You are on page 1of 3

Doc.

No: MYTZ-TW-VPWLD-790003
WELD REPAIR PROCEDURE Rev.No:A
Rev.Date:14/02/2012

TABLE OF CONTENT

1.0 PRUPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 DEFINITION

5.0 PROCEDURE

6.0 RESPONSIBILITIES

7.0 RECORDS

1.0 PURPOSE

Transwater API Sdn. Bhd. Confidential & Proprietary 1 of 3


Doc.No: MYTZ-TW-VPWLD-790003
WELD REPAIR PROCEDURE Rev.No:A
Rev.Date:14/02/2012

The purpose of this procedure develop is to ensure that weld repair are done in
prescribed manner and acceptable to project specification, code and standard applied
for Tapis EOR Rejuvenation project.

2.0 SCOPE

This procedure covers the weld repair of steel structural and piping welds during the
fabrication of GuE and TaF NAG Condensate Allocation Metering Skid for Tapis EOR
Rejuvenation Project.

3.0 REFERENCES

ASME B31.3 Process Piping


AWS D1.1 Structural Welding Code-Steel
MPDS 03-19-02 Upstream Piping Fabrication, Erection, Inspection, Testing,
and Cleaning
MPDS 29-03-02 Upstream Process Piping Welding and Inspection

4.0 DEFINITIONS

PROJECT Tapis EOR and Rejuvenation Project


CLIENT Exxon Mobil Exploration & Production (M) Inc. (EMEPMI)
CONTRACTOR Transwater API Sdn. Bhd. (TASB)
SUB-CONTRACTOR Piping Fabricator
NDT Non Destructive Testing

5.0 PROCEDURE

5.1 Any weld area does not meet the requirement for Visual inspection, Liquid
Penetrant testing, Magnetic particle testing, Radiographic Testing or
Ultrasonic Testing shall be repaired. The defective area may be ground or
excavated down to sound metal as required.
5.2 Liquid Penetrant testing or Magnetic particle testing shall be used to confirm that
the defective area are totally remove before re-welding take place. The welder
use for repair shall be qualified and approve by CLIENT. WPS use for repair
should be the same WPS use at the first instance unless otherwise specified.
5.3 After the repair has been completed the area shall be tested using the same
method of inspection and same NDT procedure used to locate the defective
area in the first instance.
5.4 Two repair attempts shall be allowed in any one defective area. The joint shall be
cut and preparing as new joint after two attempt repair was conducted.

Transwater API Sdn. Bhd. Confidential & Proprietary 2 of 3


Doc.No: MYTZ-TW-VPWLD-790003
WELD REPAIR PROCEDURE Rev.No:A
Rev.Date:14/02/2012

6.0 RESPONSIBILITIES

SUB-CONTRACTOR will be responsible for weld repair execution and monitoring by


CONTRACTOR to ensure it accordance this weld repair procedure and meet
applicable project specification, code and standard.

7.0 RECORDS

Any documentation generated during repair welding shall be form part of the record
and shall compile in appropriate section.