Company Name

Document Category

SPECIFICATION

Project Name :

LINE Project

Site Location :

Cilegon, Indonesia

Document Title :

SPECIFICATION FOR PILING WORK

Document No. :

LINE-000-CA-4-0012

Client’s Contract No. : Later


LEC’s Job No. : 15005

0 29-Dec-2021 For Construction T.Y. LEE T.S. KIM E.S. LEE


A 30-Nov-2021 For Approval Y.G. KIM T.S. KIM E.S. LEE
Rev Date Description Prepared Reviewed Approved
SPECIFICATION FOR Doc. No. : LINE-000-CA-4-0012
Rev. No. : 0
PILING WORK Page : 2 of 8

LIST OF REVISION DESCRIPTION

Rev.
Page Paragraph Description Remarks
No.

A - - First Issue

0 - - No changes are made.


SPECIFICATION FOR Doc. No. : LINE-000-CA-4-0012
Rev. No. : 0
PILING WORK Page : 3 of 8

TABLE OF CONTENTS

1 GENERAL............................................................................................................................... 4
1.1 Scope .........................................................................................................................................................4
1.2 Related Standards .....................................................................................................................................4

2 SUBMITTAL ............................................................................................................................ 4
2.1 Pile Driving Execution Procedure ..............................................................................................................4
2.2 Pile Driving Record ....................................................................................................................................4
2.3 Handling Method and Storing Method .......................................................................................................4

3 TYPE OF PILE ........................................................................................................................ 5

4 PILE DRIVING EXECUTION................................................................................................... 5


4.1 Preparation ................................................................................................................................................5
4.2 Pile Driving Operation ................................................................................................................................5
4.3 Welding Of Pile Splice................................................................................................................................6
4.4 Completion .................................................................................................................................................7

5 INSPECTION .......................................................................................................................... 7

6 EQUIPMENT ........................................................................................................................... 8

7 SAFETY REQUIREMENT ....................................................................................................... 8


7.1 Safety Matter..............................................................................................................................................8
SPECIFICATION FOR Doc. No. : LINE-000-CA-4-0012
Rev. No. : 0
PILING WORK Page : 4 of 8

1. GENERAL

1.1 Scope
(1) This construction specification covers general requirements for precast concrete piling work.
(2) Work not included: Pile cap work
(3) Other type of piles such as timber piles, cast in site concrete piles, composite piles, steel piles
and etc. are not included in this specification
(4) The work shall consist of supplying all labor, materials, tools equipment, supervision,
transportation, temporary construction other items necessary for furnishing and installing piles as
shown on the design drawings

1.2 Related Standards


(1) Related Construction Specification: LINE-000-CA-4-0019, “Specification for Earth Work”
(2) Related Standards
The requirements contained in the latest editions of the following standards shall form a part of the
specifications, in the manner and to the extent indicated herein:
-ACI, JIS or ASTM
(3) Priority Of Requirements
In case of any discrepancy among the codes/standards, SPECIFIC DESIGN CONDITION, related
Engineering Specifications and this specification, the order of priority shall be as below;
1. SPECIFIC DESIGN CONDITION
2. This specification
3. Related Engineering Specifications
4. Codes and Standards

2. SUBMITTAL

2.1 Pile Driving Execution Procedure


The Contractor shall submit details of the pile driving execution procedure for the approval of LCI
Engineer before commencing work.

2.2 Pile Driving Record


The Contractor shall maintain a complete and accurate record of all driven piles in the tabular form
approved by the LCI Engineer and shall submit such reports daily. The LCI Engineer shall have the
right to access the reports for inspection without obligation from the Contractor.

2.3 Handling Method and Storing Method


The Contractor shall submit pile handling method, storing method and driving method to the LCI
Engineer for approval.
SPECIFICATION FOR Doc. No. : LINE-000-CA-4-0012
Rev. No. : 0
PILING WORK Page : 5 of 8

3. TYPE OF PILE

3.1 Many types of piles such as Steel pile, PC pile, PHC pile, RC pile, Micro pile, Steel “H” pile, Timber pile
and etc. are used for plant construction. Pile type shall be selected following LCI approval.

3.2 Pile Type, Allowable Pile Capacity and Driving Method shall be selected referring to Geotechnical
Report or relevant documents.

3.3 Piles of prestressed concrete pile (PC) and pretensioned spun high strength concrete pile (PHC) shall
be designed in strict accordance with ACI 543 and JIS A5335. Following sections 4 to 7 are
recommended practices for PC, PHC driven pile.

4. PILE DRIVING EXECUTION

4.1 Preparation
1) All equipment shall be inspected minimum 1 (one) week before start of the work. Crane shall be
certified by authorized department
2) All crew including supervisor shall be skilled and experienced with Piling Procedures and
Operations
3) Survey to determine coordinate/ location of driving points will be done to ensure conformance
with Piling Plan drawings and is subject to inspection. Contractor will perform an independent
general check and each pile location coordinate will be confirmed prior to driving on each
location. Different types of marking shall be applied to driving points to show different type of
piles to be driven by diameter and length
4) The pile materials are to be transported from the stock yard area to piling area by flatbed truck.
Crawler crane will then lift from truck and store for piling operation.
5) Hammer base or cushion block is to be provided and shall be replaced periodically. (Hydraulic
type of hammer shall be used, to minimize environmental impact)
6) Use 2 sets of optical device (including total station, theodolite, and waterpass) to check
verticality of pile prior to pile driving. This procedure also shall be carried out before welding
work for pile splicing. Position of the device should form an angle of between 80 to 100 degrees.
7) Lift the pile and align with the center of the pile hammer. Allow the pile to drop and rest on the
ground. Adjust leader to ensure that the pile stands vertically on the right position.
8) Each pile shall be clearly marked in paint with its number and its overall length. In addition,
each pile shall be marked at intervals of 500 mm to enable easy
determination of pile penetration. Where necessary, the intervals shall be reduced to 250 mm as
directed.
9) If required, initial boring on pile location should be carried out to avoid effect of vibration due to
piling driving.

4.2 Pile Driving Operation

Pile driving operation sequence is as:


1) Survey for alignment as per IFC drawing.
2) Site and Machinery Preparation ( Inspection area and Equipment ).
SPECIFICATION FOR Doc. No. : LINE-000-CA-4-0012
Rev. No. : 0
PILING WORK Page : 6 of 8

3) Lifting pile and Positioning pile on the driving point. Positioning shall be controlled by Theodolite,
or Total Station.
4) Drive the first pile segment.
5) Position second pile segment and align properly.
6) Check vertically of pile.
7) Fully welding joint plates.
8) Calendaring record shall be done prior to pile driving is finished. Refer to blow count analysis.
Refer to ACI 543 Design, Manufacture, and Installation of Concrete Piles.
9) Pile driving records are to be filled using formats agreed with the LCI Engineer.
10) Drive each pile continuously and without interruptions either to refusal or until
the required depth of penetration or driving resistance has been attained based
on driving criteria in the foundation drawings. Final tip elevation or blow count is subject to
inspection.
11) Cut top of spun pile with cutting machine to reach final Pile Cut Of (PCO) elevation.
12) The positional and verticality tolerances of vertical piles shall not exceed the following limits:

CUT OF LEVEL POSITIONAL


VERTICALITY TOLERANCE
TOLERANCE TOLERANCE

Vertical pile 10 mm 75 mm 10 to the Vertical

Rake piles 10 mm 75 mm 10 Or 2 % to the desired angle

The above limits shall also apply for piles installed in a single line. For pile group of three or
more piles not installed in a single line, the positional tolerance of the
individual pile in the group may exceed the above limits. However, the
positional tolerance of the center of gravity of the pile group shall be 50 mm. Any pile or pile
group with position and verticality deviating more than the above mentioned
limits must be reviewed and re-engineered regarding instructed and approved by
owner.
13) Plywood formwork underneath pile head treatment should be provided prior to
installation of reinforcement and pile head concrete pouring.

4.3 Welding Of Pile Splice

1) Pile joint shall be welded in accordance with the design drawings. Parts to be welded shall be
cleaned from rust, mud, and all other foreign matters. Type of welding shall be
separated into two parts.
-Steel Pipe Piles
Ends of pipe to be spliced shall be beveled. Back-up ring or alignment clips shall be used
to ensure alignment for welding. Splices shall be full penetration butt
welds with minimum two layer/passes. A maximum of two joint splices per pile is
allowed.
-PC Spun Piles
Splices shall be partial penetration butt welds. A minimum of two joint splices per pile is allowed.
SPECIFICATION FOR Doc. No. : LINE-000-CA-4-0012
Rev. No. : 0
PILING WORK Page : 7 of 8

Refer to vendor specification for welding thickness.


2) Splicing of piles shall be conducted by certified welder as required by Welding
Procedure Specification ( WPS ) in accordance with AWS D 1.1
3) Preparation of welding equipment.
4) Clean top of pile from mud, rust and other foreign matter by means of wire brush.
5) If a field splice is required, the top of pile shall be beveled with proper size beveling band, with
touch up grinding as required before welding field splice.
6) Welding shall be done based on approved welding procedures, wherein WPS should be
available prior to commencement of work.
7) Welding during heavy rain or strong wind is not permitted.
8) Before and after each welding work, the joint will be visually inspected and recorded on
inspection format.
9) Welding work for Steel Pipe Piles shall be inspected by visual inspection
(100 %) and tested Random 20 % by Penetrant Test, Penetrant Test shall be conducted by 3rd
party and shall have personal certification under ASNT TC1A.
10) Primary painting shall be applied by brush after welding splice is completed
and have been inspected.

4.4 Completion

1) On completion of installation of piles, the piles shall be cut-off to the required level as shown on
the drawings and to a tolerance of ±10 mm or otherwise as instructed. Where a pile has been
formed below the required cut-off level, it shall be built up
2) Keep area cleaned after ex piling works.
3) Ensure daily clean up of construction areas, remove backfilling material, and reinstallation of
safety barricades.
4) Contractor shall keep records of the installation of every pile and shall submit to owner within 24
hours of driving.

5. INSPECTION
Pile shall be made available for inspection before proceeding with the next work stage described in
Inspection and Test Plan (ITP) for piling work.

Sub-contractor Contractor LCI


Piling Work
a. Quality of pile materials M W and R SW or R
b. Pile load test M W and R H or R
c. Location, number and size of
M W and R R
pile
d. Sequence of piling M W and R R
e. Visual inspection of welding M W and R SW
f. Blow-count and tip elevation M W and R SW and R
g. Rebound for driven piling (test
piles and random for production M W and R SW and R
piles)
SPECIFICATION FOR Doc. No. : LINE-000-CA-4-0012
Rev. No. : 0
PILING WORK Page : 8 of 8

note:
M = Perform & Witness
W = Witness
R = Review
SW = Spot Witness
H = Hold point

PDA Test shall be performed according to applied specification on pile test locations as indicated on
drawing approved.

6. EQUIPMENT

Equipment shall be of adequate quantity and quality to be able to meet


safety, quality and schedule requirements.

7. SAFETY REQUIREMENT

All operation in connection with pile load testing shall be carried out in such a manner so as to
minimize, avoid or eliminate the exposure of people to hazards.

7.1 Safety Matter

1) Tool box talk shall be conducted before start the work.


2) Permit To Work Prior to CONTRACTOR HSE System on Daily Basis one day before
commencement of work.
3) JSA (Job safety Analysis) shall be made and socialize to the worker before start the work.
4) All workers shall provide and wear proper mandatory PPE (Personal Protective Equipment).
5) All the excavation area shall be installed sign or barricade.
6) All equipments and working tools must be in good condition and shall be inspected each day
before starting work.
7) All waste materials including waste concrete shall be disposed in a particular area and should
not contaminate ground water or ditch.