You are on page 1of 12

5.

02- F01 HAZARD IDENTIFICATION & RISK ASSESSMENT

PRE- START CHECKLIST

Date: 08-05-2023
Project Name: Sea World Abu Dhabi
Time: 10:00 AM
Description of Task / Activity: AL Dahra _Cables Pulling
Risk Assessment No: Rev No.

002 Emp No. Name


Risk Assessor: Ibrahim Esmat

Construction Manager: Ibrahim Adel


PORJECT MANGER: Hossam Hamouda
Safety Department:
Engineer: Himanshu Karayat
SUBJECT MATTER EXPERT: Joseph Xavier
1 Manpower Required for Task:
Al Dahra _Cables Pulling
2 Work Notification Status:
3 Estimated / Planned Start Date: 02-09-2023
4 Duration of Activity: 1 days
5 Night work and Equipment: N/A
6 Equipment and Materials: As per MOS
7 Overhead Services / Underground: N/A
Sequence of Works Activity:
8 Subcontractors to be Used: Non
9 Interface with Public: N/A
10 Adjacent Activities & Interface with YES
other Sub Contractors:
11 Logistics, Loading, Delivery: N/A
12 Specific PPE Required: As per MOS
13 Environmental: N/A
14 Elevated Positions: yes
15 Confined Space Entry: N/A
16 Hoarding / Fencing / Barricading/ N/A
Demarcation:
17 Access / Egress: YES
18 Security Requirements: As per project main contractor requirements
19 Traffic: As per project main contractor requirements
20 Permit to Work Required Details: Mechanical Works PTW
21 Work Near Water: N/A
22 Hazardous Substances: N/A
23 Excavations: N/A
24 Lifting Equipment / Machinery: N/A
25 Special Emergency Arrangements: NA

5.02- F01 HAZARD IDENTIFICATION & RISK ASSESSMENT


Page 1 of 8 Rev. 4 [18-Apr-2019] CRM Controlled Document

Description of Task / Activity: SWAD _Cables Pulling


Risk Assessment No: Rev No.
26 Additional Comments: MSRA to be communicated with all the involved persons by supervision Staff
and MS & RA should be revised if work method, materials/equipment’s are
changed.

Page 2 of 8 Rev. 4 [18-Apr-2019] CRM Controlled Document


Project Name: Al Dahra Industerial – Khalifa/kizad_Abu Dhabi Project Code:
Description of Task / Activity: Al Dahra _Cables Pulling
Risk Assessment No. 005 RA Rev No.
Task Site Location: Yas Island, Abu Dhabi, UAE

RISK/LOSS POTENTIAL ASSESSMENT MATRIX


PROBABILITY of recurrence?
SEVERITY of occurrence Severity Almost Certain Very Likely Likely Unlikely Very Unlikely
Rating 1 or more times a Once every 10 Once in a lifetime/ 100
Once per month Once per year
week years years
Catastrophic
Multiple Fatalities / Low
5 High 25 High 20 High 15 Med 10
Environmental release with detrimental effects requiring external emergency services/ 5
>10m AED
Major
Med Low
Single Fatality/Multiple LTI’s/ Major Illness or Injury, disability/ 4 High 20 High 16 High 12
Environmental release with minimal off site impact/ 1-10m AED
8 4
Moderate
Single LTI/ Serious but non-permanent injury or ill health Med Med Low
3 High 15 High 12
Work days lost/ Restricted Workday 9 6 3
On site release requiring environmental emergency plan to be activated/ 100k-1m AED
Minor
Corrective Medical Treatment. Med Med Med Low Low
2
No work restrictions/ 10 8 6 4 2
Local on-site environmental release treated locally/ 10-100k AED
Negligible
First Aid Case/ Minor cuts & bruises or sickness/Preventive OR Diagnostic Medical Low Low Low Low Low
1
Treatment. 5 4 3 2 1
Nuisance release with no adverse impact/ 1-10k AED
Probability Rating 5 4 3 2 1

Page 3 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
1 3 3

Page 4 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
Description of Task / Activity: Al Dahra _Cables Pulling
Risk Assessment No: 005 RA Rev No. 00
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
• Contractor must be onboard with
project WW requirements.
• Operatives must complete project HSE +WW inductions.
• All should have their medical insurance cards & Emirates
ID with them.
• All should enter to the site with the Mandatory & Job
specific PPEs. Refer their Mandatory PPE & Job specific
PPE in the Method statement.
• DSTI to be conducted by supervisor near to the work spot
Hazard: prior to start any activity.
• Unauthorized entry • Supervisor & workers should visually inspect their work
Site / Work • Not aware of Hazard / area, equipment, plants, materials etc. prior to start their
Preparatory controls. activity.
Works for
• Slip, trip & fall • Hit with • Ensure that all tools have been inspected and color
01 Mobilization 2 3 6 Y 1 3 3 CES & GFTS
moving coded/tagged to ensure that the plant department
Material (Trays)
machinery inspected them prior to issue
on Car park
Consequence: • Guide the movement of delivery vehicles and control
• Injury from construction work operatives;
• Unauthorized persons not allowed in work area
• Barricade the work area, communicate to the nearby
activities and watch for any moving machineries at the
work spot.
• Ensure safe access/egress into & out of the area
• Ensure effective lighting requirements installed. Min 50
Lux
• All vehicle movement in construction area either with
revolving amber light or under the control of flagman
when reversing.

Page 5 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
Description of Task / Activity: SWAD _Cables Pulling
Risk Assessment No: 002 RA Rev No.
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Controasures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person

Page 6 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
• Establish traffic rules including care, speed limits and
adhering all traffic safety rules.
• Provide information on defensively driving
• Prohibit overloading and unsecured materials
• All vehicles to be checked and be roadworthy before
entering s
• Driver to take regular breaks to prevent fatigue and use
journey planning
• Prohibition of driving under the influence of drugs or
alcohol
• Monitor vehicles and driving and take disciplinary action as
required

Description of Task / Activity: Al Dahra_Cables Pulling


Page 7 of 8 Rev. 4 [18-Apr-2019]
CRM Controlled Document
Risk Assessment No: 005 RA Rev No. 00
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
Manual Handling • Reducing the individual capacity during the process of
metarules of AC Cables drawing and tightening materials
Hazard • capability
Slip, trip & fall • Hit with moving • the nature of the load
• environmental conditions
Consequences • training
Can cause injury • work organization
• ppe
• musculoskeletal disorders,
3 3 9 • Y 1 3 3
• Hand injuries, • All Workers to work in compliance with the Risk
Assessment / Method Statement and apply ‘best
• cut & bruises
practice’ handling techniques.
• Sharp edges • Using the Fourl Lift as much as possible and reducing
• Property damage the daily effort of the workers
• Use team lifting by competent fit personnel
• Supervisors and OHS team to monitor manual
handling.
• Don't lift or handle more than can be easily
managed
• Move smoothly.
• Don't flex the back any further while
pulling ,lifting

Page 8 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
• Daily DSTI briefing must be conducted to the workforce
prior to start work.
• Ensure competent workforce is assigned for the task.
• Job specific training should be conducted to the
04 Use of Hand tools Hazard 3 3 9 workforce regarding safe usage of Hand tools. Y 1 3 3 CES & GFTS
Tool fall from height, • All the tools must be tethered on rigid place while
Substandard tools, Purpose working on the roof.
made tools
• Use right tools for the right job.
• Inspect all hand tools are safe for use prior to start work.

Description of Task / Activity: SWAD _Cables Pulling


Risk Assessment No: 00 RA Rev No.
Legal Additional control
SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person
• Concerned work in charge should inspect all tools prior to
start the work.
Consequences
Serious injury to personnel Cuts, • Tools should be used for its proposed purpose only
bruises • Ensure appropriate PPE’s are provided (Goggles, Hand
Gloves, Ear Plugs) etc.
• Ensure protruded sharp edges are secured properly to
avoid injury
• Do not use homemade tools
• All the hand tools should be maintained in way that neat
and clean always.
• Homemade alterations or modifications of tools are not
permitted.
• Work should be performed in presence of concerned
work in charge.
• Close supervision at all times.
• Maintain proper cable management on workplace.
• Maintain proper storage for all power operated
equipment’s.

Page 9 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
• Only authorized personnel allowed in the work area
Hazard • Signage to identify and demarcate the work area must be
Adjacent work in Unauthorized personnel in area display
CES & GFTS /
05 other project 3 2 6 • Coordinate activities with adjacent work teams to prevent Y 1 2 2
ALEC
areas Consequences • Clashes in the work place
Personal injuries • Highlight adjacent teams and hazards to the work team
during DSTI
• Present a briefing talk emphasizing heat stress
Hazard management both on and off the job
Working in
Exposure to high temperatures
External • Initiate buddy system to early recognition of heat stress
07 Consequences 3 3 9 Y 1 3 3 CES & GFTS
areas/direct symptoms of co-workers and no lone working.
Heat stress and stork, dizziness,
sunlight. • Arrange for rest area that is significantly cooler (Ventilated)
Serious injuries.
than the work area
Description of Task / Activity: Al Dahra _Cables Pulling
Risk Assessment No: 005 RA Rev No. 00

Legal Additional control


SI Hazard Details Risk Risk
Task Step P S Current Control Measures Req. P S measures/Responsibl
No. Consequence Details Rank Rank
Y/N e Person

Page 10 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document
• Restricted working hours in accordance with ministry of
labor requirements.
• All work is to be suspended during sandstorm or where
visibility is <5m during heavy downpour and/or strong wind
condition.
• The lifting activities to be suspended when the wind speed
is over 38km/h
• Cold drinking water to all.
• All the operatives must hold personal water bottle (project
approved) at work areas.
• Enough number of coveralls to periodically wash and use
• Cover body as much as possible from UV rays, dust etc.
• Lone working strictly prohibited at site.

Page 11 of 8 Rev. 4 [18-Apr-2019]


CRM Controlled Document

You might also like