Construction of Qurayyah Combine Cycle Power Plant Project- C

DESCIPLINE: ELECTRICAL ITP NO.: 30621127-000-GIP-00034


INSPECTION & TEST PLAN FOR SITE SUBCON: REV. NO.: 005
DESCRIPTION: ELECTRICAL WORKS PAGE: 9 OF 15 RFI No.:

APPLICABLE INSPECTION LEVEL


REPORTING
STANDARD, #REF! SEC
ACTIVITY ITEM NO. TEST AND INSPECTION ACTIVITY FORMAT/
SPECIFICATION OR
CHECKLIST CONST. QA/QC INITIAL SEC INITIAL
PROCEDURE

D GROUNDING AND LIGHTNING PROTECTION SYSTEM

BELOW GRADE CABLE LAYING AND 30621127-000-4QC-


1 PTS 7.21 H W W
ELECTRODE INSTALLATION AND BONDING 45

ABOVE GRADE CONNECTION AND GROUNDING 30621127-000-4QC-


2 H W W
INSTALLATION OF GROUNDING GENERAL NOTES 45.1

LIGHTNING PROTECTION SYSTEM 30621127-000-4QC-


3 PTS 7.22 H W W
INSTALLATION 46

30621127-000-4QC-
4 LIGHTNING ARRESTORS INSTALLATION PTS 7.22 H W W
46

30621127-000-4QC-
5 GROUND GRID EARTH RESISTANCE TEST IEEE 81 H H W
47

LIGHTNING ARRESTORS TEST / 30621127-000-4QC-


6 IEEE 81 H H W
COMMISSIONING 47

Prep : Masood A. Khan


LEGEND: R: REVIEW S: SURVEILLANCE W: WITNESS H: HOLD