 RA Rev No.
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
• No tampering or unauthorized modifications on electrical
tools and systems — repairs will be done by competent
electricians only
• Hazards to be communicated to the workforce through
DSTI and acknowledged by the workforce
• All the power tools Operatives to be trained by
manufacturer
• Daily inspection by the operators
• Send the defective power tools to quarantine zone
immediately, defective tools are not allowed to be keep at
site.
• 110 V power tools to be preferred at site using by step
down transformers, in case 220+ V power tools are chosen
30 mA RCD to be fitted on DB. Special dispensation for HV
from Main Contractor must be obtained.
• Use industrial sockets and standard cables to tap the
power
• Site DB’s to be inspected by electrician weekly and record
to be kept on DB
• All the rotating parts to be guarded Grinding /Cutting
Machine: (if required)
• Hot work permits are required for cutting and grinding
activities.
• Work area to be barricaded while the work is in progress
• Fire prevention & protection to be provided
• Fire extinguishers readily available in work locations
Page 5 of 8 Rev. 4 [18-Apr-2019]
CRM Controlled Document
• Competent Fire Watch available during the activity and 30
min on completion of the activity
• All combustible material must be removed or in case
immovable, covered with fire blanket.
• All task related PPE shall be worn by operatives

Description of Task / Activity: SWAD _ Trays Installation


Risk Assessment No: 002 RA Rev No.
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
Grinding /Cutting Machine: (if required)
• Hot work permits are required for cutting and grinding
activities
• Fire prevention & protection to be provided
• Fire extinguishers available
• Competent Fire Watch available during the activity and
30 min on completion of the activity
• All combustible material must be removed or in case
immovable, covered with fire blanket,
• Issue and enforce PPE for the task
03 Work at Height Hazard General Precautions: Y 1 3 3 CES & GFTS
Works for • Fall from height • Obtain PTW before starting work
INSTALLATION • Falling objects. • PPE Gloves, safety Harness, safety shoes etc..
Cables Trays ,DC • Overhead •
Cables destitution obstruction • Tool box talk to be conducted before start the job
(use of • Fall in to sharp 3 3 9 • GFTS (HSE and supervisor) ensure that the activites is carried
Scaffolding) out properly
Consequences • (Sub con) Qualified and trained workers to work at height
Property damage, Additional Measures Scaff..
Major Injuries, Personal Injury, • Scaffolding is inspected during construction and once complete
Electrocution by an individual with a scaffolding license
• Maximum weight of scaffolding is agreed upon prior to set-up
of scaffold
Page 6 of 8 Rev. 4 [18-Apr-2019]
CRM Controlled Document
• Scaffolding to be secured to prevent unauthorized access
• Scaffolding is inspected for defects or damage prior to use
• Scaffolding is inspected after repairs have been made
• Scaffolding is inspected every thirty days
• Scaffolding to be erected and dismantled by a contractor with a
scaffolding licence
• Agree weight/strength specification of scaffolding with scaffolding
contractors before engaging them to erect scaffolding on site
• Maintain awareness of total weight on scaffold, Including
employees
• Under no circumstances are employees to alter scaffolding erected
by contractors
• No employees to work at height in adverse weather conditions
• Weather protection to be taken into account when selecting
• Employees to use the correct manual handling techniques at all
times
• Scaffold construction area to be isolated and cleared of all persons
• Trucks are to be escorted to the area where the scaffolding is to
be constructed
• Truck driver made aware, prior to driving into construction area,
where materials are to be placed and where the scaffold is to be
erected
• An emergency rescue plan has been established
• Close supervision of the work and maintain good
housekeeping
o Provide safe access & egress and ensure free
form overhead obstruction.
o Full body harness required on working platform.
Where primary fall protection not possible,
secondary fall protection will be applicable as
required by ensuring work at height permit, fall
arrest, fall restrain etc.
o Life lines to be erected where necessary to
maintain 100% tie off.

Page 7 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
• Daily DSTI briefing must be conducted to the workforce
prior to start work.
Use of Hand tools • Ensure competent workforce is assigned for the task.
for • Job specific training should be conducted to the
04 Hazard workforce regarding safe usage of Hand tools. CES & GFTS
INSTALLATION 2 3 6 Y 1 3 3
Tool fall from height, • All the tools must be tethered on rigid place while
Cables Trays
Substandard tools, Purpose working on the roof.
made tools
• Use right tools for the right job.
• Inspect all hand tools are safe for use prior to start work.

Description of Task / Activity: SWAD _ Trays Installation


Risk Assessment No: 002 RA Rev No.
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
• Concerned work in charge should inspect all tools prior to
2 3 6 start the work. Y 1 3 3
Consequences
Serious injury to personnel Cuts, • Tools should be used for its proposed purpose only
bruises • Ensure appropriate PPE’s are provided (Goggles, Hand
Gloves, Ear Plugs) etc.
• Ensure protruded sharp edges are secured properly to
avoid injury
• Do not use homemade tools
• All the hand tools should be maintained in way that neat
and clean always.
• Homemade alterations or modifications of tools are not
permitted.
• Work should be performed in presence of concerned
work in charge.
• Close supervision at all times.
• Maintain proper cable management on workplace.
• Maintain proper storage for all power operated
equipment’s.
Page 8 of 8 Rev. 4 [18-Apr-2019]
CRM Controlled Document
• Only authorized personnel allowed in the work area
Hazard • Signage to identify and demarcate the work area must be
Adjacent work in Unauthorized personnel in area display
CES & GFTS /
05 other project 3 2 6 • Coordinate activities with adjacent work teams to prevent Y 1 2 2
ALEC
areas Consequences • Clashes in the work place
Personal injuries • Highlight adjacent teams and hazards to the work team
during DSTI
General Measures
• Stop working in bad weather conditions
• Provide care facilities (drinking water and rest areas)
during high temperatures
Measures above the line
Hazard
• Before the work carried out weather monitoring should
• Height Heat
be carried out.
• Rainy
• Set the maximum safe wind speed for operation
• Windy
• Stop the work if the wind speed is above 9.8m/s .If any
Environment • Foggy
other risk is identified during lifting operation work should
condition • Dust Storme
06 2 3 6 be stopped even under lesser wind speed. y 1 3 3
Consequences
• Stopping work during the high temperature and
(Weather/climate) • (people& property)
obligatory during the summer at noon (UAE OSHAD)
• Serious injury to personnel
• Lone working strictly prohibited at site.
Cuts, bruises
• Arrange for rest area that is significantly cooler
• Heat stress and stork,
(Ventilated) than the work area
dizziness, Serious injuries
• Restricted working hours in accordance with ministry of
labor requirements.
• All work is to be suspended during sandstorm or where
visibility is <5m during heavy downpour and/or strong wind
condition.
• Present a briefing talk emphasizing heat stress
Hazard management both on and off the job
Working in
Exposure to high temperatures
External • Initiate buddy system to early recognition of heat stress
07 Consequences 3 3 9 Y 1 3 3 CES & GFTS
areas/direct symptoms of co-workers and no lone working.
Heat stress and stork, dizziness,
sunlight. • Arrange for rest area that is significantly cooler (Ventilated)
Serious injuries.
than the work area

Page 9 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
Description of Task / Activity: SWAD _ Trays Installation
Risk Assessment No: 003 RA Rev No.

Legal Additional control


SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
• Restricted working hours in accordance with ministry of
labor requirements.
• All work is to be suspended during sandstorm or where
visibility is <5m during heavy downpour and/or strong wind
condition.
• The lifting activities to be suspended when the wind speed
is over 38km/h
• Cold drinking water to all.
• All the operatives must hold personal water bottle (project
approved) at work areas.
• Enough number of coveralls to periodically wash and use
• Cover body as much as possible from UV rays, dust etc.
• Lone working strictly prohibited at site.

Page 10 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document

You might also like