You are on page 1of 19

Project N° Unit Document Code Serial N° Rev.

Page
2342 AA00 JSM 202 0 1/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for

DETAILED HAZOP/SIL REVIEW


PROCEDURE
FOR EPC PHASE
which it is specifically furnished or outside the extent of the agreed upon right of use.

0 10-10-2010 ISSUE FOR FEED C. SCALA C. PASCALI C. PAESANI / O. LOIACONO

A 20-09-2010 ISSUE FOR REVIEW C. SCALA C. PASCALI C. PAESANI / O. LOIACONO

REV. DATE STATUS WRITTEN BY CHECKED BY APPROV./AUTHOR. BY


(name & visa) (name & visa) (name & visa)
DOCUMENT REVISIONS

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 2/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

INDEX

1. INTRODUCTION, OBJECTIVE and SCOPE ...........................................................................3


1.1. Implementation of FEED HAZOP Review Recommendations.....................................3
1.2. EPC Detailed HAZOP/SIL Review...................................................................................4
1.2.1. Management of Changes.........................................................................................4
2. Study Objectives ....................................................................................................................5
2.1. Reference Data and Documents ....................................................................................6
2.2. Acronyms.........................................................................................................................6
2.3. Definitions .......................................................................................................................6
3. TEAM ORGANIZATION ...........................................................................................................8
4. HAZOP AND SIL REVIEW METHODOLOGY..........................................................................9
4.1. Guidelines for HAZOP and SIL Methodology ................................................................9
4.1.1. Consequences ...........................................................................................................9
4.1.2. Safeguards ................................................................................................................9
4.1.3. HAZOP Recommendations ........................................................................................9
4.1.4. SIF Identification ......................................................................................................10
4.1.5. SIL Classification......................................................................................................10

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 3/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

1. INTRODUCTION, OBJECTIVE and SCOPE

This document covers the procedure for the combined Hazard and Operability study
and the Safety Integrity Level (SIL) determination for the Safety Instrumented
Functions (SIFs) that shall be undertaken by the EPC Contractor (here after referred
as “Contractor”) during the Engineering Procurement Construction (EPC) phase for the
Karbala Refinery Project.

1.1. Implementation of FEED HAZOP Review Recommendations


During the FEED Phase of the Project a HAZOP Review has been developed.
The HAZOP Reports for all the Units analyzed are provided for each unit in the
relevant part of EPC Bid Package.

The HAZOP Analysis, developed during the FEED phase, identified a number of
recommendations aimed to increase the safety and operability of the systems. Two
levels of recommendations were considered:
 First level: Recommendations closed during the FEED phase of the Project and
relevant actions implemented in the Project FEED Documentation.
 Second level: Recommendations to be closed during the EPC phase. It is
responsibility of the Contractor to ensure proper follow-up and closure of all
these Recommendations.

The list of Recommendations assigned to Contractor is given for each unit in the
relevant part of ITB Package. Refer to “FEED HAZOP Review Report” - (Doc. 2234-
unit/section code-ML-210), and “FEED HAZOP Review Recommendation Close Out
Report (Doc. 2234-unit/section code-ML-220).

As part of the Flare Study developed during the FEED Stage of Karbala Project a
number of additional requirements were identified aimed to reduce the relief loads to
the flare. These shall be considered during the Detailed HAZOP / SIL Review during
the EPC phase.

The preliminary design of the Karbala Refinery flare system, as described in the Flare
Study Report from the FEED phase will be reviewed, optimized and modified as
needed by Contractor. As a result of this, Contractor:
- will have to confirm the need for all Safety Instrumented Functions which have
been already foreseen during the FEED phase as preliminary flare mitigation
measures.
- will add new Safety Instrumented Function as required to reduce flare loads further
more, if needed for flare design optimisation.
- will give the appropriate SIL level requirement to each Safety Instrumented
Function.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 4/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

1.2. EPC Detailed HAZOP/SIL Review


During the development of EPC, a full Detailed HAZOP/SIL Review shall be developed
for the all systems and units including both those units already analyzed during FEED
(process units) and those which were not analyzed in the previous phase:

- Utilities and Offsite


- Packages
- Machineries
- Interconnecting

The Review shall be developed when information on Major Packages and Machineries,
Chemical Injection Systems, Operating/Start-up Procedures are available, but early
enough to be properly implemented during detailed engineering.

1.2.1. Management of Changes


Contractor shall implement a system to monitor changes on P&IDs in order to identify
Major Process Changes on which additional HAZOP and SIL Session shall be
undertaken.

The Management of Changes shall cover all P&IDs issues after the Detailed HAZOP
and SIL Review.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 5/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

2. Study Objectives

The objective of the HAZOP study is to identify hazards and operability problems that
may be encountered during the operation of the facility such that suitable mitigation
measures can be incorporated in the design and/or in the operating procedures.

During the HAZOP review sessions, issues of concern will be defined and party
responsible for resolution will be identified, but no solution will be proposed.
Resolutions for identified issues will be solved after the completion of the HAZOP
review by the responsible parties and reported in a separate document (HAZOP
Follow-up Report).

HAZOP Review cannot be intended as a review of project design bases and operating
philosophies, since these must be defined before the HAZOP Review is carried out.

The objective of the SIL study is to determine the Safety Instrumented System (SIS)
required to prevent and to mitigate hazardous events and the Safety Integrity Level
(SIL) that the SIS has to be designed, to prevent the occurrence of hazardous event or
in some scenarios, to mitigate the consequences from such hazardous event.

The SIL indicates the minimum level of reliability in terms of Probability of Failure on
Demand (PFD) required for a SIF. Such failure probabilities are:

SIL PFD
 10 to  10
-2 -1
1
 10 to  10
-3 -2
2
 10 to  10
-4 -3
3
 10 to  10
-5 -4
4

The request of a SIL 4 has to be considered as extremely rare in the process industry.
If a classification leads to SIL 4, further study should be performed, aimed at
rearrangement of the section or installation under analysis (development of process
alternatives to eliminate the need for a SIL 4). Each SIF comprises of an initiating
element (process sensor), a logic solver (PLC/DCS), a final element (shutdown valve,
machinery).

Safety Instrumented Function shall be implemented according to the SIL level


architecture according to project specifications that will be developed.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 6/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

2.1. Reference Data and Documents

The following documentation shall be available during the Detail HAZOP/SIL Review:

 Piping & Instrument Diagrams (P&IDs)


 Process and Utility Flow Diagrams (PFDs and UFDs)
 Heat & Material Balance
 Material Selection Diagrams
 Cause and Effect Diagrams
 Interlock Process Description
 Equipment Data Sheets
 Relief Valve applicable Emergency Scenarios
 Project Basic Design Data
 Unit Basis of Design
 Plot Plan

2.2. Acronyms

HAZOP Hazard and Operability


FEED Front End Engineering Design
SIL Safety Integrity Level
SIF Safety Instrumented Function
SIS Safety Instrumented System
IPL Independent Protection Layer
PFD Probability of Failure on Demand
PLC Program Logic Solver
DCS Distributed Control System

2.3. Definitions

SIF
Safety function with a specified safety integrity level which is necessary to achieve
functional safety and which can be either safety instrumented protection function.

SIL
Discrete level (one out of four) for specifying the safety integrity requirements of the
safety instrumented functions to be allocated in safety instrumented systems. Safety
integrity level 4 has the highest level of safety integrity; safety integrity level 1 has the
lowest.

SIS
Instrumented system used to implement one or more safety instrumented functions.

IPL
Independent protection layer is applied to a safeguard which is capable of preventing a
scenario from proceeding to its undesired consequence independent of the initiating
event or the action of any other layer of protection associated with the scenario. There
is a slight distinction however, in IEC 61511, between the terms ‘protection layer’ and

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 7/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

‘independent protection layer’. Although both need to meet the criteria mentioned
above, a safeguard may qualify as a ‘Protection layer’, if at least a factor of 10 risk
reduction can be achieved while to qualify as an ‘independent protection layer’, a
higher degree of reliability is required (i.e. reduces the identified risk by a minimum of
100 fold). While this study report has used the term ‘IPL’ for all protection layers, a
100-fold risk reduction is applied only to those protection layers such as PSVs which
meet the criteria of IPL as defined in IEC 61511.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 8/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

3. TEAM ORGANIZATION

The HAZOP and SIL Review shall be lead by a Third Party independent from the
Project.

The HAZOP and SIL Review Team shall include as a minimum:


 HAZOP Team Leader
 HAZOP Scribe
 Contractor Process representative
 Licensor Representative for Licensed Units
 COMPANY Process representatives
 COMPANY Operation representatives
 Contractor Specialists (Start-Up, Machinery and Packages, Instrument …) when
required

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 9/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

4. HAZOP AND SIL REVIEW METHODOLOGY

The HAZOP and SIL Review shall cover all the P&IDs. The Team Leader shall ensure
that the technique is systematically applied to all parts of a system such that safety and
operability problems on the complete system are identified.

Contractor shall, on the basis of the below guidelines:

- Develop a detailed procedure for the HAZOP and SIL Review


- Identify the systems for which a conventional HAZOP methodology is not really
appropriate and develop a specific safety analysis methodology to review these
systems during the EPC phase
- Produce the HAZOP and SIL Report with the minimum contents shown in
Appendix C

4.1. Guidelines for HAZOP and SIL Methodology

The HAZOP technique applies a combination of a Parameter and Guide Word to


generate a Deviation from design intent. The Causes and Consequences of each
deviation are identified. Safeguards that can prevent or mitigate the hazard, and which
are already provided in the design, are listed.

A detailed list of guide words to be used for the various HAZOP reviews of the EPC
phase is attached in Appendix B.

4.1.1. Consequences

The potential consequences of each deviation will be discussed and assessed within
the limits of the information available and the expertise of the team. The potential
consequence threats will be assessed without considering operator or instrument
intervention or any mitigation or safeguards. Consequences will focus on possible
major effects in terms of personal safety, environment and production/equipment loss.

4.1.2. Safeguards

The team will identify safeguards that are effective in preventing or controlling the
hazards. The safeguards can be classified as Independent Protection Layers (IPLs)
and non-IPLs. An IPL is a device, system or action that is capable of preventing a
scenario from proceeding to its undesired consequence independent of the initiating
event or the action of any other layer of protection associated with the scenario. An IPL
may also include a Safety Instrumented System (SIS). Appendix A shows the rule
sets for IPLs.

4.1.3. HAZOP Recommendations

The team will provide recommendations if the existing protective measures are found
to be inadequate. Actions will be recommended to eliminate or mitigate any residual
hazard that is considered significant.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 10/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

The recommendation may take the form of design changes (e.g. addition of an alarm
or increase the design temperature) or request for further clarification on design basis.

4.1.4. SIF Identification

A SIF consists of one or more initiators, the logic solver and the final elements. The
initiators are the sensors that detect one or more initiating events or the hazardous
situation. The final elements are all the actuators that are required to bring the process
to a safe state to avert the hazardous event.
The final element(s) of the SIF will be chosen as those which directly meet their design
intent. Thus, only one or two final elements will be usually defined for any function, and
where more than one is selected, a success criterion will be defined for these final
elements. The other elements acted upon by the initiators will be left unclassified (they
will however, be retained for implementation in the ESD system).

4.1.5. SIL Classification

SIL Classification will assign a discrete level (SIL 1, SIL 2, etc.) to every SIF identified.

According to guidelines provided in IEC-61511, both semi-qualitative (risk graphs) or


quantitative methods (LOPA analysis) may be applied for SIL determination.

The following aspects shall be investigated for SIL assignment:

 SAFETY: personnel injury;


 ECONOMY: equipment damage and loss of production;
 ENVIRONMENT: environmental damage.

All consequences shall be classified and the most stringent SIL shall be selected for
that function. If the demand has different causes, the consequences of failure on
demand will usually be different as well, requiring a classification for all causes and
consequences.

For each aspect, the following will be considered for the analysis:
 Severity Levels
 Frequency of Demand
 Safeguards

Severity Levels

Severity Levels will be selected in accordance to the consequence identified in the review
and categorised in personal safety (S), environmental (E) and production/equipment loss
(P). An example of severity categorization is shown in Table 3.1.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 11/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

Table 4.1 Hazard severity level in terms of personal safety, environment and
production/equipment loss
Hazard Severity Levels

Level Severity
4 - Catastrophic S4: Several deaths or very many seriously injured.

E4: Large scale destruction of the soil, groundwater, water


system, flora or fauna outside the plant area. Permanent
effects.

P4: Catastrophic damage to equipment or very long interruption


of production. Negative international or domestic media
event.
3 - Major S3: Death of one person or several seriously injured.
Permanent disability to work. Permanent serious defect.
Significant exposure to toxicant or carcinogen.

E3: Large scale pollution of the soil, groundwater, water


system, flora or fauna at the plant area. Serious but
amendable or recoverable damage outside the plant
area.

P3: Very serious damage to expensive equipment or long term


shut down. Negative publicity in local media.
2 - Serious S2: Long sick leave. Temporary disability for work. Serious
injury that may heal up. Exposure leading to symptoms.

E2: Local or minor pollution of the soil, groundwater or water


system. Emission to the water system exceeding the
terms of license.

P2: Serious operational upset or damage to equipment


1 - Minor S1: Short sick leave. Non permanent injury.

E1: Temporary emissions to air

P1: Minor operational upset or minor damage to equipment


0 – No Damage No consequences for Safety, Environment or Production

Severity for safety impacts will be determined based on the nature of fluid handled,
e.g., sweet gas, sour gas, flashing liquids, liquids handled above boiling point, hot
liquids, liquids near auto ignition temperature etc. The size of release and inventory
may also be considered. This may be further expanded during the course of the study
to ensure consistency in assigning severity levels.
Also the presence of personnel and escape possibility may be considered for safety
severity levels determination according to guidelines of IEC-61511.

Production loss estimates will be determined based on expected downtime and impact
on production. Approximate monetary impacts due to production loss will be provided
by COMPANY for each unit and for the plant as a whole. Impact on production will then
be determined by the team based on cascading effect on other units, availability of
standby equipment/ trains, availability of storage capacity etc.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 12/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

For equipment damage costs, equipment costs will be assumed based on the team’s
experience on approximate costs for similar size equipment. Where standby
equipment is provided, no production loss may apply but damage costs will be
considered.
In any case the main severity criteria to be considered are relative to safety or/and
environment. Production losses or cost criteria should only be used as complementary
information only.

Frequency of Demand

A demand on a SIF may be caused by instrument malfunction, operator error, etc.


After recording the consequences, the first question to be answered by the classification
team is: How often is the SIF activated?
The IEC 61511 describes the frequency of demand in both qualitative terms where a
discrete classification is made (low, moderate, high demand, see Table 1.1 in Appendix
A) or quantitative ones, depending on the methodology adopted.

Typical values for initiating events frequency is given in Appendix A.

Safeguards

During the frequency of demand analysis, the provision of other safeguards for the
specific scenario will be reviewed. For each safeguard identified (IPL), a risk reduction
factor will be determined. Guidelines for IPL determination are given in Appendix A.

Severity / frequencies classification and SIL assignment methodology shall be agreed


before the start of the SIL review to ensure consistency between the SIL levels and the
target risk levels to be achieved.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 13/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

APPENDIX A

RULE SETS FOR SIL CLASSIFICATION

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 14/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

Frequency of Initiating Events

Table 1.1 Frequency of initiating events

Frequency of Initiating Description


Events
W5 Very high (may occur about 3 times per
year)

W4 High (may occur about 1 time per year)

W3 Moderate (may occur about 1 time per 3


years)
W2 Low (may occur about 1 time per 10 years)

W1 Very low (may occur about 1 time per 30


years or over the plant life)

Table 1.2 Rule Set for Independent Protection Layers (IPLs)

Independent Protection Layer Risk Reduction


SIS - SIL 1 10
SIS - SIL 2 100
SIS - SIL 3 1000
BPCS, when independent of initiating event 10
Internal mechanical safety trips that are 10 to 100
(1)
independent of the SIS or BPCS
Operator response under high stress, 0
average training
Operator response to Alarms with 10
procedures, low stress, recognized event and
at least 5 minutes to respond.
(2)
Check Valves 0 or 10
Dikes when capable of mitigating the 100
initiating event. This is an IPL only for
environmental events.
Notes:
(1) This may be relevant to vendor packages. Risk reduction will depend on the
integrity of the system
(2) Credit for check valve will depend on pressure differential and impact of
contamination

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 15/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

Table 1.3 Rule Set for Initiating Events

Scenario Initiating Event Frequency of


Frequency Demand (W)
(per year)
Instrumentation
Control loop failure >1.E-01 W4
Controller failure 1E-01 W4
Shutdown valve spurious closure (Mean value 3.45E-2 W5
from Exida and Sintef). No values provided in
Total Charad Data Base
Rotating Equipment
Pump Failure Loss of Flow (OREDA, 7.9E-01 W2/ W3
conservatively W2). This value is also in
agreement with Total Charad Data Base
Positive Displacement Pump Trip (OREDA) 1.1E-00 W2/W1
Centrifugal Compressor Trip (OREDA) 2.1.E-00 W2/W1
Single Mechanical Pump Seal Leak 1.E-01 W4
Double Mechanical Pump Seal Leak with 1.E-02 W5/W4
announcement
Canned/Magnetic Drive Pump Leak 1.E-02 W5/W4
Heat Exch. tube leak 1.E-02 W5/W4
Human Errors
Operator Failure (if considered in the analysis)
-Under stress, emergency, action performed W1
more than once a quarter.
- Unstressed, action performed more than W3/W4
once a quarter.
- Under stress, emergency, action performed W3/W4
once/Qtr. or less
- Unstressed, action performed once/Qtr. or W2
less

For control failure involving a control valve whose failure position is opposite to that
which leads to a hazard, the likelihood may be assigned lower than suggested above,
based on the study team’s experience.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 16/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

APPENDIX B

TYPICAL HAZOP GUIDEWORDS/PARAMETERS

AND RELATED DEVIATIONS FOR CONTINUOS PROCESS

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 17/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

PARAMETERS GUIDEWORDS DEVIATIONS


More high flow
Less low flow
FLOW
None no flow
Reverse reverse flow
More high pressure
PRESSURE Less low pressure
None vacuum
More high temperature
TEMPERATURE Less low temperature
As well as cryogenic
More high level
LEVEL Less low level
None no level
More additional phase
Less loss of phase
Reverse change of state
STATE/ COMPOSITION
Part of off-spec composition
As well as contaminants
Other than corrosive concentration
More runway reaction
REACTION As well as side reaction
Other than explosion

UTILITY: power, air, steam,


Other than loss of …
nitrogen, cooling water
UNSTEADY OPERATION: startup,
As well as difficult …
shutdown, maintenance, sampling,
Other than hazardous …
drainage

CONTAINMENT Other than loss of containment


Part of incomplete documentation
DOCUMENTATION As well as unclear documentation
Other than incorrect documentation

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 18/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

APPENDIX C

HAZOP AND SIL REVIEW REPORT CONTENTS

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2342 AA00 JSM 202 0 19/19

KARBALA REFINERY FEED PROJECT


SCOP – IRAQ (Contract n° 2171)

The HAZOP and SIL Study Report shall include:

1) Main body of report


 Introduction and Scope of Work
 Executive Summary
 Study Approach
 Study Results
 Conclusions

2) Attachments

 DRAWING LIST
 NODE LIST
 ATTENDANCE LIST
 HAZOP/SIL WORKSHEETS
 HAZOP/SIL RECOMMENDATION CLOSE OUT FORM
 SIL CLASSIFICATION LIST
 HAZOP MASTER P&IDS

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68

You might also like