Al Tasnim Handrails Fabrication & Painting Progress

Start Date: 3/28/2023 Status on : 30-Mar-23


JO No 2277 SCOPE FABRICATION Blasting & Painting Activity %
Completion Dispatch Remarks
No of No of Running Weight Fit Up Welidng & Visual Painting
S.No Priority ATM WO No
Dwgs Handrails Meter (MT) 30% 40% 30% 100%
Welding RFI Planned for
1 P1 DWO-878 9 10 53.065 0.855 10.0 10.0 0.0 30.0% 0.00 02.04.2023 @11.00 am

2 P2 DWO-879 24 42 210.084 3.373 12.0 0.0 0.0 0.0% 0.00 Materials required
3 P3 DWO-880 7 11 61.105 0.977 0.0 0.0 0.0 0.0% 0.00 balance10mm
Plate,Elbow 1x1/4
4 P4 DWO-881 43 52 263.192 4.252 0.0 0.0 0.0 0.0% 0.00

Grand Total 83 115 587.446 9.457


Inspection Stages :
1 After Welding - RFI
2 After Painting - RFI (Final Inspection)
NDT : Not in BG Scope

Snap of Fitup with 100% Safety Snap of Welding with 100% Safety Snap of QC Inspection with 100% Safety

Snap of Painting with 100% Safety Other Snap with 100% Safety