PROJECT : Radmanila Office

OWNER : Radmanila
LOCATION : Unit 11A Country Space Bldg., Buendia, Makati City
SUBJECT : Project Cost Estimates - tile on tile
DATE : March 20, 2023

Work Period: 30 working days


ITEM LABOR
DESCRIPTION QTY UNIT AMOUNT
NO. UNIT COST AMOUNT
II. DEMOLITION WORKS
2.1 Removal/stripping of wall paper 150.17 sqm - - -
2.2 Removal of CAT 6 wire and auxiliary moldings 1.00 lot - - -
2.3 Removal of amco box 2.00 pcs - - -
2.4 Removal of carpet and vinyl tiles 130.66 sqm - - -
2.5 Removal of Glass door 1.00 lot - - -
2.6 Removal of existing blue pipe and molding for acu drain 1.00 lot - - -
2.7 Removal of existing stainless drinking fountain 1.00 lot - - -
2.8 Removal of under cabinet at T&B 1.00 lot - - -
2.9 Removal of wooden baseboard 56.66 lm - - -
2.10 Demolition of pedestal of existing stainless water fountain 1.00 lot - - -
2.11 Removal of cabinet at pantry sink 1.00 lot - - -
2.12 Removal of all plumbing fixtures at two bathrooms 1.00 lot - - -
Sub-total for Demolition Works -
III. VARIOUS FIT-OUT WORKS
3.1 Ceiling and Wall Finishes
3.1.1 Replacement of damaged ceiling panels 9.00 pcs - - -
3.1.2 Single coating of ceiling panels 140.25 sqm - - -
3.1.3 Painting of walls 49.86 sqm - - -
3.1.4 Wall paper installation 41.62 sqm - -
3.1.5 Installation and painting of cork wall panel 1/2" 29.92 sqm - - -
3.1.6 Fabrication and painting of wall cladding/partition 6.51 sqm - - -
3.2 Repainting of louver, and T&B door and door jamb 18.45 sqm - - -
3.3 Replacement of frosted sticker 19.50 sqm - - -
3.4 Toilet and Bath Works -
3.4.1 wall tile installation - tile on tile procedure 45.85 sqm - -
3.4.2 floor tile installation - tile on tile procedure 9.48 sqm - -
3.4.3 countertop and marble baseboard - marble polish 1.00 lot - - -
3.4.4 Repainting of built-in cabinet under lav counter 2.00 lot - - -
3.4.5 Storage cabinet fabrication and installation 1.00 lot - - -
3.4.6 Plumbing fixtures installation at two T&B 1.00 lot - - -
3.5 Pantry Area -
3.5.1 Chipping of floor and wall for drain and waterline 1.00 lot - - -
3.5.2 Pipe laying for drain and waterline 1.00 lot - - -
3.5.3 Concrete restoration 1.00 lot - - -
3.5.4 Fabrication of pantry sink 1.00 lot - - -
3.5.5 Overhead Cabinet fabrication at pantry sink 1.00 lot - - -
Storage Cabinet Fabrication at the location of existing
3.5.6 1.00 lot - - -
drinking fountain
3.5.7 Stainless sink and faucet installation 1.00 pc - -
3.5.8 Grease Trap 10L / 4GPM 1.00 pc - - -
Sub-total for Various Fit-out Works -