METHOD STATEMENT FOR PLUMBIMG WORKS

PROJECT: CONSTRUCTION OF A PROPOSED MULTI- LABORATORY BUILDING


CLIENT: COLLAGE OF SCIENCE
CONSULTANT: KNUST DEVELOPMENT OFFICE
CONTRACTOR: ASIB LIMITED PREPARED BY: 2749120
NO. ACTIVITY QUANTITY METHOD PLANT/MANUAL LABOUR DURATION

1. Laying Drainage 180m total 100mm diameter drain pipes laid in substructure Manual Plumber and 1 day
below ground in length at positions as specified in drawing. Also indicate site engineer
substructure places where sanitary appliance will be located

2. Duct space 1500x600mm Spaces to be left in concrete slabs for pipes to Manual Mason and 4 days
area at 3 pass through to the ground flow concrete
foreman

3. Placing of stack Stack pipes Stack pipes placed in ducts and passed through Manual Plumber 2 days
pipes and fresh 300mm total duct spaces provided from ground flow to top and site
water service length at each floor. And service pipes also passed through duct engineer
pipes duct space. spaces to storage cistern on roof slab
100mm total
length of
service pipes

4. Joining of 20m Branch pipes of sanitary appliances and Manual plumber 3 days
branch pipes to laboratory appliance connected to their various
stack stacks at the appropriate slopes specified without
appliances connected
5. Joining of 400m total Branch of distribution pipes from storage cistern Manual plumber 3 days
distribution length to various appliance locations
pipes

6. Excavation of 30m3 Excavate septic tank and manhole pit to required Backhoe Banksman 0.5 day
septic tank and size and depth and surplus soil used as filling to
manhole make-up levels in compound of structure.
(caterpillar Backhoe)

7. Construction of 1 Concrete mixer Mason and 7 days


septic tank concrete
foreman

Construct
septic tank according to design and specifications
(concrete by concrete mixer)

8. Excavation of 5m3 Excavate trench to required depth from building manual Laborers 1 day
trench for foul inspection chamber to septic tank, using pick and
drainage below shovel and soil used as backfill for the trench
ground

9. Connecting of 16m Pipes laid in trench at appropriate slope to septic Manual Plumber 1 day
drainage below tank
ground to septic
tank

10. Testing of 2 Connection tested using various method to check manual Site 0.5 day
connection for slope and water tightness engineer

11. Fixing of 213 Appliances, taps, value and other relevant Manual Plumber 3 days
fixtures accessories fixed at their appropriate positions
(appliances)
12. Water Water pumped to storage cistern and appliances Centrifugal pump Plumber 1
connection and tested to ensure proper operation of all fixtures and site
final testing engineer

1. 2763920 - Nigal Madebombe Samuel


2. 2751220- Vonique Serwaa Amankwa
3. 2752120 - Frederick Appiah
4. 2750820– Akrong Kofi Eleagbe
5. 2756620 - Emmanuel Kofi Kabutey
6. 2748820 -Abel Peter
7. 2759320 -- Opoku Tufour Jonas
8. 2749120 - Abubakar Abdul-Rauf
9. 2754920 - Dadzie Desmond Senior
10. 2762420 - Sumaila Abdul Wahab
11. 2752320-- Asemsro Godwin
12. 2752720 Albert kofi Avornyoh
13. 2756420 — Tracy Hagan

You might also like