You are on page 1of 8

5.

02- F01 HAZARD IDENTIFICATION & RISK


ASSESSMENT EXTENSION CUBICEES

PRE- START CHECKLIST


Date: 12-05-2023
Project Name: Sea World Abu Dhabi
Time: 8:00 AM

Description of Task / Activity: EXTENSION CUBICEES INSTULATION


Risk Assessment No: Rev No.
005 Emp No. Name
Risk Assessor: Karim MAhmoud
Construction Manager: Maruthiraj Jagadeesan
PORJECT MANGER: Hossam Hamouda
Safety Department: 516731 Johannes Olivier
Engineer: Himanshu Karayat
SUBJECT MATTER EXPERT: Joseph Xavier
1 Manpower Required for Task: EXTENSION CUBICEES INSTULATION

2 Work Notification Status:


3 Estimated / Planned Start Date: 15-05-2023
4 Duration of Activity: 7 days
5 Night work and Equipment: N/A
6 Equipment and Materials: As per MOS
7 Overhead Services / Underground: N/A
Sequence of Works Activity:
8 Subcontractors to be Used: YES
9 Interface with Public: N/A
10 Adjacent Activities & Interface with YES
other Sub Contractors:
11 Logistics, Loading, Delivery: YES
12 Specific PPE Required: As per MOS
13 Environmental: N/A
14 Elevated Positions: N/A
15 Confined Space Entry: N/A
16 Hoarding / Fencing / Barricading/ N/A
Demarcation:
17 Access / Egress: YES
18 Security Requirements: As per project main contractor requirements
19 Traffic: As per project main contractor requirements
20 Permit to Work Required Details: Mechanical Works PTW
21 Work Near Water: N/A
22 Hazardous Substances: N/A
23 Excavations: N/A
24 Lifting Equipment / Machinery: N/A

Page 1 of 9 Rev. 4 [18-Apr-2019] CRM Controlled Document


5.02- F01 HAZARD IDENTIFICATION & RISK
ASSESSMENT EXTENSION CUBICEES
Description of Task / Activity: EXTENSION CUBICEES INSTULATION
Risk Assessment No: Rev No.
25 Special Emergency Arrangements: NA

26 Additional Comments: MSRA to be communicated with all the involved persons by supervision
EXTENSION CUBICEES INSTULATION Staff
and MS & RA should be revised if work method, materials/equipment’s are
changed.

Page 2 of 9 Rev. 4 [18-Apr-2019] CRM Controlled Document


Project Name: Sea World Abu Dhabi Project Code:
Description of Task / Activity: EXTENSION CUBICEES INSTULATION
Risk Assessment No. 005 RA Rev No.
Task Site Location: Yas Island, Abu Dhabi, UAE

RISK/LOSS POTENTIAL ASSESSMENT MATRIX


PROBABILITY of recurrence?
Almost Certain Very Likely Likely Unlikely Very Unlikely
SEVERITY of occurrence Severity Once in a
1 or more times a Once every 10
Rating week
Once per month Once per year
years
lifetime/ 100
years
Catastrophic
Multiple Fatalities / High High High Med Low
5
Environmental release with detrimental effects requiring external emergency services/ 25 20 15 10 5
>10m AED
Major
High High High Med Low
Single Fatality/Multiple LTI’s/ Major Illness or Injury, disability/ 4
Environmental release with minimal off site impact/ 1-10m AED
20 16 12 8 4
Moderate
Single LTI/ Serious but non-permanent injury or ill health High High Med Med Low
3
Work days lost/ Restricted Workday 15 12 9 6 3
On site release requiring environmental emergency plan to be activated/ 100k-1m AED
Minor
Corrective Medical Treatment. Med Med Med Low Low
2
No work restrictions/ 10 8 6 4 2
Local on-site environmental release treated locally/ 10-100k AED
Negligible
First Aid Case/ Minor cuts & bruises or sickness/Preventive OR Diagnostic Medical Low Low Low Low Low
1
Treatment. 5 4 3 2 1
Nuisance release with no adverse impact/ 1-10k AED
Probability Rating 5 4 3 2 1

Page 4 of Rev. 4 [18-Apr- CRM Controlled


Description of Task / Activity: EXTENSION CUBICEES INSTULATION
Risk Assessment No: 005 RA Rev No.
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsi
No. Consequence Details Rank Rank
Y/N ble Person

 Contractor must be onboard with project WW


requirements.
 Operatives must complete project HSE +WW inductions.
 All should have their medical insurance cards &
Emirates ID with them.
 All should enter to the site with the Mandatory & Job
specific PPEs. Refer their Mandatory PPE & Job specific
PPE in the Method statement.
 DSTI to be conducted by supervisor near to the work
Hazard:
spot prior to start any activity.
 Unauthorized entry
 Supervisor & workers should visually inspect their work
Site / Work  Not aware of Hazard /
area, equipment, plants, materials etc. prior to start
Preparatory controls.
their activity.
Works for • Slip, trip & fall
 Ensure that all tools have been inspected and color
01 EXTENSION • Hit with moving 2 3 6 Y 1 3 3 CES & GFTS
coded/tagged to ensure that the plant department
CUBICEES machinery
inspected them prior to issue
INSTULATION Consequence:
 Guide the movement of delivery vehicles and control
 Injury from construction
operatives;
work
 Unauthorized persons not allowed in work area
 Barricade the work area, communicate to the nearby
activities and watch for any moving machineries at the
work spot.
 Ensure safe access/egress into & out of the area
 Ensure effective lighting requirements installed. Min 50
Lux
 All vehicle movement in construction area either with
revolving amber light or under the control of flagman
when reversing.
Hazard  General measures
Transportation
Potential for traffic accident,  • • Ensure all drivers have valid driving license and fit
02 of material on 3 3 9 Y 1 3 3 CES & GFTS
Overturning Insecure material, body condition
site
Consequences

Page 5 of Rev. 4 [18-Apr- CRM Controlled


Serious personal injuries,  • Establish traffic rules including care, speed limits and
property damage adhering all traffic safety rules.
 • Provide information on defensively driving
 • Prohibit overloading and unsecured materials
 • All vehicles to be checked and be roadworthy before
entering s
 • Driver to take regular breaks to prevent fatigue and
use journey planning
 • Prohibition of driving under the influence of drugs
or alcohol
 • Monitor vehicles and driving and take disciplinary
action as required

 All Workers to work in compliance with the Risk


Hazard Assessment / Method Statement and apply ‘best
• Slip, trip & fall
practice’ handling techniques.
•Hit
Manual Handling  Using the Fork Lift as much as possible and reducing
Consequences the daily effort of the workers
Materials of
Can cause injury  Use team lifting by competent fit personnel
03 EXTENSION 2 3 6 Y 1 3 3 CES & GFTS
•musculoskeletal disorders,  Supervisors and OHS team to monitor manual
CUBICEES
•Hand injuries, handling.
INSTULATION
•cut & bruises
 Don't lift or handle more than can be easily managed
•Sharp edges
 Move smoothly.
•Property damage
 Don't flex the back any further while pulling ,lifting

General measures
 Electrical supply system will be checked by competent
Hazard
electrician, follow project color coding system.
Electricity, damaged tools and
Use of Power  No tampering or unauthorized modifications on
lead cable, untrained operator
tools during the electrical tools and systems — repairs will be done by
setting up an competent electricians only
Consequences
04 EXTENSION  Hazards to be communicated to the workforce through Y 1 3 3 CES & GFTS
Electrical shock, electrocution,
CUBICEES DSTI and acknowledged by the workforce
burns, fire hazards personal
INSTULATION  All the power tools Operatives to be trained by
injuries
manufacturer
 Daily inspection by the operators

Page 6 of Rev. 4 [18-Apr- CRM Controlled


3 3 9  Send the defective power tools to quarantine zone
immediately, defective tools are not allowed to be keep
at site.
 110 V power tools to be preferred at site using by step
down transformers, in case 220+ V power tools are
chosen 30 mA RCD to be fitted on DB. Special
dispensation for HV from Main Contractor must be
obtained.
 Use industrial sockets and standard cables to tap the
power


Hazard 
PTW to be obtained, prior to
commencing the task
Exposure to Electricity ‐
 Only equipment that complies with
Use of damaged and/or
 the equivalent of the UAE Standards
faulty electrical equipment
 AND OSHAD FOR HSE
(Tools, Leads,
 Energy Shutdown Permit ‐ an Energy
Temporary
Failure to install/use earth  Shutdown Permit to work on electrical
leakage protection  equipment, issued by an Authorized
devices Failure to  Person before any activities
visually inspect tools /  PPE personal protective equipment
equipment prior to use  Supervising and alerting workers to wear
Energy 3 4 12 Y 1 4 4
Failure to conduct routine  gloves and safety shoes
Shutdown FOR  Identify procedure and hazards. ...
Consequences
05 EXTENSION  Shut down. ...
Electrical shock, electrocution,
CUBICEES
burns, fire hazards personal  Isolate machine from energy source. ...
INSTULATION
injuries Fatality & Property  Apply lockout tagout devices. ...
damage,  Check stored energy. ...
 Verify isolation. ...
 Ensure all power tools are in good condition
 and appropriately maintained
 Work on low voltage electrical installation
 must only be done by a qualified electrician.
 All electrical leads will be secured off the
 ground by insulated hooks and/or lead
 stands to protect against damage
 The specialized electrician performs the

Page 7 of Rev. 4 [18-Apr- CRM Controlled


 maintenance and verification of the
 equipment
 Ensure the electrical cable is not damaged
 and has not been repaired with insulating
 tape or unsuitable connectors.
 All the power tools must be 110 volt and safe
 to use
 RAMS to be briefed to the operatives before
 start the activity and maintain the record.
 Fire extinguisher in place
 Operatives should alert while using sharp
 edge tools to avoid entanglement with
 clothing.
 ERP Plan to include site specific response
 protocol for electrocution
 Daily DSTI briefing must be conducted to the workforce
prior to start work.
 Ensure competent workforce is assigned for the task.
 Job specific training should be conducted to the
workforce regarding safe usage of Hand tools.
Hazard  All the tools must be tethered on rigid place while
Tool fall from height, working leading edges, scaffold and ladders.
Substandard tools, Purpose  Use right tools for the right job.
Use of Hand made tools  Inspect all hand tools are safe for use prior to start work.
tools for  Concerned work in charge should inspect all tools prior
Consequences
06 EXTENSION to start the work. CES & GFTS
Serious injury to personnel Cuts, 2 3 6 Y 1 3 3
CUBICEES  Tools should be used for its proposed purpose only
bruises
INSTULATION  Ensure appropriate PPE’s are provided (Goggles, Hand
Gloves, Ear Plugs) etc.
 Ensure protruded sharp edges are secured properly to
avoid injury
 Do not use homemade tools
 All the hand tools should be maintained in way that
neat and clean always.
 Homemade alterations or modifications of tools are not
permitted.

Page 8 of Rev. 4 [18-Apr- CRM Controlled


 Work should be performed in presence of concerned
work in charge.
 Close supervision at all times.
 Maintain proper cable management on workplace.
 Maintain proper storage for all power operated
equipment’s.
 Only authorized personnel allowed in the work area
Hazard  Signage to identify and demarcate the work area must be
Adjacent work in Unauthorized personnel in area display
CES & GFTS /
07 other project 3 2 6  Coordinate activities with adjacent work teams to prevent Y 1 2 2
ALEC
areas Consequences  Clashes in the work place
Personal injuries  Highlight adjacent teams and hazards to the work
team during DSTI

Page 9 of Rev. 4 [18-Apr- CRM Controlled

You might also like