HDPE DUCTS TESTING CHECKLIST

PROJECT LIGHTENING - Cable route layout plan & cross section - Mirfa (Zakum Cluster: 2x1GW Symmetrical Monopolar HVDC VSC
Project Name
Link)

Procurer Abu Dhabi National Oil Company (ADNOC) Engineer SNC LAVALIN

Sub-
Company Abu Dhabi Offshore Power Transmission Company Limited LLC ADSO LLC
Contractor
NDRC-
Contractor Samsung C&T Corporation and Jan De Nul Consortium International Foundation Group (IFG) LLC
Contractor

Checklist Title: Testing and Finalizing Pipe - HDD Works

Works Location: Mirfa Abu Dhabi

Status - Acceptable
SN Description of checking to be carried out Remarks
Yes No NA

1 Check the hdpe duct is properly installed

2 Check the duct is clean and open from both sides

3 Check the suitable sized mandrel with rope is ready to insert

4 Check the mandrel has been passed all through duct comfortably

5 Ensure the ducts are cleaned and sides are protected after test is perfomed

Remarks:

Accompanying document :

For Contractor
For Supervision Consulant (Engineer)
Quality Inspector Quality Engineer