Construction of Qurayyah Combine Cycle Power Plant Project- C

DESCIPLINE: ELECTRICAL ITP NO.: 30621127-000-GIP-00037


INSPECTION & TEST PLAN FOR SITE SUBCON: REV. NO.: 005
DESCRIPTION: ELECTRICAL WORKS PAGE: 13 OF 15 RFI No.:

APPLICABLE INSPECTION LEVEL


REPORTING
STANDARD, BEMCO SEC
ACTIVITY ITEM NO. TEST AND INSPECTION ACTIVITY FORMAT/
SPECIFICATION OR
CHECKLIST CONST. QA/QC INITIAL SEC INITIAL
PROCEDURE

G BATTERY AND UPS/INVERTER SYSTEM

30621127-000-4QC-
1 BATTERY INSTALLATION PTS 7.14 H W W
58

30621127-000-4QC-
2 BATTERY CHARGER INSTALLATION PTS 10 & 11 H W W
58.1

30621127-000-4QC-
3 UPS & INVERTER INSTALLATION PTS 10 & 11 H W W
58.2

30621127-000-4QC-
4 BATTERY TEST / PRE-COMMISSIONING PTS 10 & 11 H H W
59

BATTERY CHARGER TEST/PRE- 30621127-000-4QC-


5 PTS 10 & 11 H H W
COMMISSIONING 60.1

INVERTER AND UPS ENERGIZATION 30621127-000-4QC-


6 PTS 10 & 11 H H W
TEST/PREC-COMMISSIONING 60.2

Prep : Masood A. Khan


LEGEND: R: REVIEW S: SURVEILLANCE W: WITNESS H: HOLD