ESTIMATION OF R.C.

C SLAB CULVET
Item no Description No Length(m) Breadth(m) Height(m) Quantity Remark
1 Eathwork excavation
Abutment 2 5.1 0.7 0.6 4.284 L= 4.8+0.15+0.15=5.1M
Wing wall 4 1.2 0.7 0.6 2.016 L=1.2
Total 6.3
2 Cement concreting
Abutment 2 5.1 0.7 0.3 2.142 L=4.8+0.15+0.15=5.1
Wing wall 4 1.2 0.7 0.3 1.008 L=1.2
Total 3.15
First class
3
brickwork 1:4
Cement mortar
Abutment 2 4.8 0.4 1.5 5.76
wing wall 4 1.2 0.4 1.5 2.88
Parapet up to kerb 2 4.7 0.4 0.3 1.128 L=4.9-0.2=4.7
parapet up to curved 2 4.7 0.3 0.5 1.41 L=4.9-0.2=4.7
coping 2 4.9 0.4 0.1 0.392
Total 11.57
Deduction for
2 4.8 0.3 0.2 0.576
bearing slab
Total 10.994
4 Slab in 1:2:4 1 4.8 2.1 0.2 2.016 B=1.5+0.3+0.3=2.1
NO =4.8/0.3+1=17
Bar bending
5 17 2.38 40.46 L=2.1-2sidecover+2 hook
sheduing main bar
L=2.1-2×0.04+2×9×0.02=2.×0.42
no=4.8/0.3=16 L=2×0.42d
Alternative bendup
16 2.4 38.4 L=2×0.42×0.02=0.016
bar
L=2.38+0.016=2.396
D2/162×L=202/162×78.796=
Total 78.86
194.55Kg=1.94quintal
Distribution bar
L=4.8-0.08+18d
Bottom bar 9 4.9 44.1
L=4.8+0.08+18+0.01=4.9
D2/162×L=102/162×63.7=
top bar 4 4.9 19.6
39.32Kg=0.39quintal
Total 63.7
6 Wearing coat 2 4 2.3 0.1 1.84 B=1.5+0.4+0.4=2.3
Cement painting
7
work
face wall outer side
face work excluding
2 4.7 2.1 19.74 L=4.9-0.2=4.7 H=0.1+1.3+0.7=2.1
coping
inner side wall 2 4.7 0.8 7.52 H=0.1+0.2+0.5=0.8
Face wall coping 2 4.9 0.7 6.86 B=0.4+0.1+0.1+0.1=0.7
side parapet wall
4 0.4 0.2 0.32
upto kerb
side parapet wall
4 0.5 0.4 0.8
above kerb
coping side wall 4 0.4 0.2 0.32
Total 35.56
Deducting rectangle
2 1.5 1.3 3.9
block
Triangle block 2 Area=1/2×1.30×1.30 1.69
Total of
5.59
deduction
Net Total 29.97 35.56-5.59=29.97