C. Kuantitas Agregat A
Luas (m2)
No ROW/Cluster Tebal Rigid (m) Vol (m3)
Permukaan
1 Evodia Blok C (ROW 7) 211.134 0.15 31.6701
2 Evodia Blok D (ROW 7) 43.7514 0.15 6.56271
3 Evodia blok D (ROW 3.5) 8.3332 0.15 1.24998
4 Basella Blok A (ROW 7.5) 39.168 0.15 5.8752
5 Basella Blok A (ROW 7) 26.9346 0.15 4.04019
6 Basella Blok C (ROW 7) 93.1854 0.15 13.97781
7 Basella Blok C (ROW 3) 5.75 0.15 0.8625
8 Basella Blok D (ROW 3) 6.325 0.15 0.94875
9 Basella Blok D,E&BLV (ROW 7) 431.277 0.15 64.69155
10 Basella Blok E (ROW 3) 6.0835 0.15 0.912525
11 Boulevard 8 (ROW 3) 24.15 0.15 3.6225
12 Boulevard 8 (ROW 7) 29.6604 0.15 4.44906
13 Alium Blok 9 (ROW 7) 99.9306 0.15 14.98959
TOTAL Luas 1025.6831 TOTAL Vol 153.852465
D. Galian
Luas (m2)
No ROW/Cluster Vol (m3) Panjang
Permukaan
1 Evodia Blok C (ROW 7) 211.134 80.99 45.7
2 Evodia Blok D (ROW 7) 43.7514 17.39 9.47
3 Evodia blok D (ROW 3.5) 8.3332 3.93 5.02
4 Basella Blok A (ROW 7.5) 39.168 15.64 7.65
5 Basella Blok A (ROW 7) 26.9346 11.00 5.83
6 Basella Blok C (ROW 7) 93.1854 36.17 20.17
7 Basella Blok C (ROW 3) 5.75 2.95 5
8 Basella Blok D (ROW 3) 6.325 3.16 5.5
9 Basella Blok D,E&BLV (ROW 7) 431.277 164.65 93.35
10 Basella Blok E (ROW 3) 6.0835 3.07 5.29
11 Boulevard 8 (ROW 3) 24.15 9.94 21
12 Boulevard 8 (ROW 7) 29.6604 12.03 6.42
13 Alium Blok 9 (ROW 7) 99.9306 38.73 21.63
TOTAL Luas 1025.6831 399.639578
F. Bekisting
Luas (m2)
No ROW/Cluster Panjang Lebar
Permukaan
1 Evodia Blok C (ROW 7) 91.4 45.7 4.62
2 Evodia Blok D (ROW 7) 18.94 9.47 4.62
3 Evodia blok D (ROW 3.5) 10.04 5.02 1.66
4 Basella Blok A (ROW 7.5) 15.3 7.65 5.12
5 Basella Blok A (ROW 7) 11.66 5.83 4.62
6 Basella Blok C (ROW 7) 40.34 20.17 4.62
7 Basella Blok C (ROW 3) 10 5 1.15
8 Basella Blok D (ROW 3) 11 5.5 1.15
9 Basella Blok D,E&BLV (ROW 7) 186.7 93.35 4.62
10 Basella Blok E (ROW 3) 10.58 5.29 1.15
11 Boulevard 8 (ROW 3) 42 21 1.15
12 Boulevard 8 (ROW 7) 12.84 6.42 4.62
13 Alium Blok 9 (ROW 7) 43.26 21.63 4.62
TOTAL Luas 504.06
G. Plastik Cor
Luas (m2)
No ROW/Cluster Panjang Lebar
Permukaan
1 Evodia Blok C (ROW 7) 211.134 45.7 4.62
2 Evodia Blok D (ROW 7) 43.7514 9.47 4.62
3 Evodia blok D (ROW 3.5) 8.3332 5.02 1.66
4 Basella Blok A (ROW 7.5) 39.168 7.65 5.12
5 Basella Blok A (ROW 7) 26.9346 5.83 4.62
6 Basella Blok C (ROW 7) 93.1854 20.17 4.62
7 Basella Blok C (ROW 3) 5.75 5 1.15
8 Basella Blok D (ROW 3) 6.325 5.5 1.15
9 Basella Blok D,E&BLV (ROW 7) 431.277 93.35 4.62
10 Basella Blok E (ROW 3) 6.0835 5.29 1.15
11 Boulevard 8 (ROW 3) 24.15 21 1.15
12 Boulevard 8 (ROW 7) 29.6604 6.42 4.62
13 Alium Blok 9 (ROW 7) 99.9306 21.63 4.62
TOTAL Luas 1025.6831
INFRA SALURAN
A. Kuantitas Saluran U-40/60
Panjang Lebar No ROW/Cluster Panjang Dimensi
Panjang Lebar
45.7 4.62
9.47 4.62
5.02 1.66
7.65 5.12
5.83 4.62
20.17 4.62
5 1.15
5.5 1.15
93.35 4.62
5.29 1.15
21 1.15
6.42 4.62
21.63 4.62
Lebar
4.62
4.62
1.66
5.12
4.62
4.62
1.15
1.15
4.62
1.15
1.15
4.62
4.62
INFRA BUIS BETON INFRA TURAP
A. Kuantitas Buis Beton A. Turap
Vol (m3) No ROW/Cluster Panjang (m) No
B. Saluran Pipa Tu
No
1
INFRA TURAP INFRA KANSTIN
A. Turap A. Kuantitas Kanstin
Jenis Panjang Dimensi Vol (m3) No
SALURAN
VOLUME SALURAN
UK. 400x400mm
NO PANJANG DIMENSI VOLUME galian Sat. uraian
1 27.77 0,4 x 0,4 4.44 m3 ev-c
2 95.21 0,4 x 0,4 15.23 m3 ev-d
3 33.37 0,4 x 0,4 5.34 m3 ba-c
4 164.19 0,4 x 0,4 26.27 m3 ba-b
5 13.44 0,4 x 0,4 2.15 m3 blv-52
6 57.79 0,4 x 0,4 9.25 m3 ba-d
8 42.10 0,4 x 0,4 6.74 m3 al-e
9 4.34 0,4 x 0,5 0.70 m3 ev-d16
438.22 TOTAL 70.11 m3
UK. 400x600mm
NO PANJANG DIMENSI VOLUME Sat. uraian
1 55.97 0,4 x 0,6 13.43 m3 ba-e
JALAN
NO uraian volume sat.
Evodia Blok C (ROW 7) 80.99 m3
Evodia Blok D (ROW 7) 17.39 m3
1 Galian Evodia blok D (ROW 3.5) 3.93 m3
Basella Blok A (ROW 7.5) 15.64 m3
Basella Blok A (ROW 7) 11.00 m3
Basella Blok C (ROW 7) 36.17 m3
Basella Blok C (ROW 3) 2.95 m3
Basella Blok D (ROW 3) 3.16 m3
Basella Blok D,E&BLV (ROW 7) 164.65 m3
Basella Blok E (ROW 3) 3.07 m3
Boulevard 8 (ROW 3) 9.94 m3
Boulevard 8 (ROW 7) 12.03 m3
Alium Blok 9 (ROW 7) 38.73 m3
Evodia Blok C (ROW 7) 211.13 m2
Evodia Blok D (ROW 7) 43.75 m2
1 perapihan Evodia blok D (ROW 3.5) 8.33 m2
badan jalan Basella Blok A (ROW 7.5) 39.17 m2
Basella Blok A (ROW 7) 26.93 m2
Basella Blok C (ROW 7) 93.19 m2
Basella Blok C (ROW 3) 5.75 m2
Basella Blok D (ROW 3) 6.32 m2
Basella Blok D,E&BLV (ROW 7) 431.28 m2
Basella Blok E (ROW 3) 6.08 m2
Boulevard 8 (ROW 3) 24.15 m2
Boulevard 8 (ROW 7) 29.66 m2
Alium Blok 9 (ROW 7) 99.93 m2
EVODIA C (ROW 7) 43.77 m3
EVODIA D (ROW 7) 64.63 m3
1 Beton BASELA A (ROW 7,5) 14.82 m3
BASELA C (ROW 7) 20.38 m3
BASELA B,D,E(ROW 7) 877.21 m3
ALIUM C (ROW 7) 22.78 m3
EVODIA D16 12.50 m3
BLV 52 19.18 m3
gang way BA-A-C 5.22 m3
gang way BA-c-d 3.99 m3
gang way BA D-E 4.66 m3
gang way BA E 4.42 m3
gang way EV D- BA A 4.37 m3
EVODIA C (ROW 7) 97.27 m2
EVODIA D (ROW 7) 143.63 m2
1 bekisting BASELA A (ROW 7,5) 32.94 m2
BASELA C (ROW 7) 45.28 m2
BASELA B,D,E(ROW 7) 1949.36 m2
ALIUM C (ROW 7) 50.63 m2
EVODIA D16 27.78 m2
BLV 52 42.63 m2
gang way BA-A-C 57.99 m2
gang way BA-c-d 44.29 m2
gang way BA D-E 51.75 m2
gang way BA E 49.11 m2
gang way EV D- BA A 48.54 m2
EVODIA C (ROW 7) 389.09 m2
EVODIA D (ROW 7) 574.51 m2
1 pelastik BASELA A (ROW 7,5) 131.77 m2
BASELA C (ROW 7) 181.11 m2
BASELA B,D,E(ROW 7) 7797.46 m2
ALIUM C (ROW 7) 202.52 m2
EVODIA D16 111.11 m2
BLV 52 170.51 m2
gang way BA-A-C 92.78 m2
gang way BA-c-d 70.86 m2
gang way BA D-E 82.81 m2
gang way BA E 78.57 m2
gang way EV D- BA A 77.66 m2
limestone EVODIA C (ROW 7) 47.47 m3
EVODIA D (ROW 7) 70.09 m3
BASELA A (ROW 7,5) 16.08 m3
BASELA C (ROW 7) 22.10 m3
BASELA B,D,E(ROW 7) 951.29 m3
ALIUM C (ROW 7) 24.71 m3
EVODIA D16 13.56 m3
BLV 52 20.80 m3
KANSTIN
NO KODE URAIAN volume
1 A EV-A2A DAN 3 11.00
B EV-A12 11.02
C EV-B15 24.98
D EV-B ROW7 86.46
E PY-A KE C 51.92
F PY D 1-21 72.26
G EV-C 1-3 83.35
H EV-C DEKAT SUMUR 27.90
Kanstin I EV-D 285.14
K BA-A 171.94
L BA-B,C,D 409.11
M BLV-46-52 95.52
N BLV-40 DAN 42 14.44
O AL-E 48.50
P AL-D 13.87
Q AL-A12 DAN 12A 11.70
1419.12
1025.68
1097.93
sat. PJU
m NO uraian volume sat
m 1 PEKERJAAN PJU 18 bh
m
m
m TURAP
m NO uraian volume sat
m 1 TURAP A 15.12 m3
m TURAP B 50.45 m3
m 2 PASIR PADAT 10CM TURAP A 1.68 m3
m PASIR PADAT 10CM TURAP B 4.81 m3
m 3 GALIAN A 7.56 m3
m GALIAN B 25.23 m3
m
m
m
m
m
BUIS BETON
NO uraian volume sat
1 ev-c 1,2,3 57.85 m
1/2 BUIS 30 CM
EV-D 69.92 m
2 ev-c 1,2,3 3.99 m3
GALIAN
EV-D 4.82 m3
panjang tinggi alas volume
16.8 2 0.45 15.12
48.05 2 0.525 50.4525
16.8 0.10 1.68
48.05 0.10 4.805
491,598,826.10
C PEKERJAAN PJU
ba-a bh 1 1
ba-b bh 1 1
ba-c bh 1 1
ba-d bh 2 2
ba-e bh 3 3
D PEKERJAAN SALURAN
BC 40 X 40
Galian Tanah m3 106.74 106.74
Urugan tanah kembali m3 28.09 28.09
BC 40 X 40 m 255.36 255.36
Lantai kerja Pasir Urug m3 7.15 7.15
Subtotal I
BC 40 X 60
Galian Tanah m3 7.66 7.66
Urugan tanah kembali m3 2.01 2.01
BC 40 X 60 m 13.43 13.43
Lantai kerja Pasir Urug m3 0.38 0.38
Subtotal II
BAK Kontrol 1A
Bekisting m2 4.80 4.80
Upah Beton Readymix K300 m3 0.22 0.22
MoteriaÍ Beton Readymix K300 m3 0.25 0.25
Besi Wiremesh T lapis Mó Kg 17.03 17.03
Frame Besi Siku L 30.30.2 Bh 4.00 4.00
Batu koral m3 0.02 0.02
Ijuk m3 0.01 0.01
pasir Urug m3 0.01 0.01
Pondasi rolag m2 1.25 1.25
pasir Urug m3 0.02 0.02
Subtotal III
Lubang Kontrol
Bekisting m2 0.69 0.69
Upah Beton Readymix K300 m3 0.03 0.03
MoteriaÍ Beton Readymix K300 m3 0.03 0.03
Besi Wiremesh T lapis Mó Kg 2.72 2.72
Frame Besi Siku L 30.30.2 Bh 4.00 4.00
Subtotal IV
2 CLUSTER EVODIA
A PEKERJAAN JALAN BETON
1a evodia c (row 7)
perapihan badan jalan m2 291.82 292.82
plastik cor m2 389.09 389.09
bekisting m2 97.27 97.27
beton m3 43.77 43.77
besi wiremesh
upah beton m3 43.77 43.77
material beton m3 43.77 43.77
besi dowel dia 16mm
limestone m3 47.47 47.47
1b evodia d (row 7)
perapihan badan jalan m2 430.88 431.88
plastik cor m2 574.51 574.51
bekisting m2 143.63 143.63
beton m3 64.63 64.63
besi wiremesh
upah beton m3 64.63 64.63
material beton m3 64.63 64.63
besi dowel dia 16mm
limestone m3 70.09 70.09
1c evodia d16
perapihan badan jalan m2 83.33 84.33
plastik cor m2 111.11 111.11
bekisting m2 27.78 27.78
beton m3 12.50 12.50
besi wiremesh
upah beton m3 12.50 12.50
material beton m3 12.50 12.50
besi dowel dia 16mm
limestone m3 13.56 13.56
1d gang way ev d - ba a
perapihan badan jalan m2 29.12 29.12
plastik cor m2 77.66 77.66
bekisting m2 48.54 48.54
beton m3 4.37 4.37
besi wiremesh
upah beton m3 4.37 4.37
material beton m3 4.37 4.37
besi dowel dia 16mm
B PEKERJAAN KANSTEEN
EV-A2A DAN 3 kode A m 11 11
EV-A12 kode B m 11.022 11.022
EV-B15 kode C m 24.978 24.978
EV-B ROW7 kode D m 86.463 86.463
EV-C 1- 3 kode G m 83.352 83.352
EV-C DEKAT SUMUR kode H m 27.898 27.898
EV-D kode I m 285.14 285.14
C PEKERJAAN PJU
ev-c bh 2 2
ev-d bh 5 5
D PEKERJAAN SALURAN
BC 40 X 40
Galian Tanah m3 53.22 53.22
Urugan tanah kembali m3 3.31 3.31
BC 40 X 40 m 127.32 127.32
Lantai kerja Pasir Urug m3 3.56 3.56
Subtotal Al
BAK Kontrol 1A 8
Bekisting m2 4.80 38.40
Upah Beton Readymix K300 m3 0.22 1.76
MoteriaÍ Beton Readymix K300 m3 0.25 1.98
Besi Wiremesh T lapis Mó Kg 17.03 136.21
Frame Besi Siku L 30.30.2 Bh 4.00 32.00
Batu koral m3 0.02 0.13
Ijuk m3 0.01 0.06
pasir Urug m3 0.01 0.06
Pondasi rolag m2 1.25 10.04
pasir Urug m3 0.02 0.18
Subtotal IV
Lubang Kontrol 8
Bekisting m2 0.69 5.56
Upah Beton Readymix K300 m3 0.03 0.22
MoteriaÍ Beton Readymix K300 m3 0.03 0.22
Besi Wiremesh T lapis Mó Kg 2.72 21.79
Frame Besi Siku L 30.30.2 Bh 4.00 32.00
Subtotal IV
E PEKERJAAN TURAP
turap a m3 15.12 15.12
pasit padat 10 cm m3 1.68 1.68
galian m3 7.56 7.56
turap b m3 50.45 50.45
pasir padat 10 cm m3 4.805 4.805
galian m3 25.22625 25.22625
F PEKERJAAN BUIS BETON
evodia c m 57.85 57.85
galian m3 3.99 3.99
evodia d m 69.92 69.92
galian m3 4.82 4.82
3 CLUSTER ALIUM
A PEKERJAAN JALAN
1a cluster alium c
perapihan badan jalan m2 151.89 151.89
plastik cor m2 202.52 160.94
bekisting m2 50.63 50.63
beton m3 22.78 22.78
besi wiremesh
upah beton m3 22.78 22.78
material beton m3 22.78 22.78
besi dowel dia 16mm
limestone m3 24.71 24.71
B PEKERJAAN KANSTEEN
AL-E kode O m 48.50 48.50
AL-D kode P m 13.87 13.87
AL-A12 DAN 12A kode Q m 11.70 11.70
C PEKERJAAN PJU
al-b bh 2 2
D PEKERJAAN SALURAN
BC 40 X 40
Galian Tanah m3 17.60 17.60
Urugan tanah kembali m3 1.09 1.09
BC 40 X 40 m 42.10 42.10
Lantai kerja Pasir Urug m3 1.18 1.18
Subtotal Al
BAK Kontrol 1A 12
Bekisting m2 4.80 57.60
Upah Beton Readymix K300 m3 0.22 2.64
MoteriaÍ Beton Readymix K300 m3 0.25 2.97
Besi Wiremesh T lapis Mó Kg 17.03 204.32
Frame Besi Siku L 30.30.2 Bh 4.00 48.00
Batu koral m3 0.02 0.19
Ijuk m3 0.01 0.10
pasir Urug m3 0.01 0.10
Pondasi rolag m2 1.25 15.05
pasir Urug m3 0.02 0.27
Subtotal IV
Lubang Kontrol 12
Bekisting m2 0.69 8.33
Upah Beton Readymix K300 m3 0.03 0.33
MoteriaÍ Beton Readymix K300 m3 0.03 0.33
Besi Wiremesh T lapis Mó Kg 2.72 32.69
Frame Besi Siku L 30.30.2 Bh 4.00 48.00
4 CLUSTER PYRUS
A PEKERJAAN KANSTEEN
PY-A KE C kode E m 51.92 51.92
PY D 1-21 kode F m 72.26 72.26
5 CLUSTER BOULEVARD
A PEKERJAAN JALAN BETON
cluster boulevard 52
perapihan badan jalan m2 127.88 127.88
plastik cor m2 137.48 137.48
bekisting m2 170.51 170.51
beton m3 19.18 19.18
besi wiremesh
upah beton m3 19.18 19.18
material beton m3 19.18 19.18
besi dowel dia 16mm
limestone m3 20.802 20.802
B PEKERJAAN KANSTEEN
BLV-46-52 kode M m 95.52 95.52
BLV-40 DAN 42 kode N m 14.44 14.44
C PEKERJAAN PJU
blv-52 bh 1 1
D PEKERJAAN SALURAN
Galian Tanah m3 5.62 5.62
Urugan tanah kembali m3 1.48 1.48
BC 40 X 40 m 13.44 13.44
Lantai kerja Pasir Urug m3 0.38 0.38
Subtotal I
BAK Kontrol 1A 1
Bekisting m2 4.80 4.80
Upah Beton Readymix K300 m3 0.22 0.22
MoteriaÍ Beton Readymix K300 m3 0.25 0.25
Besi Wiremesh T lapis Mó Kg 17.03 17.03
Frame Besi Siku L 30.30.2 Bh 4.00 4.00
Batu koral m3 0.02 0.02
Ijuk m3 0.01 0.01
pasir Urug m3 0.01 0.01
Pondasi rolag m2 1.25 1.25
pasir Urug m3 0.02 0.02
Subtotal II
Lubang Kontrol
Bekisting m2 0.69 0.69
Upah Beton Readymix K300 m3 0.03 0.03
MoteriaÍ Beton Readymix K300 m3 0.03 0.03
Besi Wiremesh T lapis Mó Kg 2.72 2.72
Frame Besi Siku L 30.30.2 Bh 4.00 4.00
Subtotal III