ACTIVITY ITEM NO. TEST AND INSPECTION ACTIVITY FORMAT/
SPECIFICATION OR
CHECKLIST CONST. QA/QC INITIAL SEC INITIAL
PROCEDURE

E GENERATOR EXCITATION SYSTEM, GCB & IPB PANELS

GENERATOR PROTECTION PANELS 30621127-000-4QC-


10 PTS 10 & 11 H H W
INSTALLATION 51.5

GENERATOR PROTECTION PANELS TEST / 30621127-000-4QC-


11 PTS 10 & 11 H W W
PRE-COMMISSIONING 51.6

GENERATOR PROTECTION PANELS 30621127-000-4QC-


12 PTS 7.5 H W W
ENERGIZATION 51.7

GENERATOR EXCITATION SYSTEM 30621127-000-4QC-


13 PTS 10 & 11 H H W
INSTALLATION 51.2

GENERATOR EXCITER SYSTEM TEST / PRE- 30621127-000-4QC-


14 PTS 10 & 11 H W W
COMMISSIONING 51.3

GENERATOR EXCITER SYSTEM 30621127-000-4QC-


15 PTS 10 & 11 H W W
ENERGIZATION 51.4

GENERATOR CIRCUIT BREAKER 30621127-000-4QC-


16 PTS 10 & 11 H W W
INSTALLATION 57.2

GENERATOR CIRCUIT BREAKER TEST / 30621127-000-4QC-


17 PTS 10 & 11 H W W
PRE-COMMISSIONING 57.3

IPB PRESSURISING PANEL & HEATER 30621127-000-4QC-


18 PTS 10 & 11 H H W
PANELS INSTALLATION 57.4

IPB PRESSURISING PANEL & HEATER 30621127-000-4QC-


19 PTS 10 & 11 H H W
PANELS TEST/PRE-COMMISSIONING 57.5

Prep : Masood A. Khan