Project: P a i n t i n g W o r k RISK ASSESSMENT

Location: ARC Middle East LLC FIX IT Ref No: 1146


PO No: 2000004708

Contractor: FIX IT Electromechanical Contr. Date: 28-01-2024

 Location of work: ARC Middle East LLC


 No of workers involved in site activities: 5 nos.

S.
Activity Hazards Control Measures Remarks
No.
1. Delivery, storage  Paint Cans & Thinners to be stored in steel Site Engineer/
and Handling of containers. Foreman
Paint spillage due to
Paint and  Containers will be positioned away from any
accidental leakage,
Thinner. vehicle traffic to avoid damage from
storing damaged
collision.
container, wrong
 Hand gloves shall be worn when handling
handling of material
paint cans to avoid cuts to the hands.
 Task to be carried out with proper
supervision.
2. Paint Application  No Hot work shall be permitted in the vicinity Site Engineer/
of paint or thinner storage areas. Foreman
 All Combustible/flammable materials should be
Fire and Explosion due removed from the work area.
to Flammable  Suitable fire extinguishers and fire protection
substances systems shall be provided in the work area.
 Keep minimum quantity of flammable
materials at the work place.
 Adequate training to be given to the workforce
regarding fire risks.
3. Paint application  Adequate ventilation shall be provided on
the work place to extract fumes and blow
fresh air. Site Engineer/
Respiratory problems  Adequate training / TBT shall be given to Foreman
workers regarding painting works.
 Ensure usage of suitable PPEs such as
respiratory mask, hand gloves, safety
glasses.
Spillage and walkways  polythene sheet shall be provided to avoid Site Engineer/
not clear or poor paint thinner spillage on the ground. Foreman
housekeeping  Access routes shall be kept clear at all times.
 All spillages and waste materials shall be
disposed of and / or cleaned up as per EAD
requirements.
4. Working at  All personnel working 2 meters or above to Site Engineer/
Height and on wear Safety Harness and tied off to a suitable Foreman
Scaffoldings strong point.
Serious injuries or
 All ladders used to be in the appropriate angle
death to personnel
and secured properly.
falling from height if
 Only approved scaffoldings or working
not protected by platforms to be used.
handrails, guards or  If mobile platforms used, ensure wheels are
fall protection locked when persons working on top.
 If mobile platforms are moved to different
locations, ensure personnel are removed before
moving scaffolding to different location.
Falling objects from  Ensure area is barricaded were work is Site Engineer/
height/scaffoldings. conducted at height. Foreman
 Install appropriate warning signs "Falling
Personnel working objects"
under or nearby can  No materials to be stored on top of scaffolds
sustain serious  Ensure all scaffolds have toe boards installed to
injuries from falling prevent tools and materials from falling.
objects  Any tools to be used on top of scaffoldings shall
be secured to prevent falling.

Yours Sincerely,

Engr. Mehedi Hasan


FIX IT GROUP
Mobile: +971509500818